Permanent Occupancy | | 7/21/1998 | 7/21/1998 | | DONE |
|
|
|
|
INSP - Final | 7/21/1998 | 7/21/1998 | 7/21/1998 | A | PASS |
Jim Sly
|
|
|
as per our conversation 316 okay to give final/mps
|
Permanent occupancy | | | 7/21/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7324 issued 7-21-98 to Croft Dental Ofc.
|
Code Occupancy Approval | | | 7/2/1998 | | PASS |
|
|
|
BERM COMPLETED, SPRINKLERS IN AND WORKING, PLANTERS TAKEN CARE OF. PERMANENT OCCUP SIGNED.
|
Temporary occupancy | | | 3/2/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3557 issued 3-2-98 to Croft Dental.
|
INSP - Final | 2/25/1998 | 2/26/1998 | 2/26/1998 | A | PASS |
Jim Sly
|
|
|
02/25/98 316 - CROFT DENTAL Temp Occ. OK
|
INSP-Final Inspection | 2/25/1998 | 2/25/1998 | 2/25/1998 | P | PASS |
Joe Tawney
|
|
|
02/25/98 406 - CROFT DENTAL--PRESTON ###-#### REINSP OK FOR PERM OCC
|
INSP-Final Inspection | 1/27/1998 | 1/27/1998 | 1/27/1998 | P | FAIL |
Joe Tawney
|
|
|
01/27/98 406 - ###-#### REINSP FOR PERM OCC FAIL SMOKE SEAL ON DOOR AT BOTTOM OF STAIRS
|
Code Occupancy Approval | | | 1/26/1998 | | FAIL |
|
|
|
Insp. for Temp. Occupancy - Need to fax est. to Bond - Berm in front of Northview St./Streetlight (also small amt of soil aid needed to finish off a couple of planters and approx 200 s.ft. of sod at corner of proj. at berm on east side near Northview. Posted Bond $2,790.00 (CC).signed. (2/6/98)
|
INSP - Final | 1/9/1998 | 1/12/1998 | 1/12/1998 | A | FAIL |
Jim Sly
|
|
|
01/09/98 316 - C/N...Need required signatures...
|
INSP - Final | 1/9/1998 | 1/9/1998 | 1/9/1998 | P | NR |
Jim Sly
|
|
|
01/09/98 316 - Cancelled by contractor...
|
INSP-Final Inspection | 1/9/1998 | 1/9/1998 | 1/9/1998 | P | PART |
Joe Tawney
|
|
|
01/09/98 406 - REINSP FOR FINAL OK FOR TEMP OCC CANNOT USE MED GAS SYST
|
INSP-Final Inspection | 12/29/1997 | 1/7/1998 | 1/7/1998 | A | FAIL |
Joe Tawney
|
|
|
01/07/98 406 - FINAL FAIL EXIT DR HDWRE FIRE EXT EXIT SIGNS
|
INSP - Conference | 12/1/1997 | 12/2/1997 | 12/2/1997 | A | PASS |
Jim Sly
|
|
|
12/01/97 316 - Croft dental
|
INSP - Energy code compliance | 10/23/1997 | 10/24/1997 | 10/24/1997 | P | PASS |
Jim Sly
|
|
|
10/24/97 316 -
|
INSP - Framing/Rough-in | 10/23/1997 | 10/24/1997 | 10/24/1997 | P | PASS |
Jim Sly
|
|
|
10/24/97 316 - REINSPECT/ DENTAL OFFICE OK
|
INSP - Framing/Rough-in | 10/17/1997 | 10/21/1997 | 10/21/1997 | A | FAIL |
Jim Sly
|
|
|
10/20/97 316 - C/N...Arch to submit firestopping bsmt ceiling, lat truss
|
INSP - Carpentry | 9/17/1997 | 9/17/1997 | 9/17/1997 | P | PASS |
Jim Sly
|
|
|
09/17/97 316 - ROOF NAILING OK
|
INSP - Foundation | 8/21/1997 | 8/21/1997 | 8/21/1997 | | PASS |
Jim Sly
|
|
|
08/21/97 316 - OK
|
INSP - Footings | 8/21/1997 | 8/21/1997 | 8/21/1997 | | PASS |
Jim Sly
|
|
|
/ / 316 - OK
|
INSP - Footings | 8/18/1997 | 8/18/1997 | 8/18/1997 | | PART |
Jim Sly
|
|
|
08/18/97 316 - OK to pour pend spec insp...West 1/2 Footings...
