(F) Reprint permit | | | 6/12/2008 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/12/2008 | | DONE |
|
|
|
|
Permanent Occupancy | | 2/18/1998 | 2/18/1998 | | DONE |
|
|
|
|
INSP - Final | 2/17/1998 | 2/18/1998 | 2/18/1998 | A | PASS |
Wes Worcester
|
|
|
02/18/98 342 - Final on Michael's Furniture addition.
|
Permanent occupancy | | | 2/18/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7140 issued 2-12-98 to Michael's Furniture Showplace (addition).
|
Code Occupancy Approval | | | 2/17/1998 | | PASS |
|
|
|
Final on Landscape, Parking Lot, Handicap, stripping and wheel bumpers. Done according to plans.
|
Print Occupancy Form | | | 2/12/1998 | | |
|
|
|
|
INSP - Final | 9/19/1997 | 9/19/1997 | 9/19/1997 | P | NR |
Wes Worcester
|
|
|
09/19/97 342 - need to redo roof hatch for accessability
|
INSP - Final | 9/19/1997 | 9/19/1997 | 9/19/1997 | | PART |
Wes Worcester
|
|
|
/ / 342 - outstanding c/n for hatch and elevator shaft barricade
|
INSP-Final Inspection | 9/18/1997 | 9/18/1997 | 9/18/1997 | P | PART |
Rick Jackson
|
|
|
temp only. must paint curbing red for final occ. c/n issued.
|
INSP - Final | 9/17/1997 | 9/18/1997 | 9/18/1997 | P | NR |
Wes Worcester
|
|
|
09/18/97 342 - LATE P.M. need mechanical
|
Routing for occupancy | 9/11/1997 | 9/12/1997 | 9/12/1997 | | TEMP |
|
|
|
Inspected by Art Musser - Dumpster area needs completed; bumper installed on north side prkg. area - repair sink hole in pavement by mattress bldg. - temporary signed/no bonding required
|
Print Occupancy Form | | | 9/10/1997 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 9/3/1997 | 9/2/1997 | 9/2/1997 | P | PASS |
Rick Jackson
|
|
|
hydro ok, moving furniture in store, sprinklers off,
|
INSP-Sprinkler Rough-in/Hydro | 8/27/1997 | 8/28/1997 | 8/28/1997 | A | PART |
|
|
|
2ND FLOOR COVER, RECHECK FIRST ok to cover except stair lid. need ug and above hydro
|
INSP - Framing/Rough-in | 8/26/1997 | 8/27/1997 | 8/27/1997 | P | PASS |
|
|
|
08/27/97 333 - first thing please
|
INSP - Framing/Rough-in | 8/26/1997 | 8/26/1997 | 8/26/1997 | P | PASS |
|
|
|
08/26/97 333 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 8/21/1997 | 8/21/1997 | 8/21/1997 | | FAIL |
|
|
|
08/21/97 333 - cn not complete
|
INSP - Framing/Rough-in | 8/21/1997 | 8/21/1997 | 8/21/1997 | P | FAIL |
|
|
|
cn not made
|
INSP - Framing/Rough-in | 8/20/1997 | 8/20/1997 | 8/20/1997 | | PART |
|
|
|
West half of ground floor only approved for cover. CN issued for remainder of 1st floor.
|
INSP - Framing/Rough-in | 8/19/1997 | 8/19/1997 | 8/19/1997 | P | NH |
Russ Owen
|
|
|
08/19/97 407 - UGA -UNABLE TO GAIN ACCESS-LEFT NOTC Scheduled by Hello! on 08/19/97 at 11:30:54. late pm
|
INSP - Framing/Rough-in | 8/7/1997 | 8/7/1997 | 8/7/1997 | P | PART |
|
|
|
08/07/97 333 - talked about final
|
INSP - Framing/Rough-in | 8/6/1997 | 8/6/1997 | 8/6/1997 | P | CANC |
|
|
|
steel cover up CONTRACTOR CANCELED
|
INSP - Masonry | 7/16/1997 | 7/16/1997 | 7/16/1997 | P | PART |
Jim Storey
|
|
|
07/16/97 301 - trans to kim
|
INSP - Masonry | 7/16/1997 | 7/16/1997 | 7/16/1997 | P | PASS |
|
|
|
07/16/97 333 - RGHN-OK ROUGH IN
|
INSP - Masonry | 7/15/1997 | 7/15/1997 | 7/15/1997 | P | NR |
Jim Storey
|
|
|
07/15/97 301 - trans to kim not my area kim allready has appointment.
|
INSP - Masonry | 7/14/1997 | 7/14/1997 | 7/14/1997 | P | NR |
Jim Storey
|
|
|
07/14/97 301 - trans to kim
|
INSP - Masonry | 7/10/1997 | 7/11/1997 | 7/11/1997 | P | PASS |
|
|
|
07/11/97 333 - third pour ok
|
INSP - Masonry | 7/9/1997 | 7/10/1997 | 7/10/1997 | A | PART |
|
|
|
07/10/97 333 - second pour ok
|
INSP - Masonry | 7/7/1997 | 7/7/1997 | 7/7/1997 | P | CANC |
Jim Storey
|
|
|
07/07/97 301 - trans to kim
|
INSP - Masonry | 7/2/1997 | 7/3/1997 | 7/3/1997 | P | NR |
Jim Storey
|
|
|
07/03/97 301 - trans to kim
|
INSP - Footings | 6/16/1997 | 6/16/1997 | 6/16/1997 | P | PASS |
|
|
|
06/16/97 333 - FTG -OK FOOTING
|
INSP - Footings | 6/12/1997 | 6/13/1997 | 6/13/1997 | P | PASS |
Jim Storey
|
|
|
06/13/97 301 - FDN -OK FOUNDATION AND 6 PAD FT.
