Case Summary (BLD) | | | 2/26/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 2/13/2002 | | DONE |
|
|
|
|
Permanent Occupancy | | 2/6/1998 | 2/6/1998 | | DONE |
|
|
|
|
INSP - Final | 2/6/1998 | 2/6/1998 | 2/6/1998 | | PASS |
Jim Storey
|
|
|
/ / 301 - FNL -OK FINAL received 5 yr warranty sent to archive sys.
|
Permanent occupancy | | | 2/6/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7125 issued 2-6-98 to Hobson Fabricating.
|
Temporary occupancy | | | 2/2/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3547 issued 2-2-98 to Hobson Fabricating.
|
INSP - Final | 1/29/1998 | 1/30/1998 | 1/30/1998 | A | PART |
Bob Archibald
|
|
|
stacy ###-#### call ahead. CN issued ok for temp. occ. only.
|
INSP-Final Inspection | 1/30/1998 | 1/30/1998 | 1/30/1998 | P | PASS |
Rick Jackson
|
|
|
stacy ###-#### final occupancy occ card signed for perm
|
Code Occupancy Approval | | | 1/29/1998 | | PASS |
|
|
|
All landscape and parking in as required, signed off.
|
INSP-Final Inspection | 1/28/1998 | 1/28/1998 | 1/28/1998 | P | FAIL |
Rick Jackson
|
|
|
STACEY AT ###-#### alarm plans, NFPA 72 forms, strobes in bathrooms, replace detector.
|
INSP-Final Inspection | 1/27/1998 | 1/27/1998 | 1/28/1998 | P | FAIL |
Russ Owen
|
|
|
01/27/98 407 - went with 301 Jim S & left corrections.
|
Code Occupancy Approval | | | 1/27/1998 | | FAIL |
|
|
|
Stacy Heninger ###-#### requested final inspection, failed, missing about 30 feet of landscape curbing just north of building and handicapped parking signs, will fix and call me back.
|
PubWorks Occupancy Approval | | | 1/27/1998 | | DONE |
|
|
|
Drainage project complete 01/27/98. D.Hagen
|
INSP-Final Inspection | 11/24/1997 | 11/25/1997 | 11/25/1997 | A | FAIL |
Rick Jackson
|
|
|
10:00 attempted sprinkler system test - panel and tampers not ready.
|
INSP-Conference | 10/24/1997 | 10/24/1997 | 10/24/1997 | P | PART |
Rick Jackson
|
|
|
owner requested requirements to occupy fabricating area. exit lights; sprinkler system tested, monitored, and charged; emergency lighting; fire extinguishers are needed for temp. c/o.
|
INSP - Framing/Rough-in | 10/9/1997 | 10/9/1997 | 10/10/1997 | P | CANC |
Russ Owen
|
|
|
10/09/97 407 - cancelled .
|
INSP-Sprinkler Rough-in/Hydro | 10/8/1997 | 10/8/1997 | 10/8/1997 | A | PASS |
Rick Jackson
|
|
|
passed hydrostatic test of wet and dry systems.
|
INSP-Sprinkler Rough-in/Hydro | 10/3/1997 | 10/6/1997 | 10/6/1997 | A | PASS |
Rick Jackson
|
|
|
requests 10:00 am if possible (Roy pager ###-####) underground flush and rough-in okay.
|
INSP-Supply line flush | 9/10/1997 | 9/11/1997 | 9/11/1997 | A | PASS |
Rick Jackson
|
|
|
passed hydro only, flush at a later date
|
Routing Off Site - STRUCTURAL | 8/18/1997 | | 8/18/1997 | | |
|
|
|
RESUBMITTED PLANS RETURNED FROM STAPLEY AND GIVEN TO MIKE O.
|
(F) Reprint permit | | | 7/24/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/1997 | | PASS |
|
|
|
|
Issue PAID IN FULL permit | | | 7/23/1997 | | |
|
|
|
|
Telephone call | | | 7/23/1997 | | |
|
|
|
TALKED TO STACY/ PERMIT READY, FEE DUE
|
Print Occupancy Form | | | 7/23/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 7/23/1997 | | PASS |
|
|
|
ADMINSITRATIVE FEE ADDED TO THIS PERMIT FOR THE FOURTH AND FIFTH STRUCTURAL REVIEW BY STAPLEY ENGINEERING. FEES FROM STAPLEY WERE; PROJECT # 97002.07, INVOICE # 4, DATED 6-30-97, 450.00 AND PROJECT # 97002.07, INVOICE # 5, DATED 7-17-97, 187.5. THE TOTAL OF THE ADMINSITRATIVE FEE EQUALS 637.5. AUTHORIZATION TO ADD THIS FEE FROM B. GARRISON AND METHOD APPROVED BY J. TOOMBS. MO
|
Print Occupancy Form | | | 7/23/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/23/1997 | | |
|
|
|
|
Plan assigned to (M_O) | 3/28/1997 | | 7/23/1997 | | PASS |
|
|
|
07/23/97 11:12:45 M_O - this action updated by action script from <<>> in Case No. BLD97-0447
|
Routing Off Site - STRUCTURAL | 7/14/1997 | | 7/22/1997 | | PASS |
|
|
|
REVISED STRUCTURAL SENT OUT TO STAPLEY VIA PDQ. CORRECTION FAXED TO STACY AT HOBBSONS.