|
(F) Reprint permit | | | 8/5/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/4/1997 | | |
|
|
|
|
Plan assigned to (M_P) | 12/17/1996 | | 8/1/1997 | | PASS |
Mike Phillips
|
|
|
08/01/97 09:53:48 DAR - this action updated by action script from <<>> in Case No. BLD96-3211
|
Telephone call | | | 8/1/1997 | | |
|
|
|
PERMIT READY, FEE DUE
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/1/1997 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/1/1997 | | |
|
|
|
|
Print Occupancy Form | | | 8/1/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 7/31/1997 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 7/31/1997 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/10/1997 | | 7/29/1997 | | PASS |
|
|
|
ROUTING FOR FOLLOW-UP REVIEW. REVISED PLANS SENT OUT TO CH2MHILL STRUCTURAL COMMENTS APPROVED MP
|
Plan resubmittals received | | | 7/24/1997 | | HOLD |
|
|
|
3rd SET OF SUBMITTALS, WAITING FOR SECOND OUTSIDE STRUCTURAL REVIEW TO RETURN PRIOR TO FOLLOW-UP REVIEW
|
Plan Reviewer's activity | | | 7/11/1997 | | FAIL |
|
|
|
SENT SECOND CORRECTION REPORT,MINUS STRUCTURAL COMMENTS
|
Plan resubmittals received | | | 6/4/1997 | | FAIL |
|
|
|
WRONG PLAN SUBMITTAL SUBMITTED AGAIN NOTIFIED CONTRACTOR AND ARCHITECT
|
Plan resubmittals received | | | 5/29/1997 | | FAIL |
|
|
|
SUBMITTED WRONG SUBMITTALS. THE PLANS WHICH WERE SUBMITTED ARE PLUMBING PLANS. NOTIFIED CONTRACTOR AND ARCHITECT.
|
Routing Off Site - A.C.H.D | 12/13/1996 | | 5/9/1997 | | PASS |
|
|
|
PACKAGE #4 CONTACTED PERRY CAMPBELL AT ###-#### TO TAKE PLANS OUT TO ACHD. KMM RECEIVED IMPACT FEE RECEIPT ON 05/09/97
|
Routing - PUBLIC WORKS | 4/28/1997 | | 4/30/1997 | | PASS |
|
|
|
PACKAGE #2
|
Routing - PUBLIC WORKS | 4/14/1997 | | 4/16/1997 | | FAIL |
|
|
|
PACKAGE #2
|
Routing - PLUMBING | 3/11/1997 | | 3/12/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLUMBING | 3/5/1997 | | 3/6/1997 | | FAIL |
|
|
|
package #1
|
Routing - PUBLIC WORKS | 3/3/1997 | | 3/5/1997 | | FAIL |
|
|
|
PACKAGE #2 REQUIRES DRAINAGE PLAN REVISION BM 03-05-97
|
Routing - PLAN CHECK | 3/3/1997 | | 3/3/1997 | | |
|
|
|
package #2
|
Routing - PLANNING | 2/28/1997 | | 3/3/1997 | | PASS |
|
|
|
X-ref: DR-106-96. Approved by MS.
|
90 day tracking............. | | 12/2/1996 | 3/2/1997 | | PEND |
|
|
|
|
Routing - PUBLIC WORKS | 2/20/1997 | | 2/27/1997 | | FAIL |
|
|
|
PACKAGE #2 SAME AS PREVIOUS TIME.
|
Routing - PLAN CHECK | 2/10/1997 | | 2/20/1997 | | |
|
|
|
PACKAGE #2
|
Plan resubmittals received | | | 2/20/1997 | | PEND |
|
|
|
RESUBMITTALS FOR PACKAGE #2. SENT TO PW
|
Routing - PLUMBING | 2/18/1997 | | 2/18/1997 | | FAIL |
|
|
|
PACKAGE #1
|
Routing - FIRE | 1/15/1997 | | 2/13/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLANNING | 2/10/1997 | | 2/10/1997 | | FAIL |
|
|
|
PACKAGE #2 Landscape plan needs to be revised & cross access agreements provided per sonditions of approval. Reviewed by MS.
