Case Summary (BLD) | | | 5/10/2005 | | |
|
|
|
|
(F) Reprint permit | | | 5/10/2005 | | DONE |
|
|
|
|
Fee Review-notes | 7/15/1998 | | 11/18/1998 | | DONE |
|
|
|
|
Permanent Occupancy | | 4/3/1998 | 4/3/1998 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/3/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7189 issued 4-3-98 to Edwards Theater Circuit, Inc.
|
INSP - Final | 4/1/1998 | 4/1/1998 | 4/1/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
INSP - Final | 3/31/1998 | 4/1/1998 | 4/1/1998 | P | PASS |
|
|
|
04/01/98 338 - signed the occ req card fior the final occ . calle d cont
|
INSP-Alarm Testing | 3/17/1998 | 3/19/1998 | 3/19/1998 | A | PART |
Joe Tawney
|
|
|
03/19/98 406 - Don Walker - ###-#### - he would like for you to be there to do the alarm testing (before the box ofc. opens at 10:00) OK ON ALARM TEST NEED LETTER ON CHANGING H/S AND CENTR STAT CERTIFICATIO
|
Code Occupancy Approval | | | 3/18/1998 | | PASS |
|
|
|
Inspected for final - mets compliance w/ DR-93-96 - executed Bond Release. CAM
|
Temporary occupancy | | | 3/12/1998 | | PASS |
|
|
|
2nd Temp. Occ. Cert. #3571 issued 3-11-98 to Edwards 21 Cinemas for an addl. 60 days.
|
PubWorks Occupancy Approval | | | 3/4/1998 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 3/4/98. R.Rokovitz
|
INSP-Conference | 1/20/1998 | 1/20/1998 | 1/20/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - TESTED NEW SPEAKER/STROBE OK ON DB LEVEL MUST RETAIN SAME CA
|
INSP - Final | 1/8/1998 | 1/8/1998 | 1/8/1998 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - REINSP FOR PERM OCC FAIL VOICE EVAC DB TOOLOW OCC LOAD SIGNS
|
INSP - Temporary occupancy | 12/18/1997 | 12/18/1997 | 12/18/1997 | P | PASS |
|
|
|
12/18/97 338 - signed temp col of this card other agencies made ok
|
INSP - Final | 12/17/1997 | 12/17/1997 | 12/17/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - FINAL OK FOR TEMP OCC AND ASSEMBLY PERMIT
|
Temporary occupancy | | | 12/17/1997 | | PASS |
|
|
|
Temp. Occ. Cert. #3520 issued 12-17-97 to Edwards 21 Cinemas.
|
INSP - Final | 12/16/1997 | 12/16/1997 | 12/16/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - ALARM FINAL PARTIAL OK NEED 5 MIN BAT TEST EMERG GEN TEST EL
|
INSP-Sprinkler Rough-in/Hydro | 12/10/1997 | 12/12/1997 | 12/12/1997 | A | PART |
Rick Jackson
|
|
|
12/12/97 409 - after 10:00 she will call completed hydro - pass. will do the flow test on Tuesday with fire alar testing.
|
INSP - Conference | 12/5/1997 | 12/5/1997 | 12/5/1997 | | PART |
|
|
|
/ / 338 - misc corrections 2 hrs
|
INSP-Conference | 12/4/1997 | 12/4/1997 | 12/4/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - CHECKED FIRE EXT LOCATIONS AND FOUND LOCATIONS TO BE ACCEPTA
|
INSP-Conference | 12/2/1997 | 12/2/1997 | 12/2/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - CONF ON ALARM SYSTEM AND SMOKE/FIRE DAMPERS REQ SUBMITTAL ON
|
INSP-Conference | 11/25/1997 | 11/25/1997 | 11/25/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - INSPECTED SMOKE/FIRE DAMPERS NEED ACCESS OPENINGS AND INFO O
|
INSP-Sprinkler Rough-in/Hydro | 11/14/1997 | 11/17/1997 | 11/17/1997 | A | PART |
Joe Tawney
|
|
|
11/17/97 406 - THEATER OK ON ROUGH IN OF FRONT ENTRANCE AREA
|
INSP-Sprinkler Rough-in/Hydro | 10/30/1997 | 10/31/1997 | 10/31/1997 | A | PART |
Joe Tawney
|
|
|
10/31/97 406 - OK ON SPKLR ROUGH IN ON WEST SIDE LOWER LEVEL & LOWER CEN
|
INSP-Conference | 10/30/1997 | 10/30/1997 | 10/30/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - PRE FINAL CONFERENCE WITH ALL INSPECTORS
|
