Case Summary (BLD) | | | 2/29/2008 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/30/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 1/24/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/22/2008 | | DONE |
|
|
|
|
Letter of compliance | | | 10/25/1999 | | DONE |
|
|
|
Letter of Compliance #18162 issued 10-25-99.
|
BLD-Final | 10/13/1999 | 10/13/1999 | 10/13/1999 | A | PASS |
Jim Sly
|
|
|
Final on shell ofc. bldg.
|
PubWorks Occupancy Approval | | | 10/13/1999 | | |
|
|
|
Inspections done by Brian Murphy.
|
FIRE-Final Inspection | 10/8/1999 | 10/11/1999 | 10/11/1999 | A | PASS |
Joe Tawney
|
|
|
dennis ###-#### reinsp ok for cert of completion
|
BLD-Final | 10/7/1999 | 10/8/1999 | 10/8/1999 | A | FAIL |
Jim Sly
|
|
|
NEED REQ. SIGNATURES
|
FIRE-Final Inspection | 10/7/1999 | 10/8/1999 | 10/8/1999 | A | FAIL |
Joe Tawney
|
|
|
REINSPECTION FAIL ON DAMPER DETECTOR NOT INSTALLED
|
FIRE-Final Inspection | 10/7/1999 | 10/7/1999 | 10/7/1999 | P | FAIL |
Joe Tawney
|
|
|
DENNIS--- ###-#### FIRE FN reinsp fail
|
FIRE-Sprinkler Rough-in | 9/14/1999 | 9/15/1999 | 9/15/1999 | A | CANC |
Joe Tawney
|
|
|
R/I ALREADY SIGNED OFF
|
Code Occupancy Approval | | | 8/31/1999 | | |
|
|
|
Final Occupancy requested by Dennis Potter ###-####
|
Receive PAYMENT IN FULL | | | 7/12/1999 | | |
|
|
|
|
SUPER- Supervisor's review | 7/7/1999 | 7/7/1999 | 7/7/1999 | | |
|
|
|
jim sly is handeling work is slowly proceeding permit is to remain active
|
SUPER- Supervisor's review | 6/30/1999 | 6/30/1999 | 6/30/1999 | | |
|
|
|
jim sly will review case and reply to me by 2end week of july
|
SUPER- Supervisor's review | 6/24/1999 | 6/24/1999 | 6/24/1999 | | |
|
|
|
jim sly did job joe taweny has sprinkler problems, shell only minor interior stud framing unfinished. jim sly needs to follow up
|
SUPER- Supervisor's review | 6/18/1999 | 6/18/1999 | 6/18/1999 | | |
|
|
|
if i don't know i can't fix it. i have asked for cooperation on not answering calls or questions and routing them to me. i have not been notified of a problem on this job and i expect mr sly can fill us in on why its occupied without final.
|
(F) Reprint permit | | | 3/19/1999 | | |
|
|
|
|
Fee Review-notes | 8/5/1998 | | 11/16/1998 | | WORK |
|
|
|
|
INSP - Final | 10/6/1998 | 10/6/1998 | 10/6/1998 | P | FAIL |
Jim Sly
|
|
|
10/06/98 316 - C/N...Need appr plan, letter of appr from special insp an
|
INSP - Final | 10/6/1998 | 10/6/1998 | 10/6/1998 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - FINAL ON SHELL FAIL SPKLR ALARMS NO PLANS ON SITE FDC CONNEC
|
INSP-Sprinkler Rough-in/Hydro | 6/30/1998 | 7/1/1998 | 7/2/1998 | P | PART |
Joe Tawney
|
|
|
07/01/98 406 - Shelly ###-#### OK ON ABOVE GROUND HYDRO TEST AND ROUGH IN
|
INSP - Framing/Rough-in | 6/22/1998 | 6/22/1998 | 6/22/1998 | P | PART |
Jim Sly
|
|
|
06/22/98 316 - Insp of framed ext. framework above roof...OK
|
INSP - Framing/Rough-in | 6/16/1998 | 6/17/1998 | 6/17/1998 | P | PART |
Jim Sly
|
|
|
06/17/98 316 - FRAMING/ MECH ROOM/ OK
|
INSP-Sprinkler Rough-in/Hydro | 6/3/1998 | 6/3/1998 | 6/3/1998 | P | PART |
Joe Tawney
|
|
|
06/03/98 406 - 200 LB TEST/ ###-#### OK ON UNDERGROUND HYDRO TEST
|
INSP-Supply line flush | 5/22/1998 | 5/22/1998 | 5/22/1998 | P | PASS |
Rick Jackson
|
|
|
###-#### underground flush pass
|
INSP - Concrete | 4/30/1998 | 5/1/1998 | 5/1/1998 | A | PART |
Jim Sly
|
|
|
05/01/98 316 - Walls pending special inspectors approval.
|
INSP - Concrete | 4/27/1998 | 4/27/1998 | 4/27/1998 | P | PART |
Jim Sly
|
|
|
04/27/98 316 - Rebar in tilt panels..Pending special insp approval....
|
INSP - Foundation | 4/17/1998 | 4/17/1998 | 4/17/1998 | P | PART |
Jim Sly
|
|
|
04/17/98 316 - Tilt up panels (4)....pending special insp approval.....
|
INSP - Foundation | 4/9/1998 | 4/9/1998 | 4/9/1998 | P | PART |
Jim Sly
|
|
|
04/09/98 316 - footing West side...OK pending special insp approval...
