Permit Information
Permit NumberBLD96-03211
StatusFinaled
Name GORDON CROFT
Site Address 8300 NORTHVIEW ST
Project NameDENTAL OFFICE
Customer Number 
ePlanReviewNo
Description
CROFT DENTAL OFFICE * TO CONSTRUCT A NEW 2,674 SQ.FT. SINGLE STORY, WOOD FRAMED, TYPE V-NONRATED, DENTAL OFFICE, WITH A 844 SQ.FT. BASEMENT. ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED COMMENT LIST, CABO/ANSI STANDARDS A117.1 AND THE 1994 EDITION OF THE UBC. PERMIT TO INCLUDE RELATED SITE IMPROVEMENTS AS SPECIFIED ON THE APPROVED PLANS. MJP (PC#725-96) DR#-106-96
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 7/21/19987/21/1998 DONE
Details
INSP - Final7/21/19987/21/19987/21/1998APASS
DetailsJim Sly
as per our conversation 316 okay to give final/mps
Permanent occupancy  7/21/1998 PASS
Perm. Occ. Cert. #7324 issued 7-21-98 to Croft Dental Ofc.
Code Occupancy Approval  7/2/1998 PASS
BERM COMPLETED, SPRINKLERS IN AND WORKING, PLANTERS TAKEN CARE OF. PERMANENT OCCUP SIGNED.
Temporary occupancy  3/2/1998 PASS
Temp. Occ. Cert. #3557 issued 3-2-98 to Croft Dental.
INSP - Final2/25/19982/26/19982/26/1998APASS
DetailsJim Sly
02/25/98 316 - CROFT DENTAL Temp Occ. OK
INSP-Final Inspection2/25/19982/25/19982/25/1998PPASS
DetailsJoe Tawney
02/25/98 406 - CROFT DENTAL--PRESTON ###-#### REINSP OK FOR PERM OCC
INSP-Final Inspection1/27/19981/27/19981/27/1998PFAIL
DetailsJoe Tawney
01/27/98 406 - ###-#### REINSP FOR PERM OCC FAIL SMOKE SEAL ON DOOR AT BOTTOM OF STAIRS
Code Occupancy Approval  1/26/1998 FAIL
Insp. for Temp. Occupancy - Need to fax est. to Bond - Berm in front of Northview St./Streetlight (also small amt of soil aid needed to finish off a couple of planters and approx 200 s.ft. of sod at corner of proj. at berm on east side near Northview. Posted Bond $2,790.00 (CC).signed. (2/6/98)
INSP - Final1/9/19981/12/19981/12/1998AFAIL
DetailsJim Sly
01/09/98 316 - C/N...Need required signatures...
INSP - Final1/9/19981/9/19981/9/1998PNR
DetailsJim Sly
01/09/98 316 - Cancelled by contractor...
INSP-Final Inspection1/9/19981/9/19981/9/1998PPART
DetailsJoe Tawney
01/09/98 406 - REINSP FOR FINAL OK FOR TEMP OCC CANNOT USE MED GAS SYST
INSP-Final Inspection12/29/19971/7/19981/7/1998AFAIL
DetailsJoe Tawney
01/07/98 406 - FINAL FAIL EXIT DR HDWRE FIRE EXT EXIT SIGNS
INSP - Conference12/1/199712/2/199712/2/1997APASS
DetailsJim Sly
12/01/97 316 - Croft dental
INSP - Energy code compliance10/23/199710/24/199710/24/1997PPASS
DetailsJim Sly
10/24/97 316 -
INSP - Framing/Rough-in10/23/199710/24/199710/24/1997PPASS
DetailsJim Sly
10/24/97 316 - REINSPECT/ DENTAL OFFICE OK
INSP - Framing/Rough-in10/17/199710/21/199710/21/1997AFAIL
DetailsJim Sly
10/20/97 316 - C/N...Arch to submit firestopping bsmt ceiling, lat truss
INSP - Carpentry9/17/19979/17/19979/17/1997PPASS
DetailsJim Sly
09/17/97 316 - ROOF NAILING OK
INSP - Foundation8/21/19978/21/19978/21/1997 PASS
DetailsJim Sly
08/21/97 316 - OK
INSP - Footings8/21/19978/21/19978/21/1997 PASS
DetailsJim Sly
/ / 316 - OK
INSP - Footings8/18/19978/18/19978/18/1997 PART
DetailsJim Sly
08/18/97 316 - OK to pour pend spec insp...West 1/2 Footings...
