Permanent Occupancy | | 4/30/1997 | 4/30/1997 | | DONE |
|
|
|
|
INSP - Final | 4/29/1997 | 4/30/1997 | 4/30/1997 | P | CANC |
Jim Storey
|
|
|
04/29/97 301 - trans to kim 4th south end.
|
Permanent occupancy | | | 4/30/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6846 issued 4-30-97 to GST Telecom.
|
INSP-Final Inspection | 4/28/1997 | 4/29/1997 | 4/29/1997 | A | PASS |
|
|
|
ALARMS TESTED, BASEMENT SEPARATION OF TANK TESTED, PASS
|
90 day tracking............. | | 1/21/1997 | 4/21/1997 | | |
|
|
|
|
INSP-Final Inspection | 4/17/1997 | 4/17/1997 | 4/17/1997 | A | FAIL |
|
|
|
3rd floor corridor requirements and basement diesel tank requirements NOT MET
|
INSP-Sprinkler Rough-in/Hydro | 4/16/1997 | 4/16/1997 | 4/16/1997 | P | PASS |
|
|
|
1pm pre-action system test system trip test ok, need to connect fm 200 smoke detectors to building supervisory since panel location is not constantly attended and signal is not sent to approved central station. will check w/ final
|
INSP - Framing/Rough-in | 4/8/1997 | 4/9/1997 | 4/8/1997 | P | PASS |
|
|
|
04/09/97 333 - GRID 3 RD FLOOR SCLG-OK SUSPENDED CEILING
|
INSP-Conference | 3/26/1997 | 3/26/1997 | 3/26/1997 | A | PART |
|
|
|
delivered notice of violation to roger of merrill. Discussed possible ways to correct.
|
INSP - Final | 3/21/1997 | 3/25/1997 | 3/25/1997 | A | FAIL |
|
|
|
gst 4th flr not complete, want to use fm 200 in place of sprinklers, plans called for fm200 to be additional. alarms not connected, corridor doors not installed. advised Roger w/ Merrill to drop sprinklers into space or request approval of fm200 as a replacement system from the fire chief.
|
INSP - Ceiling grid | 3/6/1997 | 3/7/1997 | 3/6/1997 | A | PASS |
|
|
|
03/07/97 333 - 4TH FLOOR SCLG-OK SUSPENDED CEILING
|
INSP - Framing/Rough-in | 2/24/1997 | 2/24/1997 | 2/23/1997 | P | PASS |
|
|
|
02/24/97 333 -
|
Plan assigned to (DRS) | 2/3/1997 | | 2/21/1997 | | PASS |
Dan Stuart
|
|
|
02/21/97 15:36:12 DRS - this action updated by action script from <<>> in Case No. BLD97-0110
|
Inspection Record Card- Bld | | | 2/21/1997 | | |
|
|
|
|
Print Occupancy Form | | | 2/21/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 2/21/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/21/1997 | | PASS |
|
|
|
Approved with notes and attachments to contractor
|
Print Pending Permit.LaserJet4 | | | 2/21/1997 | | PASS |
|
|
|
|
Telephone call | | | 2/21/1997 | | |
|
|
|
Phone call to Brett Cato concerning a fire stop assembly that was not noted in his response. I sent him a copy of one since he did not have the 1995 UL Directory, for him to approve and send back. I also noted to him by phone that the fire dept. concerns about spill control and ventilation within the battery storage room. Brett said he had knowledge of ways to accompolish this and would comply if required.
|
Plan resubmittals received | | | 2/21/1997 | | |
|
|
|
Received resubmittals for mechanical plans, fire stop fax from Brett Cato and comments on preliminary plan review items.
|
Print Pending Permit.LaserJet4 | | | 2/21/1997 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 2/11/1997 | | |
|
|
|
Finsihed preliminary plan review for the project and faxed a copy to Brett Cato as well as mailing him a hard copy. Plans will be forwarded to Fire Dept. for review while waiting for architects response.
|
Print Pending Permit.LaserJet4 | | | 2/11/1997 | | FAIL |
|
|
|
Waiting for response from architect on plan review items needing details and or clarification.