|
INSP - Foundation | 4/2/1998 | 4/3/1998 | 4/3/1998 | A | CANC |
Tom Arcoraci
|
|
|
04/03/98 408 - BRIAN WILL CALL YOU ABOUT THIS..###-#### done by 316
|
(F) Reprint permit | | | 3/13/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/12/1998 | | |
|
|
|
|
Meeting | | | 2/27/1998 | | PASS |
|
|
|
TALKED TO RANDY AT STEED WILL BE IN ON TUESDAY OR WEDNESDAY TO PICK UP
|
Telephone call | | | 2/20/1998 | | |
|
|
|
CALLED AND TALKED TO RANDY STEED. TOLD HIM PLANS WILL BE VOIDED IF THEY DON'T PICK UP PLANS. MAILED LETTER OF EXPIREATION OF PLAN REVIEW.MPS TOLD HIM HE COULD HAVE A COUPLE OF DAYS TO GET BACK WITH ME.
|
Telephone call | | | 2/20/1998 | | PEND |
|
|
|
GRAIG GROVES CALLED WILL BE IN 2/27/98 OR WILL CALL US TO LET US KNOW.PE HE SHOULD GET FUNDS FROM BANK NEXT WEEK
|
Telephone call | | | 7/23/1997 | | |
|
|
|
TALKED TO SCOTT AT STEED, TOLD HIM PERMIT NEEDS TO BE PICKED UP OR IT WILL BE VOIDED/ HE SAID OWNER HAS STALLED ON PROJECT, WILL LET ME KNOW,
|
180 day tracking............. | | 10/10/1996 | 4/8/1997 | | PEND |
|
|
|
|
Inspection Record Card- Bld | | | 3/24/1997 | | |
|
|
|
|
Telephone call | | | 3/24/1997 | | |
|
|
|
PERMIT READY, FEE DUE/ BRING ACHD RECEIPT
|
Print Occupancy Form | | | 3/24/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/21/1997 | | PASS |
|
|
|
|
Received Certificate of Value | | | 3/21/1997 | | PASS |
|
|
|
|
Plan assigned to (M_O) | 11/5/1996 | | 3/21/1997 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 3/18/1997 | | 3/19/1997 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 2/21/1997 | | 2/24/1997 | | FAIL |
|
|
|
|
Routing - PLANNING | 1/15/1997 | | 2/20/1997 | | PASS |
|
|
|
X-REF: V-18-94,DR-134-94. APPROVED BY SR & TKW.
|
Plan resubmittals received | | | 2/18/1997 | | PEND |
|
|
|
Electrical plans submitted will need to be reviewed by ELEC.MO
|
90 day tracking............. | | 10/10/1996 | 1/8/1997 | | PEND |
|
|
|
|
Routing Off Site - STRUCTURAL | 12/16/1996 | | 12/24/1996 | | PASS |
|
|
|
|
Routing - FIRE | 12/17/1996 | | 12/17/1996 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 12/16/1996 | | FAIL |
|
|
|
Plans for structural engineer as requested received 12/16 MO. NON-STRUCTURAL CORRECTIONS MAILED AND FAXED TO ARCHITECT. MO
|
Plan resubmittals received | | | 12/16/1996 | | |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM HABITEC ARCHITECTS FOR THE ENGINEERING CONSULTANT.
|
Routing - PUBLIC WORKS | 12/6/1996 | | 12/13/1996 | | PASS |
|
|
|
|
Telephone call | | | 12/9/1996 | | FAIL |
|
|
|
CALLED GORDON MCDONALD IN CA. FOR ADDITIONAL ARCHITECTURAL SHEETS AS REQUESTED BY ATTWOOD, HINZMAN, JONES FOR STRUCTURAL REVIEW. MO
|
Routing - PLUMBING | 11/26/1996 | | 11/29/1996 | | PASS |
|
|
|
|
Routing - PLANNING | 11/14/1996 | | 11/25/1996 | | FAIL |
|
|
|
X-ref: V-18-94 & DR-134-94. Need revised plans per DR conditions of approval. Reviewed by SR & TKW.
|
Plan Reviewer's activity | | | 11/18/1996 | | FAIL |
|
|
|
structral plans received from architect as requested forwared to consulting engineer for review. Elec sheets not provided as requested. Plans are in PW as of this date. MO
|
Routing - PUBLIC WORKS | 11/7/1996 | | 11/13/1996 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN REVISION. BRIAN MURPHY KMM 11-14-96
|
Plan Reviewer's activity | | | 11/5/1996 | | |
|
|
|
PLANS RECEIVED FOR REVIEW 11-05-96. MO.
|
Plan Reviewer's activity | | | 11/5/1996 | | FAIL |
|
|
|
PLAN SUBMITTAL IS INCOMPLETE. LETTER SENT TO ARCHITECT TO PROVIDE MISSING PLANS SO CIRCULATION CAN BEGIN. WILL SEND TO P.W. THIS IS NOT A PACKAGE PLAN. MO 11-05-96.
|
Routing Off Site - A.C.H.D | 10/11/1996 | | 10/31/1996 | | PASS |
|
|
|
CONTACTED HABITEC AT ###-#### TO TAKE PLANS OUT TO ACHD
|
Received Certificate of Value | | | 10/11/1996 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 10/11/1996 | | PASS |
|
|
|
|
Gay Receipt For Partial Pay | | | 10/10/1996 | | PEND |
|
|
|
|
Application received | | | 10/10/1996 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/10/1996 | | PEND |
|
|
|
|