Permanent Occupancy | | 1/15/1998 | 1/15/1998 | | DONE |
|
|
|
|
Permanent Occupancy | | 1/15/1998 | 1/15/1998 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/15/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7102 issued 1-15-98 to Roundtree Lincoln Mercury Isuzu.
|
INSP - Final | 1/12/1998 | 1/12/1998 | 1/12/1998 | A | PASS |
|
|
|
signed the perm col on the occ req card
|
INSP-Final Inspection | 9/23/1997 | 9/24/1997 | 9/24/1997 | A | CANC |
Rick Jackson
|
|
|
they will reschedule, they were at funeral
|
INSP-Final Inspection | 9/22/1997 | 9/22/1997 | 9/22/1997 | P | CANC |
Joe Tawney
|
|
|
09/22/97 406 - call brian with mcalvain INSP CANCELLED BY CONTR PER TELECON WITH NATALIE
|
INSP - Final | 8/15/1997 | 8/15/1997 | 8/15/1997 | | PART |
|
|
|
/ / 338 - signed the temp col
|
INSP - Final | 8/15/1997 | 8/15/1997 | 8/15/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - FINAL OK FOR TEMP OCC ALARM SYSTEM CURB STRIPING RISER CLEAR
|
Temporary occupancy | | | 8/15/1997 | | PASS |
|
|
|
Temp. Occ. Cert. #3447 issued 8-15-97 to Roundtree Chevrolet.
|
INSP-Sprinkler Rough-in/Hydro | 8/13/1997 | 8/13/1997 | 8/13/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TEST OF WET PIPE SYSTEM
|
Routing Off Site - STRUCTURAL | 7/28/1997 | | 8/13/1997 | | |
|
|
|
RESUBS SENT TO CH2MHILL
|
INSP-Supply line flush | 8/12/1997 | 8/12/1997 | 8/12/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND FLUSH
|
INSP-Sprinkler Rough-in/Hydro | 8/11/1997 | 8/11/1997 | 8/11/1997 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON SPKLR ROUGH IN
|
Routing - PLUMBING | 7/24/1997 | | 7/28/1997 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/20/1997 | | 7/24/1997 | | FAIL |
|
|
|
PACKAGE #2 RESUBS TO PW NEEDS DRAINAGE PLAN REVISION
|
INSP - Framing/Rough-in | 7/16/1997 | 7/17/1997 | 7/17/1997 | A | PART |
|
|
|
07/17/97 338 - interior studs. late a.m. ok to cover with the ele and p attachments of met5al stud framing ok per the approved plan on file
|
INSP - Carpentry | 7/9/1997 | 7/10/1997 | 7/10/1997 | P | PART |
|
|
|
07/10/97 338 - ROOF NAILING INSPECTION roof deck ok still need 4 point c 5/8 studs
|
INSP - Framing/Rough-in | 7/2/1997 | 7/2/1997 | 7/2/1997 | A | |
|
|
|
active service
|
Routing for occupancy | 6/10/1997 | 6/12/1997 | 6/12/1997 | | TEMP |
|
|
|
Inspected by Art Yingl;ing - Temp Signed - Two bonds posted - 1 for Project ($68,242.00) & $16,151 for micro path
|
90 day tracking............. | | 3/10/1997 | 6/8/1997 | | |
|
|
|
|
Routing - PLANNING | 5/19/1997 | | 5/20/1997 | | PASS |
|
|
|
RESUBMITALLS SENT TO P&Z X-REF: CU-46-95/MOD & DR-92-95/MOD. APPROVED BY TKW.
|
INSP - Footings | 5/19/1997 | 5/19/1997 | 5/19/1997 | P | PART |
|
|
|
05/20/97 333 - part
|
Plan resubmittals received | | | 5/16/1997 | | |
|
|
|
REVISED PLANS FOR APPROVED PROJECT SUBMITTED THIS DATE: WILL NEED TO BE ROUTED TO ALL DEPTS. AFFECTED BY CHANGES. MO.
|
(F) Reprint permit | | | 5/13/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/12/1997 | | |
|
|
|
|
Telephone call | | | 5/9/1997 | | PASS |
|
|
|
AMY WILL HAVE A RUNNER COME AND GET IT.
