Case Summary (BLD) | | | 5/15/2007 | | |
|
|
|
|
Permanent Occupancy | | 9/10/1997 | 9/10/1997 | | DONE |
|
|
|
|
INSP - Final | 9/9/1997 | 9/10/1997 | 9/10/1997 | P | PASS |
Jim Storey
|
|
|
09/10/97 301 - FNL -OK FINAL
|
Permanent occupancy | | | 9/10/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6981 issued 9-10-97 to Associated Food Stores.
|
PubWorks Occupancy Approval | | | 9/10/1997 | | DONE |
|
|
|
Project complete per Building Department. 9/10/97. R.Rokovitz
|
INSP-Final Inspection | 8/5/1997 | 8/6/1997 | 8/6/1997 | P | FAIL |
|
|
|
need signs on ammonia piping in freezer. need class 1division 2 emergency and exit lights for machinery room.
|
Temporary occupancy | | | 8/5/1997 | | PASS |
|
|
|
Temp. Occ. Cert. #3431 issued 7-16-97 to Associated Foods Stores by Monica.
|
INSP - Final | 7/15/1997 | 7/15/1997 | 7/15/1997 | A | PART |
Jim Storey
|
|
|
07/15/97 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED tenp occ ok
|
INSP-Final Inspection | 7/15/1997 | 7/14/1997 | 7/14/1997 | P | PART |
|
|
|
c/n issued on alarms, recieved timetable for completion, all by 8/1
|
INSP-Final Inspection | 7/8/1997 | 7/9/1997 | 7/9/1997 | P | FAIL |
|
|
|
no alarms connected, no purge ventilation, no sprinklers active
|
Routing for occupancy | 6/23/1997 | 7/1/1997 | 7/1/1997 | | PASS |
|
|
|
Complies w/ DR-119-96 (SMB inspected on 7/1/97)
|
INSP-Sprinkler Rough-in/Hydro | 6/19/1997 | 6/20/1997 | 6/20/1997 | A | PART |
|
|
|
10 A.M. "TRIP TEST" MIKE - ###-#### 53 SECONDS TO FULL FLOW
|
INSP-Supply line flush | 6/9/1997 | 6/12/1997 | 6/12/1997 | A | PASS |
|
|
|
"FLUSH"
|
INSP-Sprinkler Rough-in/Hydro | 6/9/1997 | 6/11/1997 | 6/11/1997 | P | PART |
|
|
|
MIKE ###-#### hydro ok above and underground systems
|
INSP-Conference | 6/3/1997 | 6/3/1997 | 6/3/1997 | P | FAIL |
|
|
|
dropped off rejection of FPC resubmittal on ammonia tank alternative design.
|
INSP-Sprinkler Rough-in/Hydro | 5/27/1997 | 5/28/1997 | 5/28/1997 | A | FAIL |
|
|
|
deliver preaction plans w/ comments, piping hung, test port connected to branch not sprig, wrong heads used for col prot.
|
INSP-Conference | 5/21/1997 | 5/21/1997 | 5/21/1997 | A | FAIL |
|
|
|
rvw alarm plans at grinnel, dbl interlock only combined dry/preaction sys not in compliance w/ nfpa 13, will send letter to sanchez at fpc
|
INSP-Conference | 5/6/1997 | 5/6/1997 | 5/6/1997 | P | PASS |
|
|
|
reviewed resubmit on ammonia tank, approved w/conditions, faxed to job trailer letter
|
INSP-Conference | 4/1/1997 | 4/1/1997 | 4/1/1997 | A | PASS |
|
|
|
meet w/ Sanchez on vapor alarms and submittal requirements, reply to his letter of 3/28.
|
INSP-Conference | 2/26/1997 | 2/26/1997 | 2/26/1997 | P | PASS |
|
|
|
met w/ sanchez on fire hydrants for site before combustables are brought in, reviewed their resubmittal dated 2/24
|
90 day tracking............. | | 11/6/1996 | 2/4/1997 | | PEND |
|
|
|
|
Issue PAID IN FULL permit | | | 2/3/1997 | | |
|
|
|
|
Plan assigned to (M_O) | 11/27/1996 | | 1/31/1997 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 1/31/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/31/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/31/1997 | | PASS |
|
|
|
|
Print Occupancy Form | | | 1/31/1997 | | |
|
|
|
|
Telephone call | | | 1/31/1997 | | |
|
|
|
CALLED RUDY SANCHEZ WITH AMOUNT
|
Routing Off Site - STRUCTURAL | 1/27/1997 | | 1/30/1997 | | PASS |
|
|
|
RESUBMITTED CALCULATIONS FORWARDED TO STAPLEY FOR REVIEW.
