Permit Information
Permit NumberBLD97-00401
StatusFinaled
Name HEWLETT PACKARD (BLDG. 6)
Site Address 11311 W CHINDEN BLVD
Project NameHP #6 - EAST/WEST
Customer Number 
ePlanReviewNo
Description
INKJET WAFER FAB AREA - To divide H.P. Building 6 into two buildings, East & West, with a 2-hour area separation wall. To create control areas within each building by use of one hour occupancy separation walls as well as between occupancies as listed in table 3-B. To remodel areas for use as an H-6 occupancy use, chemical storage areas and associated support facilities. Also to create manufacturing, office & assembly areas. The exterior mechanical exhaustsystem, smoke stacks & support structure on the South side of bldg are included in this permit. NOTE: This building is fully fire sprinklered. Structural elements through area separation wall as well as supporting structure are protected with two hour fire resistive, listed assemblies. All per approved plans, specs & attached plan review corrections. PC#081-97/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
CHANGE STATUS TO (FNL)  5/31/2001 FNL
C.O. #007264 issued 6/4/98, copy in records, Issued by 310
Permanent occupancy  5/31/2001 PASS
C.O. #007264 issued 6/4/98. Copy in records. Issued by 310.
Fee Review-notes7/14/1998 7/22/1998
Permanent Occupancy 6/4/19986/4/1998 DONE
Details
INSP - Final5/29/19986/3/19986/3/1998PPASS
DetailsCarl Dependahl
hp #6-dan hayes ###-####/ 2HR WALL FIRESTOPPED, HPM PIPING PROTECTED ACROSS COMPRESSOR ROOM & CORRIDOR TO H-6 BASEMENT; C/N OK,CARD TO CONTRACTOR FOR C/O
INSP - Final4/24/19984/24/19984/24/1998ANR
DetailsCarl Dependahl
NO INSP...CONF W/ TIM BASHFORD, KEEP C/N. CHK W/ FLOYD RE CHEMICAL ISSUES FOR OK OF HPM CORRIDOR.
INSP - Final3/13/19983/13/19983/13/1998ANR
DetailsCarl Dependahl
conf w/ dan hayes at hp, no insp
INSP - Framing/Rough-in2/11/19982/11/19982/11/1998PPART
DetailsCarl Dependahl
chk 2hr wall at chiller tank, if tank removed; wall redone??? TANK GONE, WALL REDONE; NEED FIRESTOP DETAILING
INSP - Conference2/4/19982/3/19982/3/1998PPASS
DetailsCarl Dependahl
W/ FLOYD; ALSO SPOKE W/ ERNIE HARPER RE STATUS OF JOB
INSP - Conference1/22/19981/22/19981/22/1998APASS
DetailsCarl Dependahl
W/ DAN STUART RE SUBMITTAL FROM ANDERSON CONST RE 1HR HPM PIPING ENCLOSURE...WILL MEET W/ CONT NEXT WEEK
FEE REVIEW-NOTES  12/23/1997 REFN
VALUE WENT DOWN. 13712.80 REFUND
INSP - Conference12/2/199712/2/199712/2/1997PPASS
DetailsCarl Dependahl
W/ FLOYD RE ALARM RESUBMITTAL
INSP - Carpentry11/7/199711/7/199711/7/1997APART
DetailsCarl Dependahl
FOLLOW UP OF CONF. W BRIAN PRICE 11-6-97; LEFT MSG W/ DAN HAYES AT SITE, WILL RECALL WHEN ALL RESUBMITTALS ARE IN. FLOYD REVIEWING CHEMICAL REPORT. SENT TO 316 IN ERROR 11-6-97.
INSP - Letter of compliance11/6/199711/6/199711/7/1997 CANC
DetailsJim Sly
11/06/97 316 - Gave to Carl D.
(F) Reprint permit  11/7/1997
INSP - Conference11/6/199711/6/199711/6/1997PPASS
DetailsCarl Dependahl
W/ BRIAN PRICE, DANS. & FLOYD V. RE HP6; PROPOSAL TO PROTECT PIPING; STILL NEED CHEM. ANALYSIS & HPM SERVICE CORRIDOR RESOLUTION.
INSP - Conference11/5/199711/5/199711/5/1997APASS
DetailsCarl Dependahl
W/ BRIAN PRICE OF ANDERSON CONST. WILL COME IN 11-6-97 TO DISCUSS PROPOSAL.
