To perform structural modifications in a 21,000 sq.ft. area of an existing 52,005 sq.ft. building to lower the floor area 6 ft. below current level per approved plans on file. The sequence of events are to follow the attached letter from B. Smith, P.E. dated 12/20/96 attached to plans. Special inspections to be performed as noted in attached conditions. A final review of the project to be conducted by the structural engineer and a letter of acceptance provided to the Structural Inspector prior to final of this permit. NOTE: No other remodel or occupancy is to be granted under this permit. (P.C.#661-96/mys)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled1/29/20011/29/20011/29/2001PPASS
DetailsRuss Owen
Added by Inspector: 407 On 1/29/2001 3:58:43 PM
INSP - Letter of compliance7/22/19977/22/19977/22/1997 PASS
Details
/ / 338 - LCI-LETTER OF COMPLIANCE ISSUED 13543
INSP - Final7/22/19977/22/19977/22/1997 PASS
Details
/ / 338 - FNL -OK FINAL LCI-LETTER OF COMPLIANCE ISSUED # 13543
INSP - Letter of compliance7/22/19977/22/19977/22/1997 PASS
Details
/ / 338 - LCI-LETTER OF COMPLIANCE ISSUED 13543
INSP - Final7/22/19977/22/19977/22/1997 PASS
Details
/ / 338 - FNL -OK FINAL LCI-LETTER OF COMPLIANCE ISSUED # 13543
INSP - Temporary occupancy5/29/19975/30/19975/30/1997PPART
Details
05/30/97 338 - signed the temp col for thr 1st phase only
INSP - Temporary occupancy5/28/19975/29/19975/29/1997PCANC
Details
05/29/97 338 - cancelled by the contr.
INSP - Temporary occupancy5/27/19975/28/19975/28/1997PCANC
Details
05/28/97 338 - cancell till tomorrow per the contrac. fire alarm is a p
INSP - Ceiling grid5/5/19975/6/19975/6/1997APASS
Details
05/06/97 338 - 8455 w westpark bld 456 made ok in the clean room area
INSP - Ceiling grid4/28/19974/28/19974/28/1997PFAIL
DetailsCarl Dependahl
04/28/97 340 - T-BAR SEISMIC...C/N, NEED PLAN & PERMIT POSTED.
INSP - Framing/Rough-in4/24/19974/25/19974/25/1997APASS
Details
04/25/97 338 - misc int wall framing other agencies made ok
INSP-Sprinkler Rough-in/Hydro4/24/19974/24/19974/24/1997PCANC
DetailsJoe Tawney
04/24/97 406 - JEFF ###-#### CANCEL INCORRECT PERMIT NBR SHOULD BE BLD96-2980 ì
INSP - Footings2/5/19972/5/19972/5/1997PPASS
Details
02/05/97 338 - special insp made ok
90 day tracking............. 11/4/19962/2/1997
Plan resubmittals received  1/28/1997 PASS
S1.1,S1.2,S2.1,S2.2, REVIEWED OK'D AND PLACED IN THE BUILDING DEPART SET IN PLAN VAULT..
INSP - Footings1/16/19971/17/19971/17/1997PPASS
Details
01/17/97 338 - made ok sp ec insp made ok
INSP - Footings1/13/19971/14/19971/14/1997APASS
Details
01/14/97 338 - 1/2 READY TO POUR R-BAR PLACED TWO TRUCKS SENT BACK BECAU RATHER THAN TYP 1"- CALL WAS MADE BY THE PROJECT MANAGER
INSP - Conference1/7/19971/8/19971/8/1997PPASS
Details
01/08/97 338 - made ok observed celotex polyiso insulation around the st exposed. Verbally expressed concerns of same to the super.
Issue PAID IN FULL permit  12/24/1996
Inspection Record Card- Bld  12/24/1996
Print Occupancy Form  12/24/1996
Telephone call  12/24/1996
CALLED RUSSEL CORP/ PERMIT READY, FEE DUE
PLANS/APPL TAKEN TO FRONT DESK  12/23/1996 PASS
Plan assigned to (MYS)11/4/1996 12/23/1996 PASS
DetailsMarlene Southard
Plan Reviewer's activity  12/20/1996
Requested a letter from the architect or engineer describing the sequence of events for the project. A response letter written by the engineer was forwarded by FAX to me on 12/20/96.
Routing Off Site - STRUCTURAL11/5/1996 12/19/1996 PASS
11/5/96-Routed off site to ATWOOD-HINZMAN-JONES (AHJ). 12/2/96-Plan review failed at AHJ. Sent comments to M. Capshaw at BRS Architects. 12/9/96-Received response from PINNACLE ENGINEERS and forwarded it to AHJ. 12/12/96-Response failed at AHJ. Sent comments to M. Capshaw. 12/18/96-Received resubmittals from Pinnacle Engineers and forwarded to AHJ. 12/19/96-Received letter of approved from AHJ.
Recd Pcfee & Taken To Pln CK  11/5/1996
Gay Receipt For Partial Pay  11/5/1996
Application received  11/4/1996