CHANGE STATUS TO (D) | | | 3/26/1997 | | PASS |
|
|
|
|
CHANGE STATUS TO (D) | | | 3/26/1997 | | PASS |
|
|
|
|
INSP - Final | 3/13/1997 | 3/13/1997 | 3/12/1997 | P | PASS |
|
|
|
03/13/97 333 - FNL -OK FINAL
|
INSP - Letter of compliance | 3/12/1997 | 3/12/1997 | 3/12/1997 | | PASS |
|
|
|
/ / 333 - letter #13646
|
INSP - Letter of compliance | 3/12/1997 | 3/12/1997 | 3/12/1997 | | PASS |
|
|
|
/ / 333 - letter #13646
|
INSP - Framing/Rough-in | 3/11/1997 | 3/12/1997 | 3/11/1997 | P | FAIL |
|
|
|
03/12/97 333 - OTH-OTHER AGENCIES NOT APPROVED.
|
INSP - Energy code compliance | 12/11/1996 | 12/11/1996 | 12/11/1996 | P | PASS |
|
|
|
12/11/96 333 - INSL-OK INSULATION-ENERGY CODE
|
INSP - Framing/Rough-in | 12/10/1996 | 12/10/1996 | 12/10/1996 | P | CANC |
Wes Worcester
|
|
|
given to Kim
|
INSP - Framing/Rough-in | 12/10/1996 | 12/10/1996 | 12/10/1996 | | FAIL |
|
|
|
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED fire block at stairs required nailing of hangars per mfg spec required and engineering of overbored st south wall upatairs 7
|
INSP - Framing/Rough-in | 12/6/1996 | 12/6/1996 | 12/6/1996 | P | NR |
Jim Storey
|
|
|
12/06/96 301 - OTH-OTHER AGENCIES NOT APPROVED mech not ready for struc. insp..
|
INSP - Footings | 10/22/1996 | 10/23/1996 | 10/23/1996 | P | PASS |
|
|
|
10/23/96 400 - setbacks seem ok
|
Issue PAID IN FULL permit | | | 10/18/1996 | | |
|
|
|
|
Telephone call | | | 10/17/1996 | | |
|
|
|
TALKED TO JONIE LET HER KNOW PLANS ARE READY
|
Inspection Record Card- Bld | | | 10/17/1996 | | |
|
|
|
|
Plan assigned to (340) | 10/7/1996 | | 10/16/1996 | | PASS |
|
|
|
PLAN CHECK #759 10/16/96 16:09:07 340 - this action updated by action script from <<>> in Case No. BLD96-2648
|
Telephone call | | | 10/16/1996 | | PASS |
|
|
|
called joe w/ oei, informed him eng'g req'd at frame insp....permit is issued
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/16/1996 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/16/1996 | | PASS |
|
|
|
|
Plan assigned to (DJO) | 10/2/1996 | | 10/7/1996 | | PEND |
Dan Overy
|
|
|
|
Routing - FRONT DESK | 10/4/1996 | | 10/4/1996 | | PEND |
|
|
|
SENT TO PLAN CHECK
|
Routing - PLANNING | 10/3/1996 | | 10/4/1996 | | PASS |
|
|
|
Approved by RLB.
|
Routing - PUBLIC WORKS | 10/2/1996 | | 10/3/1996 | | PASS |
|
|
|
PASSED BY BKB
|
Application received | | | 10/2/1996 | | |
|
|
|
|
Routing - PLAN CHECK | 10/4/1996 | | | | PEND |
|
|
|
|