INSP - Conference11/5/199711/5/199711/5/1997APASS
DetailsCarl Dependahl
TALKED TO BOB G. & DAN S. RE: RESUBMITTAL FOR HPM TUBING PROTECTION AT NON H6 OCC.
INSP - Conference10/28/199710/28/199710/28/1997APASS
DetailsCarl Dependahl
W/ DAN S. RE RESUBMITTAL HP 6
INSP - Conference10/28/199710/27/199710/27/1997PPASS
DetailsCarl Dependahl
REC'D RESUBMITTAL TO UPGRADE ALARM & DETECTION SYSTEM AT HP6; DISCUSSED W/ DAN HAYES OF ANDERSON/HP; GAVE COPY TO FLOYD FOR REVIEW
INSP - Conference10/24/199710/24/199710/24/1997PPASS
DetailsCarl Dependahl
W/ DAN S RE SUBMITTAL REC'D FOR 1 HR PROTECTION OF HPM PIPING...NEED BETTER DETAIL THAT MEETS CODE, PROVIDES RATING FOR ENTIRE ASSEMBLY PER DAN.
INSP - Final10/15/199710/16/199710/16/1997PFAIL
DetailsCarl Dependahl
hp6...KEEP C/N,STILL NEED APPROVED CHEM. ANALYSIS
INSP - Final10/13/199710/15/199710/14/1997PCANC
DetailsJim Sly
10/14/97 316 - bld 6 Gave to Carl D.
INSP - Conference10/14/199710/13/199710/13/1997PPASS
DetailsCarl Dependahl
W/ DAN HAYES OF ANDERSON CONST. RE FINAL REQ'S & PROPOSAL FOR SUBMITTALS.
INSP - Conference10/8/199710/8/199710/8/1997APASS
DetailsCarl Dependahl
W/ DAN HAYES, ANDERSON CONST/HP...TOLD TO HAVE ARCH SUBMIT DETAIL FOR PROTECTION OF HPM PIPING RATHER THAN APPROVE IN FIELD
INSP - Conference10/2/199710/1/199710/1/1997PPASS
DetailsCarl Dependahl
W/BRIAN PRICE OF ANDERSON CONST. CONT. TO BE OFF JOB SOON...NEED TO MAKE ARRANGEMENTS FOR FINAL; RESUBMITTALS AND RESOLUTION TO ITEMS NOTED IN INITIAL PLAN CHECK AND CORRECTIONS IS STILL REQ'D
INSP-Final Inspection9/29/19979/30/19979/30/1997APASS
DetailsJoe Tawney
09/30/97 406 - REINSP FOR FINAL OK FOR PERM OCC OR CERT OF COMPL
INSP - Conference9/29/19979/29/19979/29/1997PPASS
DetailsCarl Dependahl
W/ JOE TAWNEY RE FINAL FOR HP 6
INSP - Conference9/26/19979/26/19979/26/1997PPASS
DetailsCarl Dependahl
09/26/97 340 - CONT TO BE OFF JOB SOON, NO FINAL ISSUED; HPM ISSUES YET RESOLVED....NEED TO CONSULT G.S. OR?
INSP - Letter of compliance9/26/19979/26/19979/26/1997PCANC
DetailsCarl Dependahl
09/26/97 340 - CANC, NR FOR FINAL, KEEP C/N
INSP - Conference9/23/19979/23/19979/23/1997PPASS
DetailsCarl Dependahl
09/23/97 340 - HP 6; AWAITING RESOLUTION TO C/N, CHEM, COMPLETION OF STO DISPOSAL; NEED ALL FINAL SIGS.
INSP - Carpentry9/22/19979/22/19979/22/1997PPART
DetailsCarl Dependahl
09/22/97 340 - HP 6, FAB AREA/BSMT.
INSP - Carpentry9/18/19979/19/19979/19/1997PPART
DetailsCarl Dependahl
09/19/97 340 - RE FINAL FOR #6
INSP - Carpentry9/18/19979/19/19979/19/1997PPART
DetailsCarl Dependahl
09/19/97 340 -
INSP - Conference9/18/19979/18/19979/18/1997APASS
DetailsCarl Dependahl
CHK'D W/ DAN RE SUBMITTALS FOR FINAL ON BLDG 6 INK JET PROJECT; CHEM ANALYSIS, HPM SEPARATION, ETC.
