CHANGE STATUS TO (D) | | | 2/10/1997 | | PASS |
|
|
|
|
INSP - Final | 1/27/1997 | 1/28/1997 | 1/28/1997 | P | PASS |
Alan Hauser
|
|
|
01/28/97 350 - FINAL
|
INSP - Letter of compliance | 1/28/1997 | 1/28/1997 | 1/28/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - C/C #11297
|
INSP - Letter of compliance | 1/28/1997 | 1/28/1997 | 1/28/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - C/C #11297
|
INSP - Energy code compliance | 12/19/1996 | 12/19/1996 | 12/19/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - insulation ok, ok to cover
|
INSP - Framing/Rough-in | 12/18/1996 | 12/19/1996 | 12/19/1996 | A | PASS |
Alan Hauser
|
|
|
12/19/96 350 - frame ok, ok to insulate
|
INSP - Framing/Rough-in | 12/16/1996 | 12/17/1996 | 12/17/1996 | P | PASS |
Alan Hauser
|
|
|
12/17/96 350 - frame ok, ok to insulate
|
INSP - Foundation | 10/30/1996 | 10/31/1996 | 10/31/1996 | P | PASS |
Alan Hauser
|
|
|
10/31/96 350 - INSPECTION WAS ON 1 HR. PARTY WALL
|
INSP - Footings | 10/28/1996 | 10/28/1996 | 10/28/1996 | | NR |
Alan Hauser
|
|
|
/ / 350 - NOT READY
|
INSP - Footings | 10/25/1996 | 10/25/1996 | 10/28/1996 | P | PASS |
Alan Hauser
|
|
|
10/25/96 350 - FTNS OK REBAR IN PLACE
|
INSP - Framing/Rough-in | 10/23/1996 | 10/23/1996 | 10/23/1996 | | PASS |
Alan Hauser
|
|
|
/ / 350 - UNDERFLOOR INSPECTION OK
|
Inspection Record Card- Bld | | | 10/23/1996 | | |
|
|
|
|
Plan assigned to (PRP) | 10/15/1996 | | 10/23/1996 | | PASS |
|
|
|
10/23/96 08:14:38 PRP - this action updated by action script from <<>> in Case No. BLD96-2774
|
Print Pending Permit.LaserJet4 | | | 10/23/1996 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/23/1996 | | PASS |
|
|
|
ISSUE
|
Plan Reviewer's activity | | | 10/23/1996 | | PASS |
|
|
|
RECEIVED PLANS AND APPLICATION CLEARED THROUGH PW AND PLANNING FOR REVIEW. BUILDING TYPE B, PREVIOUSLY REVIEWED AND APPROVED, STAMP APPROVED AND ISSUE.
|
Issue PAID IN FULL permit | | | 10/23/1996 | | |
|
|
|
|
Telephone call | | | 10/23/1996 | | |
|
|
|
CALLED BILL TOLD HIM PLANS ARE READY TO BE PICKED UP GAVE HIM DOLLAR AMOUNTS ON BOTH PROJECTS.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/1996 | | PASS |
|
|
|
ISSUE
|
Routing - PLANNING | 10/15/1996 | | 10/18/1996 | | PASS |
|
|
|
X-ref: CU-53-93. Approved by RLB.
|
Application received | | | 10/15/1996 | | |
|
|
|
|
Plan assigned to (DJO) | 10/15/1996 | | 10/15/1996 | | PEND |
Dan Overy
|
|
|
|
Routing - PUBLIC WORKS | 10/15/1996 | | 10/15/1996 | | PASS |
|
|
|
PASSED BY R
|
Routing - PLAN CHECK | 10/22/1996 | | | | PEND |
|
|
|
|