INSP-Conference | 10/23/1997 | 10/23/1997 | 10/23/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - CONF WITH HARRY & ANELL ABOUT FIRE EXT PLACEMENT IN THEATRE
|
INSP-Sprinkler Rough-in/Hydro | 10/14/1997 | 10/15/1997 | 10/15/1997 | A | PART |
Joe Tawney
|
|
|
10/15/97 406 - OK ON ROUGH IN FOR UPSTAIRS AREA AND EAST SIDE DOWNSTAIRS
|
INSP-Sprinkler Rough-in/Hydro | 9/30/1997 | 9/30/1997 | 9/30/1997 | P | FAIL |
Joe Tawney
|
|
|
09/30/97 406 - EDWARDS CINEMA spklr rough in fail SWAY BRACING HANGERS & STRAPS RELOCATE MAINS
|
INSP-Sprinkler Rough-in/Hydro | 9/24/1997 | 9/25/1997 | 9/25/1997 | A | CANC |
Rick Jackson
|
|
|
nobody on-site knew why we were requested
|
INSP - Conference | 9/22/1997 | 9/22/1997 | 9/22/1997 | P | PASS |
Tom Arcoraci
|
|
|
|
INSP-Supply line flush | 9/15/1997 | 9/15/1997 | 9/15/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND FLUSH
|
INSP-Sprinkler Rough-in/Hydro | 9/11/1997 | 9/12/1997 | 9/12/1997 | A | NR |
Joe Tawney
|
|
|
09/12/97 406 - underground flush NOT READY RESCH
|
INSP - Framing/Rough-in | 8/26/1997 | 8/27/1997 | 8/28/1997 | A | PART |
|
|
|
08/28/97 338 - WALKED TH SITE WITH RANDY, GOOD INSP. ONLY 40 PERSONS OR QUESTIONS ABOUT THE ELEVATOR SHAFT RE SETTING 1-HOUR 15 MIN
|
INSP - Framing/Rough-in | 8/18/1997 | 8/18/1997 | 8/18/1997 | | PASS |
|
|
|
08/18/97 338 - partial made ok verbal requirement for the minimum lap fo metal studs. what is used on the south west corner appears to be un acceptable.
|
INSP - Framing/Rough-in | 8/18/1997 | 8/18/1997 | 8/18/1997 | | PASS |
|
|
|
08/18/97 338 - partial made ok verbal requirement for the minimum lap fo metal studs. what is used on the south west corner appears to be un acceptable.
|
INSP-Conference | 5/12/1997 | 5/12/1997 | 5/12/1997 | P | PASS |
Joe Tawney
|
|
|
05/12/97 406 - CONFERENCE 2:00 PM DISCUSSED FD PLAN REVIEW AND REQUIREMENT FOR ALARM SYSTEM SUBMITTAL
|
90 day tracking............. | | 2/7/1997 | 5/8/1997 | | |
|
|
|
|
(F) Reprint permit | | | 5/6/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/5/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 4/9/1997 | | 5/2/1997 | | PASS |
|
|
|
PACKAGE #2
|
Routing - PLAN CHECK | 4/11/1997 | | 5/2/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLAN CHECK | 4/1/1997 | | 5/2/1997 | | PASS |
|
|
|
PACKAGE #4
|
Plan assigned to (JCM) | 2/26/1997 | | 5/2/1997 | | |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/2/1997 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 5/2/1997 | | |
|
|
|
|
Print Occupancy Form | | | 5/2/1997 | | |
|
|
|
|
Telephone call | | | 5/2/1997 | | |
|
|
|
PERMIT READY, FEE DUE, CALLED MCALVAIN
|
Plan resubmittals received | | | 4/24/1997 | | PASS |
|
|
|
PLANS APPROVED FOR ISSUE. FINAL PLAN REVIEW COMMENT LIST MAILED TO RICK OVERLEY AT PERKOWITZ+RUTH ARCHITECTS, INC.
|
Plan resubmittals requested | | | 4/21/1997 | | PEND |
|
|
|
RESUBMITTALS REQUESTED BY FAX AND MAIL TO RICK OVERLY OF PERKOWITZ+RUTH.
|
Routing - ELECTRICAL | 4/10/1997 | | 4/11/1997 | | PASS |
|
|
|
PACKAGE #1
|
Plan resubmittals received | | | 4/10/1997 | | PEND |
|
|
|
RECEIVED ELECTRICAL RESUBMITTALS STAMPED WITH ELECTRICAL ENGINEER STEPHEN R. ZAJICEK CALIFORNIA ELECTRICAL ENGINEERS STAMP AND HIS IDAHO STATE TEMPORARY NUMBER. DAR
|
Routing - PLAN CHECK | 4/9/1997 | | 4/10/1997 | | |
|
|
|
PACKAGE #1
|
Routing - PUBLIC WORKS | 4/4/1997 | | 4/9/1997 | | PASS |
|
|
|
PACKAGE #2
|
Routing - FIRE | 3/4/1997 | | 4/9/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLANNING | 3/17/1997 | | 4/3/1997 | | PASS |
|
|
|
PACKAGE #2 X-ref: CU-44-96, DR-93-96. Approved by RC & MS.