INSP - Conference9/15/19979/11/19979/11/1997PPASS
DetailsCarl Dependahl
W/ FLOYD RE CHEM ANALYSIS, HPM CORR, BLDG 6; REJECT, KEEP CN
INSP - Carpentry9/3/19979/3/19979/4/1997PPART
DetailsCarl Dependahl
09/03/97 340 - BLDG 6; CHK C/N FOR FINAL...WIP,NEED REPORT ON CHEM ANALY PLAN CHK ITEMS
INSP - Carpentry8/28/19978/28/19978/28/1997 PART
DetailsCarl Dependahl
/ / 340 - walked job w/ andersen, chk'd wip for c/n on t/o
INSP - Carpentry8/25/19978/25/19978/25/1997PPART
DetailsCarl Dependahl
08/25/97 340 - IJ14, BLDG 6; WIP
INSP - Conference8/22/19978/22/19978/22/1997PPASS
DetailsCarl Dependahl
W/ DAN S. RE SILANE AREA; NEED MECH & ELEC TO CHECK OFF
INSP - Conference8/21/19978/21/19978/21/1997 PASS
DetailsCarl Dependahl
08/21/97 340 - W/ FLOYD VARLEY RE CHEM REPORT FOR HPM WASTES
INSP - Conference8/21/19978/21/19978/21/1997 PASS
DetailsCarl Dependahl
08/21/97 340 - W/ FLOYD VARLEY RE CHEM REPORT FOR HPM WASTES
INSP - Conference8/18/19978/18/19978/18/1997 PASS
DetailsCarl Dependahl
08/18/97 340 - W/DAN STUART RE T/O
INSP - Conference8/18/19978/18/19978/18/1997PPASS
DetailsCarl Dependahl
W/DAN STUART RE T/O
INSP - Final8/8/19978/8/19978/8/1997PFAIL
DetailsCarl Dependahl
recd letter from HP, issued c/n, ok for t/o, card to contractor at Cathy's desk. Copies of c/n & letter to Dan s.
Temporary occupancy  8/8/1997 PASS
Temp. Occ. Cert. #3442 issued 8-8-97 to H-P, Bldg. #6.
INSP - Conference8/7/19978/7/19978/7/1997PPASS
DetailsCarl Dependahl
w/ MARK ELIOT, ARCH. WANTS TO ARRANGE CONF. W/ TIM H. HP, DAN S. ETC TO SEE ABOUT T/O...WILL HAVE TO FOLLOW UP ON REQUEST
INSP - Carpentry8/7/19978/7/19978/7/1997P
DetailsCarl Dependahl
###-#### Paul
INSP - Carpentry8/5/19978/6/19978/6/1997PPART
DetailsCarl Dependahl
###-#### fire penetration walls call the # if there are any questions
INSP - Conference8/5/19978/5/19978/5/1997PPASS
DetailsCarl Dependahl
08/05/97 340 - MET W/ PAUL, FOREMAN ANDERSON CO. REC'D LETTERS FROM HILT
INSP - Conference8/4/19978/4/19978/4/1997 PASS
DetailsCarl Dependahl
/ / 340 - BLD6 INK JET PROJ...KEEP CN; HPM CORR AT BSMT STILL UNDER RE
INSP - Final8/1/19978/1/19978/1/1997 PART
DetailsJoe Tawney
/ / 406 - OK ON TRIP TEST OF DELUGE SYSTEM FOR SILANE BOTTLE COOLING
INSP - Conference8/1/19978/1/19978/1/1997 PASS
DetailsCarl Dependahl
/ / 340 - REC'D INCOMPLETE SPEC INSP REPORT COMPOSITE FROM MTI; NEED C AT HP. SPOKE W/ DAVE OF I.S.I.
