INSP - Letter of compliance | 4/24/1997 | 4/24/1997 | 4/24/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - c/c #13346
|
INSP - Letter of compliance | 4/24/1997 | 4/24/1997 | 4/24/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - c/c #13346
|
INSP - Final | 4/24/1997 | 4/24/1997 | 4/24/1997 | | PASS |
Alan Hauser
|
|
|
/ / 350 - final
|
INSP - Final | 4/22/1997 | 4/23/1997 | 4/22/1997 | P | PASS |
|
|
|
04/23/97 333 - no heating FNL -OK FINAL
|
INSP - Carpentry | 3/31/1997 | 4/1/1997 | 4/1/1997 | A | PASS |
Alan Hauser
|
|
|
04/01/97 350 - eng'g ok for trusses that were in question, interior gyp. for brace panels. ok to cover
|
INSP - Energy code compliance | 3/28/1997 | 3/28/1997 | 3/28/1997 | P | PART |
Carl Dependahl
|
|
|
03/28/97 340 - PART, NEED HI R AT HSE GAR WALL
|
INSP - Framing/Rough-in | 3/28/1997 | 3/28/1997 | 3/28/1997 | P | PART |
Carl Dependahl
|
|
|
03/28/97 340 - FRAME REINSPECT; PART, PENDIND ENG'S LETTER. OK TO COVER
|
INSP - Framing/Rough-in | 3/27/1997 | 3/27/1997 | 3/27/1997 | P | FAIL |
Carl Dependahl
|
|
|
03/27/97 340 - C/N,NEED TRUSS ENG'S OK OR FIX, BRACING, ETC. OK TO INSUL
|
INSP - Energy code compliance | 3/27/1997 | 3/27/1997 | 3/27/1997 | P | NR |
Carl Dependahl
|
|
|
03/27/97 340 - NR, AIR SEAL OK; NEED HVAC BOOTS IN & SEALED
|
Issue PAID IN FULL permit | | | 3/20/1997 | | |
|
|
|
|
Plan resubmittals received | | | 3/11/1997 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/11/1997 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/11/1997 | | PASS |
|
|
|
|
Telephone call | | | 3/11/1997 | | |
|
|
|
ANGIE CALLED
|
Inspection Record Card- Bld | | | 3/11/1997 | | |
|
|
|
|
Plan assigned to (DJO) | 2/21/1997 | | 3/11/1997 | | PASS |
Dan Overy
|
|
|
03/11/97 11:05:58 DJO - this action updated by action script from <<>> in Case No. BLD97-0367
|
Routing - PLAN CHECK | 2/28/1997 | | 3/11/1997 | | PASS |
|
|
|
|
INSP - Foundation | 3/7/1997 | 3/7/1997 | 3/7/1997 | P | PASS |
Alan Hauser
|
|
|
03/07/97 350 - FTNS OK, SETBACKS AS PER PLAN
|
Plan resubmittals requested | | | 3/4/1997 | | PEND |
|
|
|
request roof framing details, all headers and beams, and seperation requirements between garage and structure.
|
Plans ACCEPTED BY PLAN CHECK | | | 3/3/1997 | | PEND |
|
|
|
|
Routing - PLANNING | 2/25/1997 | | 2/28/1997 | | PASS |
|
|
|
Approved by MGH.
|
Routing - PUBLIC WORKS | 2/21/1997 | | 2/25/1997 | | PASS |
|
|
|
|
Application received | | | 2/21/1997 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 2/21/1997 | | |
|
|
|
|