Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD97-00320
StatusFinaled
Name SKIP WINGFIELD
Site Address 8555 W HACKAMORE DR
Project NameK2 (CORPORATE)
Customer Number 
ePlanReviewNo
Description
(K2 CORPORATE OFFICE)(K2 CONSTRUCTION INC.) THE FIRST BUILDING IS TO CONSTRUCT A NEW 2 STORY 17900 SQUARE FOOT OFFICE BUILDING WITH ONLY THE SECOND FLOOR FINISHED. CONSTRUCTION TO BE ALL NONCOMBUSTIBLE MATERIALS, CONCRETE FOUNDATION AND FLOOR SLABS, STEEL (DELTA JOIST),CONCRETE BLOCK AND BRICK VENEER EXTERIOR AND STRUCTURAL STEEL SUPPORT COLUMNS AND BEAMS, INTERIOR TO BE SHEET ROCKED AND SUSPENDED CEILINGS AND FINISHED RESTROOMS BOTH FLOORS. SECOND FLOOR ONLY TO HAVE INTERIOR PARTITIONS, DOORS AND INTERIOR GLAZING. NOTE! THIS BUILDING IS FULLY FIRE SPRINKLERED AND IS USED FOR ONE-HOUR SUBSTITUTION. THE SECOND BUILDING IS A PRE-ENGINEERED STEEL BUILDING WITH 3876 SQUARE FEET WAREHOUSE BUILDING. THIS BUILDING IS NON-SPRINKLERED AND NO INTERIOR FINISH, ALL LOCATED ON A CONCRETE FOUNDATION AND FLOOR SLAB. ALL PER APPROVED PLANS ON FILE. DR#77-96 PC#064-97
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 11/21/199711/21/1997 DONE
Details
Permanent occupancy  11/21/1997 PASS
Perm. Occ. Cert. #7058 issued 11-21-97 to K2 Construction.
INSP - Final11/20/199711/20/199711/20/1997PPASS
Details
signed the final col perm out building ok also
INSP - Final11/20/199711/20/199711/20/1997 PASS
DetailsJoe Tawney
/ / 406 - REINSP FOR FINAL OK FOR PERM OCC & CERT OF COMPLETION
INSP-Final Inspection11/18/199711/19/199711/19/1997AFAIL
DetailsJoe Tawney
11/19/97 406 - REINSP FOR FINAL FAIL SHUNT TRIP FOR ELEVATOR DID NOT WO
INSP-Final Inspection11/14/199711/14/199711/14/1997PFAIL
DetailsJoe Tawney
11/14/97 406 - REINSP FOR FINAL FAIL HEAT DET FOR SHUNT TRIP FIRE EXT CA
Routing for occupancy11/17/1997 11/13/1997 PASS
Approved by: Carol A. Montgomery (DR-77-96)
INSP-Final Inspection10/8/199710/10/199710/13/1997PPART
DetailsJoe Tawney
10/10/97 406 - FINAL OK FOR TEMP OCC ELEV SHUNT TAG EXT STRIPE CURBS SP
INSP - Final10/8/199710/10/199710/10/1997PPART
Details
10/10/97 338 - temp ok other agencies approved for temp only storage bui
INSP - Conference10/10/199710/10/199710/10/1997 PASS
Details
/ / 338 -
INSP - Framing/Rough-in10/6/199710/7/199710/6/1997APASS
Details
10/07/97 338 - CEILING GRID/ K2 OFFICE made ok except the front entry 1s check at the final insp
INSP - Carpentry10/3/199710/3/199710/3/1997 PASS
Details
/ / 338 - met with the ceiling grid man wants inspection as late as po
INSP - Framing/Rough-in10/2/199710/3/199710/3/1997PPASS
Details
10/03/97 338 - made ok GRID
INSP-Final Inspection10/2/199710/2/199710/2/1997PPART
DetailsJoe Tawney
10/02/97 406 - OK ON HYDRO TEST FOR SPKLR SYSTEM
(F) Reprint permit  9/29/1997
INSP-Supply line flush9/5/19979/5/19979/5/1997PPART
DetailsJoe Tawney
09/05/97 406 - OK ON UNDERGROUND FLUSH AND SPKLR SYSTEM ROUGH IN