INSP - Final7/29/19977/29/19977/29/1997 FAIL
DetailsJoe Tawney
/ / 406 - FINAL INSP OF DELUGE SYSTEM FOR SILANE STATION FAIL SOL VLV
INSP - Final7/29/19977/29/19977/29/1997PPART
DetailsJoe Tawney
/ / 406 - ALARM TEST ON GAS DETECTION SYSTEM PASS
INSP - Conference7/29/19977/29/19977/29/1997 PASS
DetailsCarl Dependahl
07/29/97 340 - W/DAN, HP STAFF & ARCH; KEEP C/N , NEED RESUBMITTAL RE BS
INSP - Conference7/22/19977/22/19977/22/1997PPASS
DetailsCarl Dependahl
W/ DAN S. RE C/N'S & RESUBMITTAL
INSP - Carpentry7/21/19977/21/19977/21/1997PFAIL
DetailsCarl Dependahl
issued c/n; complete all control area walls, panic hdwe at main fl break room/ corridor. Need all spec insp reports & acceptance from MTI. Remove or seal pH adjust room non-rated dampers & firestop new plbg. Partial insp
INSP - Temporary occupancy7/18/19977/18/19977/18/1997PNR
DetailsCarl Dependahl
07/18/97 340 - BLDG 6, keep c/n, Dan S reviewing resub at bsmt hpm corr
INSP - Carpentry7/17/19977/17/19977/18/1997PFAIL
DetailsCarl Dependahl
07/17/97 340 - MEET ALAN 3 PM; KEEP C/N RE DOORS, FIRESTOPS, DAMPER AT C
INSP - Carpentry7/16/19977/16/19977/16/1997PFAIL
DetailsCarl Dependahl
C/N: DOORS, CORRIDORS,HVAC FINAL, FIRESTOPPING, ETC. NEED TO GET ALL SPEC INSP REPORTS, WALK CAT-WALKS, ENG'S OK FOR UNUSUAL FIRESTOPS
INSP - Final7/16/19977/16/19977/16/1997 PART
DetailsJoe Tawney
/ / 406 - REINSP FOR FINAL OK FOR TEMP OCC
INSP - Carpentry7/15/19977/15/19977/15/1997PNR
DetailsCarl Dependahl
HP #6 EAST/... NEED FIRE / SAFETY & OTHER OKS....WANTS T/O, WILL REINSPECT AFTER OTHER OKS. SPOKE TO JOHN KERR W/ ANDERSON CONST
INSP-Final Inspection7/14/19977/15/19977/15/1997PFAIL
DetailsJoe Tawney
07/15/97 406 - 1:00 HP #6 FINAL FAIL ALARM SYSTEM DOORS IN EXIT CORRIDORS
INSP - Conference7/15/19977/14/19977/14/1997PPASS
DetailsCarl Dependahl
W/DAN STUART RE DOOR REQS
Print Occupancy Form  7/14/1997
INSP - Carpentry7/10/19977/10/19977/10/1997PCANC
DetailsCarl Dependahl
w/ PAUL H. OF ANDERSON CONST. OFF ###-####, CEL ###-####
INSP - Carpentry7/10/19977/10/19977/10/1997PCANC
DetailsJim Sly
07/10/97 316 - Gave to Carl D.
INSP - Carpentry7/10/19977/10/19977/10/1997PPART
DetailsCarl Dependahl
07/10/97 340 - W PAUL OF ANDERSON ###-####, CEL 8502997, KEEP CN WIP
INSP - Carpentry7/8/19977/9/19977/10/1997ACANC
DetailsAlan Hauser
07/10/97 350 - ###-#### Paul in bld 6 this is for #340
INSP - Conference7/10/19977/8/19977/8/1997APASS
DetailsCarl Dependahl
re swo for silane area (bld97-1640)
INSP-Sprinkler Rough-in/Hydro7/3/19977/3/19977/3/1997PPART
DetailsJoe Tawney
07/03/97 406 - building 6 OK ON HYDRO TEST FOR PREACTION SYSTEM
INSP - Carpentry7/1/19977/1/19977/1/1997PFAIL
DetailsCarl Dependahl
07/01/97 340 - BUILDING 6 PAUL ###-####; REQ'D REPAIR & BOX INSTALL PER
INSP - Carpentry6/30/19976/30/19976/30/1997PPART
DetailsCarl Dependahl
06/30/97 340 - Paul ###-#### ì
INSP-Sprinkler Rough-in/Hydro6/27/19976/27/19976/27/1997PPART
DetailsJoe Tawney
BLDG #6 TERRY NELSON - ###-####- CALL & THE OFFICE WILL PAGE HIM WITH THE TIME OF MEETING OK ON HYDRO TEST FOR BLDG #6
INSP - Conference6/25/19976/25/19976/25/1997 PASS
W/ DAN STUART RE SWO IN RELATION TO REST OF BLDG...SWO ON PENDING BLD97-1640 ONLY (SILANE SHED)
INSP - Conference6/19/19976/23/19976/23/1997APASS
DetailsJoe Tawney
06/23/97 406 - CONF./ INSP. WITH CARL, DAN STUART, ALAN HAUSER AT HP BLD PERFORMED WALK THRU OF CONSTRUCTION AREA