(F) Reprint permit  8/5/1997
Issue PAID IN FULL permit  8/4/1997
Plan assigned to (M_P)12/17/1996 8/1/1997 PASS
DetailsMike Phillips
08/01/97 09:53:48 DAR - this action updated by action script from <<>> in Case No. BLD96-3211
Telephone call  8/1/1997
PERMIT READY, FEE DUE
PLANS/APPL TAKEN TO FRONT DESK  8/1/1997 PASS
Inspection Record Card- Bld  8/1/1997
Print Occupancy Form  8/1/1997
Plan Reviewer's activity  7/31/1997 PASS
Print Pending Permit.LaserJet4  7/31/1997 PASS
Routing Off Site - STRUCTURAL7/10/1997 7/29/1997 PASS
ROUTING FOR FOLLOW-UP REVIEW. REVISED PLANS SENT OUT TO CH2MHILL STRUCTURAL COMMENTS APPROVED MP
Plan resubmittals received  7/24/1997 HOLD
3rd SET OF SUBMITTALS, WAITING FOR SECOND OUTSIDE STRUCTURAL REVIEW TO RETURN PRIOR TO FOLLOW-UP REVIEW
Plan Reviewer's activity  7/11/1997 FAIL
SENT SECOND CORRECTION REPORT,MINUS STRUCTURAL COMMENTS
Plan resubmittals received  6/4/1997 FAIL
WRONG PLAN SUBMITTAL SUBMITTED AGAIN NOTIFIED CONTRACTOR AND ARCHITECT
Plan resubmittals received  5/29/1997 FAIL
SUBMITTED WRONG SUBMITTALS. THE PLANS WHICH WERE SUBMITTED ARE PLUMBING PLANS. NOTIFIED CONTRACTOR AND ARCHITECT.
Routing Off Site - A.C.H.D12/13/1996 5/9/1997 PASS
PACKAGE #4 CONTACTED PERRY CAMPBELL AT ###-#### TO TAKE PLANS OUT TO ACHD. KMM RECEIVED IMPACT FEE RECEIPT ON 05/09/97
Routing - PUBLIC WORKS4/28/1997 4/30/1997 PASS
PACKAGE #2
Routing - PUBLIC WORKS4/14/1997 4/16/1997 FAIL
PACKAGE #2
Routing - PLUMBING3/11/1997 3/12/1997 PASS
PACKAGE #1
Routing - PLUMBING3/5/1997 3/6/1997 FAIL
package #1
Routing - PUBLIC WORKS3/3/1997 3/5/1997 FAIL
PACKAGE #2 REQUIRES DRAINAGE PLAN REVISION BM 03-05-97
Routing - PLAN CHECK3/3/1997 3/3/1997
package #2
Routing - PLANNING2/28/1997 3/3/1997 PASS
X-ref: DR-106-96. Approved by MS.
90 day tracking............. 12/2/19963/2/1997 PEND
Routing - PUBLIC WORKS2/20/1997 2/27/1997 FAIL
PACKAGE #2 SAME AS PREVIOUS TIME.
Routing - PLAN CHECK2/10/1997 2/20/1997
PACKAGE #2
Plan resubmittals received  2/20/1997 PEND
RESUBMITTALS FOR PACKAGE #2. SENT TO PW
Routing - PLUMBING2/18/1997 2/18/1997 FAIL
PACKAGE #1
Routing - FIRE1/15/1997 2/13/1997 PASS
PACKAGE #1
Routing - PLANNING2/10/1997 2/10/1997 FAIL
PACKAGE #2 Landscape plan needs to be revised & cross access agreements provided per sonditions of approval. Reviewed by MS.
