Information based on query as of Friday, July 19, 2024.
Permit Information
Permit NumberBLD96-02597
StatusExpired
Name FACILITIES & OPERATIONS SHED
Site Address 400 FORT
Project NameSCHOOL
Customer Number 
ePlanReviewNo
Description
TO CONSTRUCT A 5200 SQ. FT., TYPE V-N OPEN PARKING GARAGE FOR LARGE VEHICAL EQUIPMENT. CONSTUCTION WILL BE WOOD STUDS WITH METAL SIDING AND TJI ROOF FRAME AND CONCRETE SLAB AND FOUNDATION. A PORTION OF THE SOUTH WALL WHICH IS LESS THAN 20 FEET FROM THE TECHNOLOGY BUILDING SHALL BE A ONE-HOUR ASSEMBLY. ALL WORK IS PER APPROVED PLANS & ATTACHEMNTS, PC#549-96. 2-4-97- This project has been modified by adding an additional 1116 sq. ft. of storage garage to the east end of the building. Total sq. footage is now 6316 sq. ft. Additional fees are due. MO
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes7/14/1998 7/22/1998
INSP - Final11/20/199711/21/199711/21/1997AFAIL
Details
signatures needed
Receive PAYMENT IN FULL  11/13/1997
FEE REVIEW-NOTES  10/6/1997 FEES
additional fees due from additional elect. work..3500.00 value. fees due of 41.49 lh
(F) Reprint permit  10/6/1997
INSP - Conference8/25/19978/25/19978/25/1997 PASS
Details
/ / 333 - talked to Gus about finals
INSP - Conference8/21/19978/21/19978/21/1997APASS
Details
08/21/97 333 - 11am remind them of unpaid fee met with Gus
INSP - Conference8/19/19978/20/19978/20/1997ACANC
Details
change to tomorrow
INSP - Conference8/1/19978/4/19978/4/1997PPASS
Details
08/04/97 333 - AT 1 P.M. AS PER YOU talked about 1 hr walls
INSP - Framing/Rough-in7/11/19977/11/19977/11/1997PPART
Details
07/11/97 333 - partial rough-in
INSP - Framing/Rough-in6/30/19976/30/19976/30/1997PNR
Details
06/30/97 333 - not completly framed
Telephone call  2/18/1997 '
fee's due
Issue PAID IN FULL permit  2/18/1997
Plan assigned to (M_O)1/29/1997 2/4/1997 PASS
02/04/97 10:06:33 M_O - this action updated by action script from <<>> in Case No. BLD96-2597
Print Occupancy Form  2/4/1997
Inspection Record Card- Bld  2/4/1997
PLANS/APPL TAKEN TO FRONT DESK  2/4/1997 PASS
plan for additional 400 sq. ft. to already approved plans this permit. MO.
Print Pending Permit.LaserJet4  2/4/1997 PASS
PLAN FOR ADDITIONAL 400 SQ. FT. TO ALREADY APPROVED PLANS THIS PERMIT. KMM MO
Telephone call  2/4/1997
called left message on davids machine left dollar amount
Plan Reviewer's activity  1/31/1997 PASS
ADDED 1116 FT. TO EAST END OF BUILDING. EAST WALL IS ONE-HOUR FIREE RATED. PROPERTY LINE BETWEEN BUILDINGS IS SET AT 14 FEET FROM NEW STORAGE BUILDING. MO
Routing - PUBLIC WORKS1/23/1997 1/28/1997 PASS
RESUBMITTED PLANS 1-23-97
Plan routing begun/NEW & ADDTN  1/23/1997 PASS
PLAN RESUBMITTALS READY FOR ROUTING PER MIKE O.
Routing - PLANNING1/23/1997 1/23/1997 PASS
RESUBMITTED PLANS ROUTING TO PLANNING PER MIKE O. KMM 1-23-97 Approved by GRH. X-ref: Zoning Certificate @ 400 Fort.
Application received  1/23/1997 PASS
RESUBMITTALS RECEIVED
Received Certificate of Value  1/23/1997 PASS
RECEIVED NEW CERT. OF VALUE PER MIKE O.
Plan resubmittals received  1/23/1997 PASS
STAMPED IN FOR ROUTING PER MIKE O.
INSP - Foundation12/30/199612/30/199612/30/1996PPASS
DetailsWes Worcester
special insp on site
INSP - Foundation12/30/199612/30/199612/30/1996PNR
DetailsWes Worcester
90 day tracking............. 9/27/199612/26/1996
INSP - Footings12/24/199612/24/199612/24/1996PNR
Details
12/24/96 333 - gate locked
INSP - Footings12/18/199612/18/199612/18/1996PPART
DetailsWes Worcester
that that was in place was ok....ck back later
(F) Reprint permit  12/13/1996
Issue PAID IN FULL permit  12/12/1996
Telephone call  12/3/1996
TOLD HEATHER AT SCHOOL DISTRICT PERMIT NEEDS TO BE PICKED UP
Telephone call  11/8/1996
LEFT MESSAGE ON CHUCKS ANSWERING MACHINE GAVE DOLLAR AMOUNT
Print Occupancy Form  11/8/1996
Inspection Record Card- Bld  11/8/1996
Print Occupancy Form  11/8/1996
Plan assigned to (M_O)10/21/1996 11/7/1996 PASS
Corrections mailed and faxed to architect and also discussed correction items with Boise School District Facilities Administrator 11-01-96. MO
Routing - PLAN CHECK11/5/1996 11/7/1996 PASS
PLANS/APPL TAKEN TO FRONT DESK  11/7/1996 PASS
Print Pending Permit.LaserJet4  11/7/1996 PASS
Plan resubmittals received  11/6/1996 PEND
Routing - FIRE11/1/1996 11/5/1996 PASS
Plan resubmittals requested  11/1/1996 FAIL
Routing - PUBLIC WORKS10/22/1996 10/23/1996 PASS
Routing - PUBLIC WORKS10/15/1996 10/18/1996 FAIL
REQUIRES DRIANAGE PLAN. 10-18-96. LMH.
Routing - PLANNING10/11/1996 10/14/1996 PASS
X-ref: ZC @ 400 Fort. Approved by GRH.
Routing Off Site - A.C.H.D10/1/1996 10/11/1996 PASS
CONTACTED DAVID RUBY AT ###-#### TO TAKE PLANS OUT TO ACHD CAME BACK ON 10-11-96.
Plan routing begun/NEW & ADDTN  10/1/1996 PASS
Received Certificate of Value  10/1/1996 PASS
Gay Receipt For Partial Pay  9/27/1996
Recd Pcfee & Taken To Pln CK  9/27/1996
Application received  9/27/1996
Routing - PLAN CHECK1/29/1997  
RESUBMITTED PLANS