INSP-Sprinkler Rough-in/Hydro6/23/19976/23/19976/23/1997PPART
DetailsJoe Tawney
06/23/97 406 - TERRY NELSON (OFFICE ###-####). CALL OFFICE & THEY WILL P MEET YOU AT SPECIFIED TIME.... BLDG.#6. ROUGH IN OK TO COVER
INSP - Conference6/19/19976/23/19976/23/1997APASS
DetailsAlan Hauser
06/23/97 350 - MEET W/ JOE, CARL, & HP AT BLDG 6 went through new fab. facility in bld. #6, with struct. and plan review
INSP - Framing/Rough-in6/23/19976/23/19976/23/1997 FAIL
DetailsCarl Dependahl
/ / 340 - C/N; FIRESTOPS, WALL CONST, DOOR INSTALL, SPEC INSP REPORTS
INSP - Conference6/19/19976/23/19976/23/1997APASS
DetailsCarl Dependahl
06/23/97 340 - TAKE DAN S...MEET W/ JOE, ALAN, HP BLDG 6. REQUESTED RESU CORR ADDED AT BSMT
INSP - Conference6/19/19976/19/19976/19/1997APASS
DetailsCarl Dependahl
W/ DAN S. JOE TAWNEY & ALAN HAUSER TO ARRANGE GROUP CONF/ INSP AT BLDG 6 MON. 6-23
INSP-Sprinkler Rough-in/Hydro6/16/19976/17/19976/17/1997APART
DetailsJoe Tawney
06/17/97 406 - Before you go out or when you get there call ###-#### and TErry Nelson and he will come and pick you up. SPKLR ROUGH IN OK TO COVER
INSP - Framing/Rough-in6/16/19976/17/19976/17/1997ANR
DetailsCarl Dependahl
06/17/97 340 - PLEASE CALL DAVE REIMER AT ###-#### FOR ACCESS..NEED: COM BSMT. FIRESTOPPING THRU OUT, WRAP BEAMS, COLS ETC
INSP - Conference6/17/19976/17/19976/17/1997 PASS
DetailsCarl Dependahl
/ / 340 - MET W/ ARCH AT SITE; ASKED FOR SUBMITTAL FOR FIREPROOFING CH
Plan Reviewer's activity  6/9/1997
Carl Dependahl came by to visit about the HP Project and a possibility of going to the site with him on June 11, 1997 to walk through and discuss work in progress and relationship of plans to work to be done. There is a large tank in the basement that is in line with the location of the two hour area separation wall that won't be moved until after the tenant wants to occupy the area adjacent thereto, per Anderson construction, through Carl. I told Carl that they needed to contact the architect of record and have him review the situation and present a written request of HP's position and how they propose to handle for city concurence. Carl took all plans and notes from behind my desk, to his office downstairs to review to help familiarize hinmself with the project.
INSP - Carpentry6/5/19976/6/19976/6/1997PPART
DetailsCarl Dependahl
06/06/97 340 - PAUL ###-####..CHK'D BSMT 2HR WALL FRAMING; PART, NEED SP
90 day tracking............. 2/25/19975/26/1997
Issue PAID IN FULL permit  5/22/1997
Telephone call  5/22/1997
LEFT MESSAGE ON BRIAN PRICE'S VOICE MAIL/ PERMIT READY, FEE DUE
Inspection Record Card- Bld  5/22/1997
Print Occupancy Form  5/22/1997
Plan Reviewer's activity  5/22/1997 PASS
Received a fax copy of the signed letter of agreement sent to Mark Elliot, Brian Price, Tim Bashford & John White stating they felt they could comply with any outstanding items within 30 days. Preparing to issue permit.
PLANS/APPL TAKEN TO FRONT DESK  5/22/1997 PASS
RECEIVED LETTER OF AGREEMENT SIGNED BY ARCHITECT, MARK ELLIOT; CONTRACTOR, BRIAN PRICE; PROJECT MANAGER, TIM BASHFORD, FOR HP; AND HP VP, JOHN WHITE, NOTING ACCEPTANCE OF AGREEMENT. READY TO ISSUE PERMIT.
Routing - PLAN CHECK4/16/1997 5/21/1997 PASS
CONDITIONAL ISSUANCE OF PERMIT BASED ON LETTER OF AGREEMENT ON FILE.
