INSP - Final | 10/26/1998 | 10/26/1998 | 10/26/1998 | P | PASS |
|
|
|
10/26/98 338 - Final - St. Al's - 365 sq.ft. addn. fire riser rm. & elec. rm. made ok for c/o
|
Permanent occupancy | | | 10/26/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7473 issued 10-26-98 to St. Alphonsus Hospital for addns.
|
Permanent Occupancy | | 10/23/1998 | 10/23/1998 | | DONE |
|
|
|
|
INSP - Final | 10/16/1998 | 10/16/1998 | 10/16/1998 | A | PART |
|
|
|
10/19/98 338 - cecil -###-#### fn occ per perry at 10:30 made ok for tem
|
INSP - Final | 10/16/1998 | 10/16/1998 | 10/16/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - REINSP ALARM SYSTEM OK SPKLR SYSTEM ISSUES REMAIN
|
INSP-Final Inspection | 10/1/1998 | 10/5/1998 | 10/5/1998 | P | FAIL |
Joe Tawney
|
|
|
10/06/98 406 - CECIL ###-#### FINAL FAIL ALARM SYSTEM TEST
|
INSP-Conference | 5/7/1998 | 5/7/1998 | 5/7/1998 | P | PASS |
|
|
|
05/07/98 338 - made ok need drawings for backup on wall change details
|
INSP-Final Inspection | 1/9/1998 | 1/12/1998 | 1/12/1998 | P | PART |
Joe Tawney
|
|
|
01/12/98 406 - Cecil ###-#### 1st floor east end FINAL OK FOR TEMP OCC OF ROOM 1A
|
INSP-Supply line flush | 11/13/1997 | 11/13/1997 | 11/13/1997 | A | PASS |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND FLUSH OK ON OVERHEAD ROUGH IN OK TO COVER
|
INSP - Framing/Rough-in | 11/10/1997 | 11/12/1997 | 11/12/1997 | P | PASS |
|
|
|
ST. AL'S, EAST END, PARTIAL made ok to cover behind the ele insp passes
|
INSP - Wall cover | 9/25/1997 | 9/26/1997 | 9/26/1997 | A | PASS |
|
|
|
09/26/97 338 - parapet on the roof hope this is under the correct inspec block/stop is in place at the
|
INSP - Foundation | 7/29/1997 | 7/31/1997 | 7/31/1997 | A | PART |
|
|
|
07/31/97 338 - concrete canopy pouring/ emerg. entrance east end divisio insp MASN-REBAR OK
|
INSP - Footings | 7/31/1997 | 7/31/1997 | 7/31/1997 | | PASS |
|
|
|
/ / 338 - sp insp made ok MASN-REBAR OK
|
Issue PAID IN FULL permit | | | 5/30/1997 | | |
|
|
|
|
Telephone call | | | 5/28/1997 | | |
|
|
|
TOLD PAMELA PERMIT READY
|
Inspection Record Card- Bld | | | 5/28/1997 | | |
|
|
|
|
Print Occupancy Form | | | 5/28/1997 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/21/1997 | | 5/27/1997 | | PASS |
|
|
|
FAX FROM CRAIG BARRETT AT CH2MHILL INDICATES THAT THE STRUCTURAL REVIEW IS COMPLETE AND ACCEPTABLE.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/27/1997 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/27/1997 | | 5/27/1997 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 2/18/1997 | | 5/27/1997 | | PASS |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 4/25/1997 | | 5/19/1997 | | PEND |
|
|
|
CORRECTION LIST RECEIVED FROM CRAIG BARRET AT CH2MHILL. FAXED A COPY TO DAVE JOHNSON OF GERALD NICHOLS, REQUESTING STRUCTURAL REVISIONS.
|
Routing - FIRE | 4/22/1997 | | 4/22/1997 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/21/1997 | | 3/27/1997 | | PEND |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/7/1997 | | 3/26/1997 | | |
|
|
|
SENT TO CH2MHILL FOR REVIEW.
|
90 day tracking............. | | 12/24/1996 | 3/24/1997 | | |
|
|
|
|
Routing - FIRE | 3/18/1997 | | 3/21/1997 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 2/20/1997 | | 3/21/1997 | | |
|
|
|
|
Plan resubmittals requested | | | 3/17/1997 | | PEND |
|
|
|
CORRECTION LIST MAILED TO VINSON JOHNSON AT GERALD R. NICHOLS ARCHITECTS.
|
Routing - PLUMBING | 2/19/1997 | | 2/20/1997 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 2/18/1997 | | 2/19/1997 | | PASS |
|
|
|
|
Plan assigned to (RGG) | 1/2/1997 | | 2/18/1997 | | |
|
|
|
|
Routing - ELECTRICAL | 2/4/1997 | | 2/14/1997 | | PASS |
|
|
|
NO PLAN CHECK, FIELD REVIEW ONLY PER 324
|
Routing - MECHANICAL | 1/30/1997 | | 2/4/1997 | | PASS |
|
|
|
NO REVIEW, FIELD VERIFY.
|
Routing - PLUMBING | 1/27/1997 | | 1/30/1997 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 1/15/1997 | | 1/27/1997 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN. BM
|
Routing Off Site - A.C.H.D | 1/8/1997 | | 1/8/1997 | | PASS |
|
|
|
CONTACTED MARK KRIZENBECK AT###-#### TO TAKE PLANS OUT TO ACHD PLANS APPROVED AND IMPACT CERTIFICATE #97-0431
|
Routing - PLANNING | 12/27/1996 | | 1/7/1997 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 12/24/1996 | | 1/2/1997 | | |
Marlene Southard
|
|
|
|
Gay Receipt For Partial Pay | | | 12/24/1996 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/24/1996 | | |
|
|
|
|
Application received | | | 12/24/1996 | | |
|
|
|
|