Permit Information
Permit NumberBLD96-03372
StatusFinaled
Name GSA
Site Address 1249 S VINNELL WAY
Project NameBLM BLDG
Customer Number 
ePlanReviewNo
Description
To finish an existing area of 11,674 sq. ft. for use as offices and support areas for the Social Security Administration. All framing to be of noncombustible materials covered with fire code sheetrock. To install a new suspended ceiling system. Separate electrical, plumbing & mechanical permit s are required. This building is fully fire sprinklered & shall be maintained per NFPA #13. All per approved plans, notes & attachments. PC#774-96/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  4/28/2010 DONE
Permanent Occupancy 9/10/19979/10/1997 DONE
Details
CHANGE STATUS TO (D)  9/10/1997
INSP - Final9/3/19979/4/19979/4/1997APASS
Details
09/04/97 338 - SIGNED THE PERM COL OF THE OCC REC FORM
INSP - Final8/28/19979/2/19979/2/1997PNH
Details
09/02/97 338 - no access
INSP-Final Inspection8/25/19978/26/19978/27/1997PPASS
DetailsJoe Tawney
08/26/97 406 - REINSP FOR FINAL OK FOR PERM OCC
INSP-Final Inspection8/4/19978/7/19978/8/1997PFAIL
DetailsJoe Tawney
08/07/97 406 - 4:30 FINAL FAIL ALARM SYSTEM
INSP-Final Inspection7/22/19977/24/19977/25/1997PCANC
DetailsJoe Tawney
07/24/97 406 - CANCELLED
INSP-Final Inspection6/13/19976/17/19976/17/1997APART
DetailsJoe Tawney
06/17/97 406 - PARTIAL FOR TEMPORARY. MIKE MASON - 1-###-####. OK FOR TEMP OCC DOOR CLOSER SMOKE SEALS HORN/STROBES EMERG LIGHTS
90 day tracking............. 12/30/19963/30/1997 PEND
INSP - Framing/Rough-in3/19/19973/19/19973/18/1997PNR
Details
03/19/97 338 - out of time no one on site after 3:30 will do # 1 03/20/9
INSP - Framing/ Rough-in3/18/19973/18/19973/18/1997 PART
Details
/ / 338 - partial ok with ele approval
Issue PAID IN FULL permit  3/7/1997
Plan assigned to (DRS)1/8/1997 3/3/1997 PASS
DetailsDan Stuart
03/03/97 09:56:38 DRS - this action updated by action script from <<>> in Case No. BLD96-3372
Plan Reviewer's activity  3/3/1997
Inserted resubmittals into the original plans and began review and transfer of notes to new sheets as required.
Print Pending Permit.LaserJet4  3/3/1997 PASS
Telephone call  3/3/1997
Inspection Record Card- Bld  3/3/1997
Routing - PLAN CHECK2/28/1997 3/3/1997 PASS
Completed review of resubmittals and preparation of plans for processing for issuance of permit. Mechanical sheets reviewed notes on plans - to be reviewed and approved in field by mechanical inspector. As of staff meeting on 02/27/97 we are the City is enforcing the 1991 UBC until the 1997 is adopted and we are not asking for new submittal sheets, just making the architect aware of possible problems and leaving the review and approval to the field inspector.
Print Occupancy Form  3/3/1997
PLANS/APPL TAKEN TO FRONT DESK  3/3/1997 PASS
Routing - PLAN CHECK1/31/1997 2/28/1997
Stared review of new resubmittals received from Tim Wilcomb.
Plan resubmittals received  2/25/1997
Plan resubmittals received from Tim Wilcomb of Jordan Wilcomb Construction. Will review as soon as job under review is completed.
INSP-Sprinkler Rough-in/Hydro2/19/19972/21/19972/21/1997APART
DetailsJoe Tawney
02/21/97 406 - JIM - ###-#### OK FOR UNDERGRND HYDRO TEST OK TO COVER FIRST FLOOR
CHANGE STATUS TO (I)  2/20/1997
Telephone call  2/12/1997
Call from Steve Hardy, mechanical engineer for the 1249 S Vinnell Way SSA office project. Question concerning the plan review comment on automatic smoke detection shut down of Air-moving equipment when exceeding 2000 CFM to interconected areas. I reviewed this requirement with him based on Sec. 608 1994 UMC and definition in Sec 203. He asked me when we had adopted the 1994 UMC and I explained that the way the ordinance is written the city adopts the latest edition of the UMC. I also told him that we were told this did not mean the 1997 edition that has just come out.
Plan Reviewer's activity  2/4/1997
Received fax from Brett Tullis asking for review of proposal on realignment of corridor/ room wall, 146 to make this area a part of the proposed room 147 and not an exit corridor. Also a layout for the exiting from rooms 148, 149 & 150, one into an extension of the existing corridor and one through an adjoining room. I requested further clarification on the exiting from Rooms 148, 149 & 150 based on the requested occupant load factor to be used for these rooms. The widening of the extension of room 147 was approved as requested by architect.
Routing - FIRE1/27/1997 1/31/1997 PASS
TO PC
Plan resubmittals requested  1/24/1997
Faxed & mailed copy of preliminary plan review to architect. Routing plans to fire dept. for review while waiting for response.
Routing - PUBLIC WORKS1/8/1997 1/10/1997 PASS
Telephone call  1/9/1997
told tim wilcomb partial permit ready to pick up
Inspection Record Card- Bld  1/9/1997
Print Pending Permit.LaserJet4  1/9/1997 \
Print Pending Permit.LaserJet4  1/9/1997
Plan Reviewer's activity  1/9/1997
PARTIAL PERMIT ISSUED 01/09/97 AT REQUEST OF DPLUMBING CONTRACTOR, KENNY CALKINS, CLOVERDALE PLUMBING.
Issue FEE-DUE permit  1/9/1997
Plan routing begun/TENANTS  1/8/1997
Route to PUBLIC WORKS then back to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT.
Application received  12/30/1996
Recd Pcfee & Taken To Pln CK  12/30/1996 PEND
Gay Receipt For Partial Pay  12/30/1996