Plan assigned to (DRS)2/25/1997 5/21/1997 PASS
DetailsDan Stuart
05/21/97 16:55:53 DRS - this action updated by action script from <<>> in Case No. BLD97-0401
Telephone call  5/8/1997
Call to Mark Elliot, Architect of Record, IDC, concerning the letter of understanding sent to him for review of items still pending clarification & submittal. If letter of understanding is acceptable to and signed, dated & returned to me from Jim White, Tim Bashford, Brian Price & Mark Elliot, I will process the plans for issuance of a permit for HP#6 Inkjet Project, Package IJ14 with the understanding that matters will be resolved within a 30 day period from the issuance of the permit. Mark will contact HP to verify they will sign the understanding and let me know.
Plan Reviewer's activity  5/7/1997
Prepared a letter of understanding reviewing matters of concern that still need to be resolved through clarification, resubmittals & or appeals of requirements. Sent copies of letter to Mark Elliot, IDC, Architect of Record; Brian Price, Anderson Construction representative; Tim Bashford, HP Project manager; and Jim White, HP Facilities and Engineering Manager. I asked them to review the letter and if in agreement that we will work together to resolve the listed items, to include changing/correcting any work done improperly, to sign and date the letter and send me a copy signed dated copy back for my records and then I will proceed to process the plans for issuance of a permit. I reviewed the comments from Wren Ross to Tim Hogland concerning the classification of the PH-Adjust Room as an F-1 instead of an H-3. Tim stated that there was no further clarification needed from HP. The fire dept. has re-reviewed the plans & resubmittals & Wren Ross response to Tim Hogland and signed off on the plans with noted conditions which allows the plans to be processed for permit when plan check div. is ready.
Plan resubmittals received  5/2/1997
Received letter from HP designating Mark Elliot as Architect of Record for this project. Also received new sheet, B6G-0001, not submitted with original plans but referenced in the architects respone of April 24, 1997.
Routing - FIRE4/28/1997 5/1/1997 PASS
Checked with Dave Miller 5/21/97 to verify that he had reviewed and approved the plans for issuance of permit based on letter of agreement sent to Mark Elliot & personel associated with the HP#6 Inkjet Project, IJ14, for compliance with code requirements for submittals to plan review comments within the next 30 days to the satisfaction of the Fire & Plan check agencies.
Plan resubmittals received  4/30/1997
Copy of specifications for metal studs received from Carl Depandahl, structural inspector. Specs had been put in his box in the structural div. I received them from him on the 3 of May. Attached copies to plans as part of approved plans.
Telephone call  4/29/1997
Call from Tim Bashford, HP #6, concerning progress on permit issuance. I explained that I was reviewing Mark Elliot's respose data to my plan review and I did have some areas of question concerning data refered to but I didn't have. I told Tim I would send off a follow up letter to Mark as soon as I had finished my review. I also have to send the plans to fire dept for their approval. This will involve a resolution to the question by the fire dept. concerning the PH Adjust Room. A letter was to come from HP/Earnie Harper through Mark Elliot to Wren Ross, Fire Chief, reviewing the history of the site and requesting a specific approval for using the PH Adjust Room as an F-1 Occupancy instead of an H3/H7 occupancy. Tim Said Earnie was working on the letter now and should have it in shortly.
Plan resubmittals received  4/28/1997
Received stamped, signed sheets B6A-0201, showing new floor areas & multiple occupancy ratio calcs and control area boundaries for 1-hour occupancy separation walls & B6A-0203 for Lower Level Area. Also received written response for Plan Review Corrections sent to Mark Elliot
Plan resubmittals received  4/27/1997
Reveived plan resubmittals that are not stamped or signed. Called Mark Elliot to request stamped signed plans before starting re-review of HP #6.
Plan resubmittals received  4/25/1997 HOLD
RESUB. RECEIVED HOWEVER THEY WERE NOT STAMPED OR SIGNED. GAVE TO DAN STUART TO HOLD. KMM
Plan resubmittals received  4/23/1997
Received new sheets, B6A-0201 & 0203 to attach to plans
Plan Reviewer's activity  4/21/1997
I went to P&Z this morning to see if there was a record for submittal & review for the addition of an exterior exhaust system, two new smoke stacks and support structure on the South side of H.P. Building #6. This project had recently been completed by Tempra Wilson and she gave me a copy of the design review comments for the file, DR-55-97. The ten day appeal period ends at 5:00 p.m. on April 28, 1997. The work covered within the scope of this review had been deleted as part of BLD97-0044, IJ07, Structural Upgrade permit, at the request of mark Elliot for HP in order that we may issue said permit. The exhaust system, stacks & support system were being transfered to be part of IJ14 package and submitted for approval to P&Z.