|
INSP-Supply line flush | 6/11/1997 | 6/11/1997 | 6/11/1997 | P | FAIL |
|
|
|
water didnt run clear, nearby hydrant bad also, contacted U W and engine co #5
|
INSP - Footings | 6/10/1997 | 6/11/1997 | 6/11/1997 | P | NH |
Jim Storey
|
|
|
06/11/97 301 - TRANS TO KIM M.
|
Issue PAID IN FULL permit | | | 6/10/1997 | | |
|
|
|
|
Plan assigned to (JCM) | 4/3/1997 | | 6/6/1997 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 4/14/1997 | | 6/6/1997 | | PASS |
|
|
|
PACKAGE #1
|
Print Occupancy Form | | | 6/6/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/6/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/1997 | | PASS |
|
|
|
|
Telephone call | | | 6/6/1997 | | PASS |
|
|
|
LEFT MESSAGE
|
Routing - PLAN CHECK | 4/28/1997 | | 6/6/1997 | | PASS |
|
|
|
PACKAGE #2
|
Routing Off Site - STRUCTURAL | 5/28/1997 | | 6/5/1997 | | |
|
|
|
SENT TO STAPLEY ENGINEERING (RESUBS)
|
90 day tracking............. | | 2/28/1997 | 5/29/1997 | | PEND |
|
|
|
|
Routing Off Site - A.C.H.D | 3/4/1997 | | 5/28/1997 | | PASS |
|
|
|
PACKAGE #4 CONTACTED DICK TALBOY AT ###-#### TO TAKE PLANS OUT TO ACHD FEES PAID. CERTIFICATE #97-1269
|
Plan resubmittals received | | | 5/5/1997 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 5/2/1997 | | PEND |
|
|
|
ADDITIONAL REVISIONS WERE REQUESTED AFTER REVIEW OF THE RESUBMITTAL DOCUMENTS. I FAXED A NEW CORRECTION LIST TO JIM GLANCEY AND MAILED HIM A COPY.
|
Plan resubmittals received | | | 4/30/1997 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 4/1/1997 | | 4/28/1997 | | |
|
|
|
PACKAGE #2
|
Routing - PUBLIC WORKS | 4/28/1997 | | 4/28/1997 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 3/27/1997 | | 4/23/1997 | | PEND |
|
|
|
PACKAGE #3
|
Routing Off Site - STRUCTURAL | 4/23/1997 | | 4/23/1997 | | |
|
|
|
RESUBS RETURNED.
|
Routing - FIRE | 4/9/1997 | | 4/14/1997 | | PASS |
|
|
|
PACKAGE #1
|
Plan resubmittals requested | | | 4/9/1997 | | PEND |
|
|
|
A COPY OF THE BUILDING DEPARTMENT AND STRUCTURAL ENGINEER'S CORRECTION LISTS WERE MAILED TO JAMES T. GLANCEY FOR REQUIRED CORRECTIONS.
|
Routing - PLAN CHECK | 3/27/1997 | | 4/9/1997 | | PEND |
|
|
|
PACKAGE #1
|
Plan assigned to (RGG) | 3/4/1997 | | 4/4/1997 | | |
|
|
|
|
Routing - PUBLIC WORKS | 3/21/1997 | | 3/31/1997 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN REVISION. PACKAGE #2
|
Routing Off Site - STRUCTURAL | 3/4/1997 | | 3/27/1997 | | |
|
|
|
PACKAGE #3 CONTACTED PDQ TO TAKE PLANS OUT TO STAPLEY ENGINEERING
|
Routing - ELECTRICAL | 3/23/1997 | | 3/23/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLUMBING | 3/12/1997 | | 3/20/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLANNING | 3/14/1997 | | 3/18/1997 | | PASS |
|
|
|
PACKAGE #2 X-ref: DR-141-96. Approved by MS.
|
Routing - PUBLIC WORKS | 3/14/1997 | | 3/17/1997 | | FAIL |
|
|
|
requires drainage plan revision
|
Plan routing begun/NEW & ADDTN | | | 3/12/1997 | | PASS |
|
|
|
SEE ACTION 007 DATED 3-12-97
|
Plans ACCEPTED BY PLAN CHECK | | | 3/12/1997 | | PASS |
|
|
|
RECEIVED PLUMB. SHEETS FROM DICK TALBOY. PACKAGES #1 AND 2 ARE READY FOR ROUTING. KMM THESE SHEETS WERE NOT STAMPED OR SIGNED HOWEVER WILL LET LEE RICE DECIDE IF HE WANTS THEM STAMPED.
|
Routing - MECHANICAL | 3/4/1997 | | 3/4/1997 | | PASS |
|
|
|
PACKAGE #1 NO REVIEW WILL FIELD VERIFY
|
Plan routing begun/NEW & ADDTN | | | 3/4/1997 | | HOLD |
|
|
|
SEE ACTION 007
|
Received Certificate of Value | | | 3/4/1997 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 3/4/1997 | | HOLD |
|
|
|
WAITING FOR PLUMBING SHEETS FOR PACKAGE #1 AND #2. CONTACTED DICK TALBOY AND INFORMED HIM OF THIS NEED.
|
Application received | | | 2/28/1997 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/28/1997 | | PEND |
|
|
|
|