|
Inspection Record Card- Bld | | | 5/9/1997 | | |
|
|
|
|
Print Occupancy Form | | | 5/9/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 4/11/1997 | | 5/8/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLAN CHECK | 4/7/1997 | | 5/8/1997 | | PASS |
|
|
|
PACKAGE #3
|
Routing - PLAN CHECK | 4/8/1997 | | 5/8/1997 | | PASS |
|
|
|
PACKAGE #4
|
Routing - PLAN CHECK | 3/26/1997 | | 5/8/1997 | | PASS |
|
|
|
PACKAGE #2
|
Plan assigned to (M_O) | 4/3/1997 | | 5/8/1997 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/8/1997 | | PASS |
|
|
|
|
Received Certificate of Value | | | 5/8/1997 | | PASS |
|
|
|
|
Waiting for Cert. of Value | | | 5/7/1997 | | PASS |
|
|
|
SPOKE WITH ARCHITECT BRUCE POE ABOUT PROVIDING CERTIFICATE OF VALUE SO PERMIT PROCESSING CAN BE COMPLETED. MO
|
Plan resubmittals received | | | 5/6/1997 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/2/1997 | | 5/6/1997 | | PASS |
|
|
|
RESUBS SENT TO CH2MHILL
|
Plan resubmittals requested | | | 5/1/1997 | | |
|
|
|
|
Plan resubmittals received | | | 4/29/1997 | | |
|
|
|
|
Routing - FIRE | 4/9/1997 | | 4/11/1997 | | PASS |
|
|
|
PACKAGE #1
|
Plan resubmittals requested | | | 4/9/1997 | | FAIL |
|
|
|
corrections mailed and faxed to architect 4-9-97 MO.
|
Routing Off Site - A.C.H.D | 3/11/1997 | | 4/8/1997 | | PASS |
|
|
|
PACKAGE #4 CONTACTED BRUCE POE AT ###-#### TO TAKE PLANS OUT TO ACHD ACHD FEES NOT PAID 4/8/97 DAR
|
Routing Off Site - STRUCTURAL | 3/11/1997 | | 4/7/1997 | | FAIL |
|
|
|
PACKAGE #3 CONTACT PDQ TO TAKE PLANS OUT TO CH2MHILL ATTEN: GRAIG BARRETT. RECEIVED STRUCTURAL REVIEW FROM CH2MHILL AND GAVE TO MIKE O. KMM 4-7-97 CORRECTION LIST GIVEN TO BRUCE POE 4-7-97. MO
|
Plan assigned to (RGG) | 3/11/1997 | | 4/4/1997 | | |
|
|
|
|
Plan resubmittals received | | | 3/28/1997 | | PASS |
|
|
|
Received E2.0 and 4.1 sheets for package #1. 3-26-97
|
Routing - PLANNING | 3/21/1997 | | 3/26/1997 | | PASS |
|
|
|
PACKAGE #2 X-ref: CU-46-95 & DR-92-95. Approved by SRS & TKW.
|
Routing - PUBLIC WORKS | 3/11/1997 | | 3/21/1997 | | PASS |
|
|
|
PACKAGE #2
|
Routing - PLUMBING | 3/17/1997 | | 3/18/1997 | | PASS |
|
|
|
PACKAGE #1
|
Received Certificate of Value | | | 3/11/1997 | | PASS |
|
|
|
|
Routing - MECHANICAL | 3/11/1997 | | 3/11/1997 | | PASS |
|
|
|
NO REVIEW WILL FIELD VERIFY PACKAGE #1
|
Plan routing begun/NEW & ADDTN | | | 3/11/1997 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 3/10/1997 | | 3/11/1997 | | PEND |
Marlene Southard
|
|
|
|
Application received | | | 3/10/1997 | | |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 3/10/1997 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/10/1997 | | |
|
|
|
|
Routing - ELECTRICAL | 3/11/1997 | | 3/17/1994 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLAN CHECK | 5/20/1997 | | | | |
|
|
|
RESUB. FROM P&Z PACKAGE #2
|