Telephone call  4/18/1997
Call from Mark Elliot. He will be in town on the 21st and we have set up a meeting at 10:30 A.M. or as close as possible if plane arrives on time. Mark has been sent copies of building department and fire dept. plan reviews for his response. This meeting will help resolve some of the questions. I have invited Bob Garrison, Plan Check Division Manager, & Dave Miller, Fire Protection Engineer / Plans Examiner to the meeting. I also notified Tim Hogland, Building Dept. Director of the meeting. He thought he may try and attend and invite John White of H.P. We will see who attends. Mark Elliot said Tim Bashford of H.P. had stated that Boise City bulding dept. had accepted letters from H.P. in the past saying H.P. would comply with all requirements listed in the plan review correction reports by providing details, explanations & field corrections of deficiencies, etc., and the city gave them a permit. Mark ask if this was possible. I told him this was not the general case, that we liked to have answers and approved plans prior to issuance of a permit but this was somthing he could bring up at the meeting.
Routing - FIRE4/15/1997 4/16/1997 FAIL
Print Pending Permit.LaserJet4  4/15/1997
Plan resubmittals requested  4/15/1997
Sent copy of plan review comments to Mark Elliot by FAX and by mail.
Routing - PLAN CHECK3/3/1997 4/15/1997
Routing plans to Fire Dept. for review.
Print Pending Permit.LaserJet4  4/15/1997
Permit for HP Bldg. #6 East
Plan resubmittals received  4/14/1997
Received new update to Chemical Usage Study. Have ask Mark Elliot to work with expert technician to fill in the blanks still remaining in the report.
Telephone call  4/14/1997
Conference call with Tim Hogland, Building Dept Dir & John White of HP Engineering Manager to discuss the progress of the plan review. Discussed the original plans submittal not being submitted as the latest documents but as a package with addendums to plans and specs separate. This took time to get plans in order before the plan review could start. A later meeting with Mark Elliot revieled that I still did not have the latest information. Mark would forward to me. Still have unanswered questions on the chemical classifications, occupancy separation walls, protection of openings & penetrations, etc. Plan review almost done for the first time through. Plan review comments should go to Mark Elliot tommorrow and the plans to the fire dept. Mr. Hogland will ask the fire dept. to review the plans as soon as they get them. I wiil need to get the answers to my review questions back from Mr. Elliot and approve them before issuing permit unless directed otherwise by Mr. Hogland.
Meeting  4/9/1997
Met with Brian Price of Anderson Construction to review plan review progress and to discuss plan submittals for the fabrication equipment. Told Brian to expect to pay plan review fee's for equipment review and I would let him know if it wasn't required. Brian also ask about permit costs. He said that other projects already issued were included with the construction cost of this job. I told him to resubmit a new certificate of value showing new cost and a sheet showing the permit values he has already paid for and I will refigure the cost of the permit based on the new value. If he chooses to wait until the project is done and then bring in a copy of all actual costs he can review with Dave Hattrick or Linda Hartwell to adjust the fee's paid.
Plan resubmittals received  4/3/1997
Received new copy of Chemical Usage Study. Information was still incomplete. MSDS sheets were not completely filled out with information. Silane, Methan & Amonia were not include in the study.
Meeting  4/3/1997
Met with Mark Elliot to review progress on plan review. Silane, ammonia & methane products were not included in tge Chemical Use Study of Feb. 24, 1997 or the April 3,1997 resubmittal. Several product MSDS sheets or CAS numbers were still incomplete with questions on the ink classification data. Mark will correct by sending me new study. Also reviewed door swing in corridor, pass through door assemblies, occupancy separation walls needed between control areas, use of basement corridor for transporting HPM materials and note from city approving this use as noted in the plans. Will send copy of plan review comments to Mark as soon as they are complete.
Telephone call  3/17/1997
Mark returned my call. I asked him about the information needed for the hazardous materials report that was incomplete. This information will be needed to complete my review and to allow the fire dept. to do their review. Mark thought they had received the information from HP on thursday the 14th and that I should have the information the first part of next week. I told him his request for a relocation of the two-hour area separation wall had been approved as shown, by Bob Garrison, and a copy of the approved detail would be attached to the plans. I also told him that at the location where the 8" pipe penetrates the alcove offset in the two-hour wall would need to be checked for proper "F" & "T" rating firestops. I also had questions concerning his response to the structural review questions from Jan Welch of Stapley Engineers. Refere to notes under BLD97-0044.