|
Plan resubmittals received | | | 7/21/1997 | | PEND |
|
|
|
RECEIVED REVISED STRUCTRUAL PLANS AND CALCS FROM CSHQA AT 3:40 P.M. 7-21-97. MO
|
Plan resubmittals requested | | | 7/18/1997 | | PEND |
|
|
|
RESUBMITTALS FOR THE HANDICAPPED RAMP REQUIRED PER STRUCTRUAL ENGINEERS REVIEW OF 7-18-97. CORRECTION FAXED TO STACY AT HOBBSON'S 7-18-97. MO
|
Routing - PLUMBING | 7/11/1997 | | 7/15/1997 | | PASS |
|
|
|
PACKAGE #1
|
Plan resubmittals received | | | 7/11/1997 | | FAIL |
|
|
|
received more structrual revisions for handicapped ramp at 4:10 PM Fri afternoon. Will send to structural engineer. MO
|
Routing - FIRE | 7/1/1997 | | 7/10/1997 | | PASS |
|
|
|
|
Telephone call | | | 7/10/1997 | | PEND |
|
|
|
received call from Stacey at Hobbsons regarding status. I told him plans were just brought back from Fire after lunch and still need structural corrections from CSHQA. Pkg # 1 being routed back to plumbing for final review.
|
Plan resubmittals received | | | 7/7/1997 | | FAIL |
|
|
|
received more revised plans from metal bldg manufacture for pkg 3 on 7-7-97. Still waiting for corrected plans from CHSQA so pkg. # 3 can go back to Stapley for review.
|
Plan Reviewer's activity | | | 7/1/1997 | | PEND |
|
|
|
Received additional plan corrections from Stapley. Faxed corrections to architect Holtz and draftsman for Hobson Stacy. MO
|
Routing Off Site - STRUCTURAL | 6/18/1997 | | 6/30/1997 | | FAIL |
|
|
|
resubmittals sent to Stapley for review 6-18-97. MO Plans again were rejected by Stapley with additional corrections for the metal building and the handicapped ramp. THese corrections were done be Greg Leishman from Stapley's. MO
|
Plan resubmittals received | | | 6/23/1997 | | PEND |
|
|
|
FOR PKG 1.
|
Telephone call | | | 6/20/1997 | | FAIL |
|
|
|
RECEIVED CALL FROM BRYCE STAPLEY THAT SUBMITTAL FROM METAL BLDG. MANUFACTURE DID NOT INCLUDE THE LINE ITEM RESPONSE AND THAT THE ANCHOR BOLTS THAT HAD BEEN PREVIOUSLY APPROVED APPEARED TO BE INSUFFICIENT. MO
|
Plan resubmittals received | | | 6/20/1997 | | FAIL |
|
|
|
RECEIVED LINE ITEM RESPONSE FROM METAL BLDG. COMPANY ENGINEER FOR STRUCTURAL FAXED TO STAPLEY. MO
|
Telephone call | | | 6/20/1997 | | FAIL |
|
|
|
CONTACTED STACY AT HOBBSON TOLD HIM ABOUT POSSIBLE PROBLEM WITH ANCHOR BOLTS AND TO HOLD-OFF ON POUR UNTIL RESOLVED. ALSO TOLD STACY ABOUT LACKING WRITTEN RESPONSE FROM ENGINEER AND LACK OF STRUCTRUAL DESIGN FOR HANDICAPPED RAMP.MO
|
Plan resubmittals received | | | 6/20/1997 | | |
|
|
|
RECEIVED STRUCTURAL PLANS AND CALCS FOR HANDICAPPED RAMP. SENT TO STAPLEY FOR REVIEW AND COMMENT.
|
Telephone call | | | 6/20/1997 | | FAIL |
|
|
|
CALLED DICK HOLTZ AND INFORMED HIM THAT LINE ITEM RESPONSE AS REQUESTED ON PLAN REVIEW COMMENTS FROM BLDG AND STRUCTRUAL ENGINEER WERE NOT INCLUDED WITH THE RESUBMITTAL AND NEED TO BE PROVIDED FROM THE METAL BLDG. MANUFACTURES ENGINEER.MO
|
(F) Reprint permit | | | 6/18/1997 | | |
|
|
|
|
Routing - FIRE | 6/11/1997 | | 6/18/1997 | | FAIL |
|
|
|
PACKAGE #1
|
Plan resubmittals requested | | | 6/11/1997 | | FAIL |
|
|
|
review of resubmittal of 6-3-97 pkg 1 completed with corrections mailed and faxed to architect and owner Ted Frisbee.