INSP-Sprinkler Rough-in/Hydro9/5/19979/5/19979/5/1997PPART
DetailsJoe Tawney
09/05/97 406 - OK ON SPKLR SYSTEM ROUGH IN
INSP - Framing/Rough-in8/21/19978/22/19978/22/1997PPART
Details
08/22/97 338 - made ok to cover behind the plmg inspector will mnot cove
INSP - Conference8/6/19978/6/19978/6/1997 PASS
Details
/ / 338 -
INSP - Conference8/6/19978/6/19978/6/1997PPART
Details
08/06/97 338 - need details for stair support changes, sp insp on new ep details for colum wrap and termination and penetrations of same.need flo pene assys
INSP - Masonry7/16/19977/16/19977/16/1997PPASS
Details
07/16/97 338 - made ok MASN-REBAR OK
INSP - Masonry7/11/19977/14/19977/14/1997PPASS
Details
07/14/97 338 - not ready with the paperwork but ok t opour with the sp i topfinal bond beam
INSP - Masonry7/9/19977/10/19977/10/1997APASS
Details
07/10/97 338 - made ok with sp insp approval MASN-REBAR OK
INSP - Masonry7/8/19977/9/19977/9/1997APASS
Details
07/10/97 338 - re-bar MASN-REBAR OK OK WITH SP INSP APPROVAL
INSP - Masonry7/7/19977/8/19977/8/1997APASS
Details
07/08/97 338 - REBAR GROUT POUR MASN-REBAR OK
INSP - Masonry6/19/19976/20/19976/20/1997APART
DetailsTom Arcoraci
MASONRY REBAR...part, 338 area
INSP - Masonry6/19/19976/19/19976/19/1997PPASS
Details
06/19/97 338 - BLK.WALL & REBAR r-bar placed MASN-REBAR OK
INSP - Masonry6/17/19976/18/19976/18/1997APASS
Details
06/18/97 338 - REBAR AND BLK WALL MASN-REBAR OK
INSP - Masonry6/10/19976/11/19976/10/1997PPASS
Details
06/11/97 338 - BLOCK WALLS made ok r-bar placed
INSP - Masonry6/10/19976/10/19976/10/1997PNR
Details
06/10/97 338 - BLOCK WALLS LATE PM. NOT READY WILL REINSPECT FOR TOMORR
INSP - Foundation6/10/19976/10/19976/10/1997PPASS
Details
06/10/97 338 - FND. WALL
INSP - Masonry6/10/19976/10/19976/10/1997 PASS
Details
/ / 338 - MADE OK R-BAR PLACED
INSP - Foundation6/5/19976/6/19976/6/1997APASS
Details
06/06/97 338 - north west found walls ok
INSP - Foundation6/2/19976/3/19976/3/1997APASS
Details
06/03/97 338 - after 9 a.m. FDN -OK FOUNDATION
INSP - Footings6/2/19976/3/19976/3/1997APASS
Details
06/03/97 338 - after 9 a.m. FTG -OK FOOTING
INSP - Wall cover5/29/19975/30/19975/30/1997APASS
Details
05/30/97 338 - foundation of main building south wall
INSP - Footings5/23/19975/27/19975/27/1997PPASS
Details
05/27/97 338 - REBAR FOOTING/SLAB RIGHT AFTER LUNCH IF POSSIBLE good r-b dobies
INSP - Wall cover5/20/19975/21/19975/21/1997ACANC
Details
05/21/97 338 - was called in for a found insp for r-bar and steel placem
INSP - Conference5/21/19975/21/19975/21/1997 PASS
Details
/ / 338 - recieved change design to make the footing concrete thicker upper foundation wall form placing.
INSP - Foundation5/21/19975/21/19975/21/1997 PASS
Details
/ / 338 - r-bar placed forms erected ok to pour concrete.
INSP - Foundation5/21/19975/21/19975/21/1997 PASS
Details
/ / 338 - r-bar placed forms erected ok to pour concrete.