|
Additional plans submitted | | | 2/11/1997 | | |
|
|
|
Roger of Merrill Contractors brought in two copies of the mechanical plans and left with Dave Radford. The plans were unstamped - noted because this had been the problem causing delays of permit review per the contractor when the he had tried to turn the plans in a week ago ????
|
Routing - PLAN CHECK | 1/24/1997 | | 2/11/1997 | | |
|
|
|
Routing to Fire dept. Comments for architect response faxed and mailed to architect.
|
Telephone call | | | 2/10/1997 | | |
|
|
|
Late A.M. Call to Brett Cato of Fraley/Stricker Architects to clarify detail on plan for wall construction at the H3 Fuel Tank Storage Room Occupancy in the basement and to let him know I had not received the mechanical plans on Friday, Feb. 7, 1997 as I had been told I would. He was not available at the time of my call but his secretary said she would have him call.
|
Telephone call | | | 2/10/1997 | | |
|
|
|
Brett Cato returned my call. I asked about the wall detail on Sheet A4, which walls the detail applied to represented? Not the rated walls - they would run from floor to deck. The use of the switch room was mechanical with possibly two staff personel. I told him I had not received the mechanical plans and I had not been able to find out who had rejected them and that at this time a mechanical stamp by a licensed Idaho Mech Eng was not required. Brett said he woild follow up on getting the mechanical plans turned in.
|
Telephone call | | | 2/7/1997 | | |
|
|
|
Call to Brett Cato concerning the specific uses of the 4th flor switch gear rooms, what the FM200 Tanks were, information on the battery storage units and the call out on the plans for a 2-hour wall arounf the new room - reason for requirement and how the wll was to be protected at openings and penetrations. Also discussed with Brett that there may be future complications with exiting from the balcony area adjoining the East end of the tenant space depending on the use of the area by his customer or a possible future restaurant. If the restaurant uses all the space then they amy not want his office to have access to the area. If a means to prevent access to the restaurant area is installed in line with the tenants North wall accross the terrace, a n exit will have to be available back through the tenant space and a door will have to have proper hardware per section 1004.3 UBC. Mr. Cato said he understood and would make his client aware of the circumstances.
|
Plan resubmittals received | | | 2/7/1997 | | |
|
|
|
Recieved written clarrification from Brett Cato on the uses of the rooms in the Switch Room, information on the batteries (for fire dept. review) and the FM200 Fire Suppression Tanks.
|
Plan resubmittals received | | | 2/4/1997 | | |
|
|
|
Received revision to plans concernign seismic bracing from Brett.
|
Plan resubmittals received | | | 2/3/1997 | | |
|
|
|
Received fax note from Brett with cut sheet for fuel tank, clarification on location of mechanical equipment in relationship to new vestibule entry from garage to 3rd floor, and a note that the mechanical engineer had applied to Idaho for a temporary license so he could stamp the plans.
|
Telephone call | | | 2/3/1997 | | |
|
|
|
Call to Brett Cato concerning specifications on the fuel tank, location of mechanical equipment in parking garage in relation to the new vestibule access from the third floor to the parking garage, mechanical plans for the project and a note on the plans concerning seismic bracing at 8 feet o.c. - I refered him to UBC Standard 25-2 for review for ceiling bracing. Brett said he would respond ASAP.
|
Plan assigned to (CJW) | 1/22/1997 | | 2/3/1997 | | |
Carl Westfall
|
|
|
|
Routing - PUBLIC WORKS | 1/22/1997 | | 1/24/1997 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 1/22/1997 | | |
|
|
|
Route to PUBLIC WORKS then back to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT.
|
Application received | | | 1/21/1997 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/21/1997 | | |
|
|
|
|
Gay Receipt For Partial Pay | | | 1/21/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 2/21/1997 | | 1/21/1997 | | PASS |
|
|
|
Plan review done by Fire dept. Mechanical plan resubmittals and notes & plans from architect inserted into plans and reviewed for compliance with plan review comments.
|