|
Routing Off Site - STRUCTURAL | 6/2/1997 | | 6/9/1997 | | PEND |
|
|
|
PACKAGE #3 RESUBS SENT TO STAPLEY VIA PDQ. 6-9-97\ RECEIVED LETTER FROM TI-FEI-LO STAPLEY'S OFFICE THAT THE FOUNDATION (EXCLUDING THE HANDICAPPED RAMP) WAS APPROVED AND NEEDS NO FURTHER REVIEW. THE REMAINDER OF THE STRUCTURE STILL REMAINS UNAPPROVED.
|
Plan resubmittals received | | | 6/3/1997 | | |
|
|
|
resubmittals received from meeting in april that put a hold on this project due to building out of compliance for area and type of construction. MO
|
90 day tracking............. | | 2/28/1997 | 5/29/1997 | | PEND |
|
|
|
|
Routing - PLANNING | 5/2/1997 | | 5/22/1997 | | PASS |
|
|
|
PACKAGE #2 X-REF: DR-62-96. APPROVED BY MGS.
|
Meeting | | | 4/3/1997 | | HOLD |
|
|
|
HAD MEETING WITH OWNER TED FRISBEE AND ARCHITECT DICK HOLTZ. DISCUSSED OVER AREA BUILDING, OCCUPANCY GROUPS, HAZARDOUS MATERIALS AND HANDICAPPED ACCESS.
|
Routing Off Site - STRUCTURAL | 3/7/1997 | | 4/3/1997 | | FAIL |
|
|
|
PACKAGE #3 ON HOLD WAITING 3RD. SET OF PLANS CONTACTED TED RECEIVED THIRD SET OF PLANS. SHIPPED PLANS BY PDQ TO STAPLEY ENGINEERING. 3/7/97 DAR Corrections received 4-3-97 and givent to architect and owner on 4-3-97 at meeting. MO
|
Routing - PUBLIC WORKS | 3/26/1997 | | 4/2/1997 | | PASS |
|
|
|
|
Plan assigned to (RGG) | 3/4/1997 | | 3/28/1997 | | |
|
|
|
|
Routing - PLANNING | 3/23/1997 | | 3/25/1997 | | FAIL |
|
|
|
PACKAGE #2 X-ref: DR-62-96. Applicant needs to provide revised plans per DR conditions of approval. Phoned Ted Frisbee 3/25/97.
|
Routing - PUBLIC WORKS | 3/4/1997 | | 3/21/1997 | | FAIL |
|
|
|
PACKAGE 2 REQUIRES DRAINAGE PLAN REVISION PER BM. DAR
|
Routing - FIRE | 3/14/1997 | | 3/17/1997 | | PEND |
|
|
|
PACKAGE #1 SENT TO FIRE FOR GRADING ONLY. 03-14-97 KMM GRADING ONLY PASSED 3/17/97
|
Received Certificate of Value | | | 3/14/1997 | | PASS |
|
|
|
RECEIVED NEW CERT. OF VALUES. ONE AT AN INITIAL VALUE OF 182,000 FOR GRADING AND ONE AT AN INITIAL VALUE OF 668,000 FOR BUILDING PERMIT. KMM 3-14-97
|
Routing - PLUMBING | 3/10/1997 | | 3/10/1997 | | FAIL |
|
|
|
PACKAGE #1
|
Routing - ELECTRICAL | 3/4/1997 | | 3/7/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing Off Site - A.C.H.D | 3/4/1997 | | 3/5/1997 | | PASS |
|
|
|
PACKAGE #4 CONTACTED TED FRISBEE AT ###-#### TO TAKE PLANS OUT TO ACHD
|
Received Certificate of Value | | | 3/4/1997 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 3/4/1997 | | PASS |
|
|
|
PACKAGE #3 ON HOLD WAITING 3RD SET. CONTACTED TED FRISBEE REGUARDING THIS NEED.
|
Routing - MECHANICAL | 3/4/1997 | | 3/4/1997 | | PASS |
|
|
|
PACKAGE #1 NO REVIEW FIELD VERIFY
|
Plan routing begun/NEW & ADDTN | | | 3/4/1997 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/28/1997 | | |
|
|
|
|
Application received | | | 2/28/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 8/18/1997 | | | | |
|
|
|
RESUBMITTED PLANS RETURNED FROM STAPLEY.
|