Office final | 5/7/1997 | 5/7/1997 | 5/7/1997 | | PASS |
|
|
|
finaled by 316 5/2/97.
|
Letter of compliance | | | 5/7/1997 | | PASS |
|
|
|
issued #13446 c of c by mjw this date.
|
CHANGE STATUS TO (D) | | | 4/29/1997 | | PASS |
|
|
|
|
90 day tracking............. | | 1/24/1997 | 4/24/1997 | | |
|
|
|
|
INSP - Final | 4/3/1997 | 4/3/1997 | 4/3/1997 | P | FAIL |
Jim Sly
|
|
|
04/03/97 316 - Cannot find any structure etc. at this location........Ne information at time of inspection request.
|
Print Occupancy Form | | | 3/27/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/3/1997 | | |
|
|
|
|
Plan assigned to (PRP) | 2/18/1997 | | 2/24/1997 | | PASS |
|
|
|
PLAN CHECK DONE, ROUTED TO FIRE-2-19-97 02/24/97 14:05:16 PRP - this action updated by action script from <<>> in Case No. BLD97-0140
|
Routing - FIRE | 2/19/1997 | | 2/24/1997 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/24/1997 | | PASS |
|
|
|
ISSUE
|
Telephone call | | | 2/24/1997 | | |
|
|
|
PERMIT READY, FEE DUE. TALKED TO DALE
|
Print Occupancy Form | | | 2/24/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/24/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 2/19/1997 | | PASS |
|
|
|
REVIEW PLANS, CALL PROJECT MANAGER ABOUT THE SHELTER TYPE AND IF PART OF PROJECT, MARK-UP, FORWARD TO FIRE.
|
Telephone call | | | 2/19/1997 | | PASS |
|
|
|
CALLED MIKE LANDON ABOUT PROJECT.
|
Print Pending Permit.LaserJet4 | | | 2/19/1997 | | PASS |
|
|
|
FILES
|
Plan assigned to (RGG) | 1/27/1997 | | 2/18/1997 | | |
|
|
|
|
Telephone call | | | 2/18/1997 | | PEND |
|
|
|
CALLED DAVID BRINKER OF UNR-ROHN TO CLEARIFY BACKFILL OF ANTENNA REQUIREMENTS. IT IS OK TO FOLLOW THE REDESIGN DONE BY NOEL HARGRAVE-THOMAS OF "G-2" FOR BACKFILLING.
|
Routing - PLANNING | 2/13/1997 | | 2/13/1997 | | PASS |
|
|
|
X-ref: Zoning Certificate @ 6260 Eagle Rd. Approved by GRH.
|
Routing - PUBLIC WORKS | 2/10/1997 | | 2/13/1997 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 1/27/1997 | | 2/10/1997 | | PASS |
|
|
|
CONTACTED DALE RAYNOR AT ###-#### TO TAKE PLANS OUT TO ACHD.
|
Plan routing begun/NEW & ADDTN | | | 1/27/1997 | | PASS |
|
|
|
|
Received Certificate of Value | | | 1/27/1997 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 1/27/1997 | | |
|
|
|
|
Application received | | | 1/24/1997 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/24/1997 | | |
|
|
|
|
Gay Receipt For Partial Pay | | | 1/24/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 2/14/1997 | | | | |
|
|
|
|
Routing - PLAN CHECK | 2/24/1997 | | | | |
|
|
|
|