|
Plan resubmittals received | | | 1/29/1997 | | FAIL |
|
|
|
revised structural plans received 1-29-97 sent to Stapley same day. MO.
|
Telephone call | | | 1/28/1997 | | FAIL |
|
|
|
SPOKE WITH RUDY SANCHEZ. PLANS FOR STRUCTURAL CORRECTIONS DID NOT ARRIVE. WILL TRY AND SUBMIT ON WED 1-29-97. MO
|
Plan resubmittals received | | | 1/27/1997 | | FAIL |
|
|
|
RECEIVED CALCULATIONS FOR STRUCTURAL RESUBMITTAL FOR STAPLEY. REVISED PLANS ARE TO FOLLOW IN NEXT TWO DAYS PER R. SANCHEZ. MO
|
Routing Off Site - STRUCTURAL | 1/14/1997 | | 1/22/1997 | | FAIL |
|
|
|
RESUBMITTALS SENT TO STAPLEY ENGINEERING VIA PDQ. Received 8 item correction list on resubmittals from Chris Merrill, P.E. Stapley Engineering. List Faxed to applicant 1-22-97. MO
|
Routing - FIRE | 1/14/1997 | | 1/21/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLAN CHECK | 12/11/1996 | | 1/14/1997 | | |
|
|
|
PACKAGE #1
|
Routing - FIRE | 12/6/1996 | | 12/11/1996 | | FAIL |
|
|
|
PACKAGE #1
|
Routing - PUBLIC WORKS | 11/27/1996 | | 12/9/1996 | | PASS |
|
|
|
PACKAGE # 2
|
Routing - PLAN CHECK | 11/27/1996 | | 12/6/1996 | | |
|
|
|
PACKAGE #1
|
Routing - ELECTRICAL | 11/26/1996 | | 11/27/1996 | | PASS |
|
|
|
PACKAGE #1
|
Plan assigned to (RGG) | 11/13/1996 | | 11/27/1996 | | |
|
|
|
|
Routing - PLUMBING | 11/22/1996 | | 11/26/1996 | | PASS |
|
|
|
PACKAGE#1
|
Routing - MECHANICAL | 11/7/1996 | | 11/21/1996 | | PASS |
|
|
|
PACKAGE 1 NO REVIEW WILL FIELD VERIFY
|
Routing - PLANNING | 11/18/1996 | | 11/20/1996 | | PASS |
|
|
|
PACKAGE #2 X-ref: DR-115-96. Approved by TKW.
|
Routing Off Site - STRUCTURAL | 11/7/1996 | | 11/19/1996 | | FAIL |
|
|
|
PACKAGE #3 CONTACTED PDQ TO TAKE PLANS OUT TO STAPLEY ENGINEERING. KMM CORRECTIONS BY CHRISTOPHER MERRILL, P.E. 11-19-96.
|
Routing - PUBLIC WORKS | 11/12/1996 | | 11/18/1996 | | FAIL |
|
|
|
PACKAGE ##2
|
Routing Off Site - A.C.H.D | 11/7/1996 | | 11/14/1996 | | PASS |
|
|
|
PACKAGE #4 CONTACTED DEAN BRIGGS AT ###-#### TO TAKE PLANS OUT TO ACHD. KMM IMPACT FEES PAID #97-0172 11-1-96
|
Routing Off Site - C.D.H | 11/7/1996 | | 11/12/1996 | | PASS |
|
|
|
PACKAGE #2 CONTACTED DEAN BRIGGS AT ###-#### TO TAKE PLANS OUT TO CDH
|
Plan routing begun/NEW & ADDTN | | | 11/7/1996 | | PASS |
|
|
|
|
Received Certificate of Value | | | 11/6/1996 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/6/1996 | | |
|
|
|
|
Gay Receipt For Partial Pay | | | 11/6/1996 | | |
|
|
|
|
Application received | | | 11/6/1996 | | |
|
|
|
|
Routing - PLAN CHECK | 12/9/1996 | | | | |
|
|
|
PACKAGE #2
|
Routing - PLAN CHECK | 1/22/1997 | | | | PEND |
|
|
|
PACKAGE #1 Corrections satisfied on resubmittals of 1-21-97. MO Still need structural.
|