|
Routing - PUBLIC WORKS | 12/13/1996 | | 2/10/1997 | | FAIL |
|
|
|
PACKAGE #2 NEEDS DRAINAGE PLAN REVISION. NEEDS STREET LIGHTING PLANS.
|
Application received | | | 2/10/1997 | | |
|
|
|
|
Plan resubmittals received | | | 1/31/1997 | | PEND |
|
|
|
RECEIVED PLUMBING RESUBS. MARK AND MATCH.
|
Routing - PLAN CHECK | 12/27/1996 | | 1/15/1997 | | |
|
|
|
PACKAGE #1D
|
Plan Reviewer's activity | | | 1/8/1997 | | FAIL |
|
|
|
SENT COMPLETYE CORRECTION NOTICE 01/08/97
|
Routing Off Site - STRUCTURAL | 12/13/1996 | | 12/31/1996 | | FAIL |
|
|
|
PACKAGE #3 PLANS TAKEN TO CH2MHILL ATTEN CRAIG BARRETT VIA PDQ. KMM 1) STRUCTURAL REVIEW NOT COMPLETE WAITING FOR ADDITIONAL INFORMATION TO BE SUBMITTED FROM OUTSIDE ENGINEERING FIRM. 12/31/96 2) STRUCTURAL REVIEW COMPLETE SENT CORRECTION 01/08/97
|
Routing - FIRE | 12/24/1996 | | 12/27/1996 | | FAIL |
|
|
|
PACKAGE #1
|
Routing - PLAN CHECK | 12/24/1996 | | 12/24/1996 | | |
|
|
|
PACKAGE #1
|
Routing - MECHANICAL | 12/19/1996 | | 12/24/1996 | | PASS |
|
|
|
PACKAGE #1 NO REVIEW FIELD VERIFY PER 337 12/24/96 DAR
|
Print Pending Permit.LaserJet4 | | | 12/19/1996 | | FAIL |
|
|
|
PARTICIAL CORRECTION READY WAITING FOR STRUCTURAL REVIEW TO RETURN PRIOR TO SENDING TO ARCHITECT.
|
Plan Reviewer's activity | | | 12/19/1996 | | FAIL |
|
|
|
WAITING FOR STRUCTURAL REVIEW TO RETURN PRIOR TO SEND COMPLETE CORRETION LIST OUT.
|
Plan assigned to (RGG) | 12/4/1996 | | 12/17/1996 | | |
|
|
|
|
Routing - ELECTRICAL | 12/13/1996 | | 12/17/1996 | | PASS |
|
|
|
PACKAGE #1 ELECTRICAL DRAWING NOT COMPLETE. (ITEMS NEEDED:) 1. ONE LINE OF SERVICE. 2. LOCATION OF PANEL (5) AND MAIN SERVICE. 3. GROUNDING (MIN. CONCRETE ELECTRODE) ELECT. INSP. WILL REVIEW AT TIME OF INSPECTION. RESUBMITALS REQUIRED AND WILL BE FIELD REVIEWED. KMM 12-17-96
|
Routing - PLUMBING | 12/17/1996 | | 12/17/1996 | | FAIL |
|
|
|
PACKAGE #1
|
Plan routing begun/NEW & ADDTN | | | 12/13/1996 | | PASS |
|
|
|
PRESTON OF BAKER CONSTRUCTION BROUGHT STRUC. CALCS., DRAINAGE CALCS., SOIL BEARING PRESSURE. SECTION SHEETS 6,7,10 AND FAUL ENGINEERING SHEETS ALL STAMPED AND SIGNED. PLANS ARE READY FOR ROUTING. KMM 12-13-96
|
Plan routing begun/NEW & ADDTN | | | 12/4/1996 | | HOLD |
|
|
|
PLAN ROUTING ON HOLD. WAITING FOR STURCTURAL CALCS. SOIL BEARING, DRAINAGE CALCS. SHEETS 6,7,10, AND FAULL ENG. NEED STAMPS AND SIGN. KMM 12-04-96 CONTACTED PRESTON BAKER AND INFORMED HIM OF THESE NEEDS. 12-03-96 KMM
|
Recd Pcfee & Taken To Pln CK | | | 12/2/1996 | | |
|
|
|
|
Application received | | | 12/2/1996 | | |
|
|
|
|
Gay Receipt For Partial Pay | | | 12/2/1996 | | |
|
|
|
|
Received Certificate of Value | | | 12/2/1996 | | PASS |
|
|
|
|