Routing - PUBLIC WORKS12/13/1996 2/10/1997 FAIL
PACKAGE #2 NEEDS DRAINAGE PLAN REVISION. NEEDS STREET LIGHTING PLANS.
Application received  2/10/1997
Plan resubmittals received  1/31/1997 PEND
RECEIVED PLUMBING RESUBS. MARK AND MATCH.
Routing - PLAN CHECK12/27/1996 1/15/1997
PACKAGE #1D
Plan Reviewer's activity  1/8/1997 FAIL
SENT COMPLETYE CORRECTION NOTICE 01/08/97
Routing Off Site - STRUCTURAL12/13/1996 12/31/1996 FAIL
PACKAGE #3 PLANS TAKEN TO CH2MHILL ATTEN CRAIG BARRETT VIA PDQ. KMM 1) STRUCTURAL REVIEW NOT COMPLETE WAITING FOR ADDITIONAL INFORMATION TO BE SUBMITTED FROM OUTSIDE ENGINEERING FIRM. 12/31/96 2) STRUCTURAL REVIEW COMPLETE SENT CORRECTION 01/08/97
Routing - FIRE12/24/1996 12/27/1996 FAIL
PACKAGE #1
Routing - PLAN CHECK12/24/1996 12/24/1996
PACKAGE #1
Routing - MECHANICAL12/19/1996 12/24/1996 PASS
PACKAGE #1 NO REVIEW FIELD VERIFY PER 337 12/24/96 DAR
Print Pending Permit.LaserJet4  12/19/1996 FAIL
PARTICIAL CORRECTION READY WAITING FOR STRUCTURAL REVIEW TO RETURN PRIOR TO SENDING TO ARCHITECT.
Plan Reviewer's activity  12/19/1996 FAIL
WAITING FOR STRUCTURAL REVIEW TO RETURN PRIOR TO SEND COMPLETE CORRETION LIST OUT.
Plan assigned to (RGG)12/4/1996 12/17/1996
Routing - ELECTRICAL12/13/1996 12/17/1996 PASS
PACKAGE #1 ELECTRICAL DRAWING NOT COMPLETE. (ITEMS NEEDED:) 1. ONE LINE OF SERVICE. 2. LOCATION OF PANEL (5) AND MAIN SERVICE. 3. GROUNDING (MIN. CONCRETE ELECTRODE) ELECT. INSP. WILL REVIEW AT TIME OF INSPECTION. RESUBMITALS REQUIRED AND WILL BE FIELD REVIEWED. KMM 12-17-96
Routing - PLUMBING12/17/1996 12/17/1996 FAIL
PACKAGE #1
Plan routing begun/NEW & ADDTN  12/13/1996 PASS
PRESTON OF BAKER CONSTRUCTION BROUGHT STRUC. CALCS., DRAINAGE CALCS., SOIL BEARING PRESSURE. SECTION SHEETS 6,7,10 AND FAUL ENGINEERING SHEETS ALL STAMPED AND SIGNED. PLANS ARE READY FOR ROUTING. KMM 12-13-96
Plan routing begun/NEW & ADDTN  12/4/1996 HOLD
PLAN ROUTING ON HOLD. WAITING FOR STURCTURAL CALCS. SOIL BEARING, DRAINAGE CALCS. SHEETS 6,7,10, AND FAULL ENG. NEED STAMPS AND SIGN. KMM 12-04-96 CONTACTED PRESTON BAKER AND INFORMED HIM OF THESE NEEDS. 12-03-96 KMM
Recd Pcfee & Taken To Pln CK  12/2/1996
Application received  12/2/1996
Gay Receipt For Partial Pay  12/2/1996
Received Certificate of Value  12/2/1996 PASS