Telephone call  3/14/1997
Called Mark Elliot. He had not returned my call of the 12th. Mark was not in but would be checking his messages, per his voice-mail, and would call me back.
Telephone call  3/12/1997
Call to Mark Elliot concerning questions about plans and incomplete table concerning hazardous products in the H-6 Occupancy. This information was not available from HP to IDC when I had met with Mark on the 24th of Feb. I had also received a request from Mark asking consideration for approving an offset of 8" in the location of the area separation wall in the basement and the wall location on the first floor. Request was do to the location of an 8" water main in the basement located were the wall would need to be. This change was approved by Bob Garrison and I was calling to let mark know. Mark Elliot was not in and I left an voice-mail message for him to call me.
Plan Reviewer's activity  3/3/1997
Finished inserting new sheets into plans and organizing the sections to match the order of the index cover sheet.
Routing - PLAN CHECK2/28/1997 3/3/1997
Started reviewing plans.
Plan Reviewer's activity  2/28/1997
Started to change out plans of latest addendum designs submitted at the same time with originals. This will delay the start process but will make it so I don,t review the same sheet twice and cut down on the final plan thickness.
Telephone call  2/28/1997
Called for Mr. Elliot to discuss questions on plans submitted. Anderson Construction had inserted the specsification addendums into the spec books but had not inserted the latest plan changes into the original plans before they were turned into the city. I questioned Mark concerning the differences in the plans and to let him know I was going to insert the latest sheets before I started the review and through away the sheets being replaced. The process of correcting plans will delay the review process as I will do this between other jobs.
Routing - PUBLIC WORKS2/26/1997 2/27/1997 PASS
Plan Reviewer's activity  2/25/1997
Anderson Construction has submitted the plans and paid the plan review fee without combining the latest addendums and plan changes into one package before submitting them. I called Brian Price of anderson Const. to come back and handle the plan & spec upgrades before I could start the plan review. They said they would send someone down to get it done.
Inspection Record Card- Bld  2/25/1997
Plan routing begun/TENANTS2/25/1997 2/25/1997
Route to PUBLIC WORKS then back to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT.
Application received  2/25/1997
Recd Pcfee & Taken To Pln CK  2/25/1997
Meeting  2/24/1997
To meet with Anderson Construction (Brian Price) & others to review the plans for submittal and plans in process of review for the HP#6 project to see what if any overlapping there is. No one from Anderson const. showed up but Mr Mark Elliot, the architect of record from IDC in Portland, OR, was waiting for them in our lobby. I had a short meeting with Mark Elliot. It was discovered that addendums to the specifications and changes in plans had been presented along with the original copies of plans & specs without being combined and those portions of the plans & specs that no longer apply being destroyed before turning them in for processing. I told Mark that I would have Anderson const. update the specs & plans before they were accepted to process. It was also agreed that it would be quicker to continue the structural upgrades as a separate permit as they were already submitted to Jan Welch of Stapley engineering for review & were only waiting for the architects or engineers response through the architect before the permit could be issued. We would have to start the process over and the plans would route to all agencies, with the rest of the architectural plans, causing a delay in issuing the structural permit. Mark Elliot was to send me a copy of the latest structural plans (it turns out I didn't have the latest changes) to incorporate into the plans being processed under separate application, Plan IJ07, BLD97-0044.
Meeting  2/21/1997
Met with Brian Price, John Kerr & Pat McIntyre of Anderson Construction. They brought in copies of plans to be submitted for plan review as well as specs. They left these with Dave Radford. Money to pay the plan review fee's had not been brought by Anderson const. so the plans could not be accepted. A check will be brought back on the 24th so they can submit the plans. I discussed the permits that were currently in the review process for HP#6, Structural Upgrade, and the Demo and partial 2-hour area separation wall construction & upgrades permits already issued. It was noted that the two hour area separation walls are to line up for the full height of the building in response to a question by Mr. Kerr. We arranged for a meeting at 2 P.M. on the 24th to discuss any other questions they have and to do a preliminary review of the plans for the project.
INSP - Final5/18/19985/18/19985/18/1908AFAIL
DetailsCarl Dependahl
need eng'g letter (hazardous chemicals) per Floyd and Dan S.