(F) Reprint permit  5/20/1997
90 day tracking............. 2/18/19975/19/1997 PEND
INSP - Footings5/14/19975/15/19975/15/1997PPASS
Details
05/15/97 338 - mad eok r-bar placed all buthe entry
(F) Reprint permit  5/15/1997
Print Pending Permit.LaserJet4  5/13/1997 PASS
Issue PAID IN FULL permit  5/13/1997
PLANS/APPL TAKEN TO FRONT DESK  5/13/1997 PASS
Inspection Record Card- Bld  5/13/1997
Print Occupancy Form  5/13/1997
Telephone call  5/13/1997 PASS
SHE WILL LET SKIP KNOW
Routing - PLAN CHECK4/10/1997 5/9/1997
PACKAGE #3
Routing - PLAN CHECK4/1/1997 5/9/1997
PACKAGE #2
Routing Off Site - STRUCTURAL4/23/1997 5/9/1997
PACKAGE #3 RESUBMITTALS TO STAPLEY ENGINEERING. KMM SHEETS S-1.1, S-1.2, S-2.1, S-2.3, S-2.4, ONE SHEET OF EACH. CONTACTED PDQ TO TAKE RESUBMITTAL SHEETS ABOVE TO STAPLEY
Routing - PLAN CHECK2/28/1997 5/9/1997
PACKAGE #1 INSERTED ONE SET OF ROOF STRCT. CALCS. 03-04-97
Routing - PLAN CHECK5/6/1997 5/9/1997
PACKAGE #1
Plan assigned to (RGG)2/20/1997 5/9/1997
PROJECT ON HOLD
Routing Off Site - A.C.H.D2/21/1997 5/8/1997 PASS
PACKAGE #4 CONTACTED SKIP AT ###-#### TO TAKE PLANS OUT TO ACHD ACHD FEES PAID 5/8/97 DAR
Routing - PUBLIC WORKS4/24/1997 5/6/1997 PASS
package #4
Routing - FIRE5/6/1997 5/6/1997 PASS
PACKAGE #1
Routing - PLANNING4/15/1997 4/23/1997 PASS
PACKAGE #2 X-ref: DR-77-96. Approved by MGS.
Routing Off Site - STRUCTURAL2/21/1997 4/10/1997
PACKAGE #3 CONTACTED PDQ TO TAKE PLANS OUT TO STAPLEY ENGINEERS SENT VIA PDQ 2 SETS OF ROOF STRUC. CALCS. TO STAPLEY ENGINEERS. KMM 03-04-97 RECEIVED REVISED STRUCTURAL REVIEW AND SENT TO STAPLEY ONE COPY AND FILED OTHER COPY. 04/07/97 SENTM RESUBS TO STRUCTURAL ENGINEER. DAR
Routing - PUBLIC WORKS3/27/1997 3/31/1997 FAIL
PACKAGE #2 RECEIVED REVISED C-1 AND C-2 SHEETS REQUIRES DRAINAGE PLAN REVISION PER BRIAN MURPHY. 4-1-97
Routing - PLAN CHECK3/25/1997 3/27/1997
package #2
Routing - PUBLIC WORKS3/23/1997 3/25/1997 FAIL
PACKAGE #2
Routing - PLAN CHECK3/7/1997 3/23/1997
PACKAGE #2
Plan Reviewer's activity  3/11/1997 HOLD
LETTER SENT TO K-2 CORPORATE OFFICE REQUIRING RESPONSES TO THE ENGINEERING CONCERNS.
Routing - PLANNING3/4/1997 3/6/1997 FAIL
PACKAGE #2 Applicant need to provide revised plans per DR conditions. Reviewed by MS.
Routing - PUBLIC WORKS2/21/1997 3/4/1997 FAIL
NEEDS DRAINAGE PLAN REVISION.
Routing - PLUMBING2/25/1997 2/28/1997 FAIL
PACKAGE #1
Routing - ELECTRICAL2/21/1997 2/25/1997 PASS
PACKAGE #1
Plans ACCEPTED BY PLAN CHECK  2/21/1997 PASS
Received Certificate of Value  2/21/1997 PASS
Plan routing begun/NEW & ADDTN  2/21/1997 PASS
Routing - MECHANICAL2/21/1997 2/21/1997 PASS
NO REVIEW FIELD VERIFY PACKAGE #1
Recd Pcfee & Taken To Pln CK  2/18/1997
Gay Receipt For Partial Pay  2/18/1997
Application received  2/18/1997