|
Plan resubmittals requested | | | 4/2/1997 | | PEND |
|
|
|
FAXED RICK OVERLY THE PLAN REVIEW COMMENT LIST. THIS LIST IS COMPLETE WITH THE EXCEPTION OF THE A2.1 THEATER EXITING CONCERNS. AN UPDATED VERSION WILL BE SENT AFTER THESE CONCERNS HAVE BEEN RESOLVED.
|
Routing Off Site - A.C.H.D | 2/10/1997 | | 4/1/1997 | | PEND |
|
|
|
PACKAGE #4 CONTACTED RICK OVERLEY AT ###-#### TO TAKE PLANS OUT TO ACHD MARKUS GREEN CALLED AND ADVISED THAT ACHD APPROVED THE CONSTRUCTION OF THE ACTUAL BUILDING BUT NOT OF GRADING AND DRAINAGE OF THE SITE. A PROBLEM EXISTS ON ROAD DRAINAGE. FEES NOT PAID.
|
Routing Off Site - STRUCTURAL | 3/20/1997 | | 3/31/1997 | | PASS |
|
|
|
PLAN REVISTIONS REVIEWED AND APPROVED BY ATWOOD-HINZMAN-JONES (DAVID HAUGLAND)
|
Plan Reviewer's activity | | | 3/28/1997 | | PEND |
|
|
|
FAXED RICK OVERLEY A PARTIALLY FINISHED PLAN REVIEW TO LET HIM BEGIN TO MAKE THE REQUIRED PLAN REVISIONS WHILE I FINISHED THE PLAN REVIEW PROCESS.
|
Plan Reviewer's activity | | | 3/28/1997 | | PEND |
|
|
|
FAXED A PARTIALLY COMPLETED PLAN REVIEW LIST TO RICK OVERLY AT PERKOWITZ & RUTH SO HE COULD START THE REQUIRED PLAN CORRECTIONS WHILE THE REMAINDER OF THE CORRECTION LIST WAS BEING COMPLETED.
|
Routing - PLAN CHECK | 2/25/1997 | | 3/20/1997 | | PEND |
|
|
|
PACKAGE #3
|
Routing - PUBLIC WORKS | 3/3/1997 | | 3/14/1997 | | FAIL |
|
|
|
PACKAGE #2
|
Routing - PLAN CHECK | 2/26/1997 | | 3/4/1997 | | PEND |
|
|
|
PACKAGE #1
|
Routing Off Site - C.D.H | 2/10/1997 | | 3/3/1997 | | PASS |
|
|
|
PACKAGE #2 CONTACTED RICK OVERLEY AT ###-#### TO TAKE PLANS OUT TO CDH
|
Plan resubmittals received | | | 3/3/1997 | | PASS |
|
|
|
RESUBS. FOR CDH SENT OUT TO BUD FULLERTON VIA PDQ
|
Plan assigned to (RGG) | 2/10/1997 | | 2/26/1997 | | |
|
|
|
|
Routing - PLUMBING | 2/21/1927 | | 2/25/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing Off Site - STRUCTURAL | 2/10/1997 | | 2/24/1997 | | PEND |
|
|
|
PACKAGE #3 CONTACTED PDQ TO TAKE PLANS OUT TO ATWOOD HINZMAN & JONES REVISIONS REQUESTED BY ATWOOD-HINZMAN-JONES (DAVID HAUGLAND) CORRECTION LIST FORWARDED TO GCI ENGINEERS FOR REQUIRED REVISIONS.
|
Routing - ELECTRICAL | 2/18/1997 | | 2/21/1997 | | FAIL |
|
|
|
PACKAGE #1
|
Routing - MECHANICAL | 2/10/1997 | | 2/18/1997 | | PASS |
|
|
|
PACKAGE #1 NO PLAN REVIEW, FIELD VERIFY.
|
Plan routing begun/NEW & ADDTN | | | 2/10/1997 | | PASS |
|
|
|
|
Received Certificate of Value | | | 2/10/1997 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 2/10/1997 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/7/1997 | | |
|
|
|
|
Gay Receipt For Partial Pay | | | 2/7/1997 | | |
|
|
|
|
Application received | | | 2/7/1997 | | |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|