Permanent occupancy | | | 10/4/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8852 issued 10-4-01 to Micron Technology.
|
Permanent Occupancy | | 9/21/2001 | 9/21/2001 | | DONE |
|
|
|
|
BLD-Final | 9/20/2001 | 9/21/2001 | 9/21/2001 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/20/2001 at 08:21:29. Contact: ###-####. final ok, 9/21/2001 12:23:57 PM
|
BLD-Conference | 9/10/2001 | 9/11/2001 | 9/11/2001 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 09/10/2001 at 11:13:43. Contact: ###-####. finsh scope of work. 9/12/2001 1:07:52 PM
|
BLD-Final | 8/30/2001 | 8/30/2001 | 8/30/2001 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/30/2001 at 07:38:02. Contact: ###-####. north exit door needs landing 1/4 slope and 44 depth. 8/31/2001 10:00:41 AM
|
BLD-Final | 8/24/2001 | 8/24/2001 | 8/24/2001 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/24/2001 at 08:52:35. Contact: ###-####.
|
BLD-Final | 8/17/2001 | 8/17/2001 | 8/17/2001 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 08/17/2001 at 09:07:47. Contact: ###-####.
|
FIRE-Final Inspection | 8/15/2001 | 8/15/2001 | 8/15/2001 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/15/2001 at 07:44:50. Contact: ###-####. 8/15/2001 9:22:17 AM
|
Code Occupancy Approval | | | 8/15/2001 | | PASS |
|
|
|
Inspected and passed.
|
Print Occupancy Form | | | 7/13/2001 | | DONE |
|
|
|
|
90 day tracking............. | | 3/17/1997 | 6/15/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/19/1997 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/7/1997 | | PASS |
|
|
|
|
Telephone call | | | 5/7/1997 | | |
|
|
|
CALLED BOB AT K-2 CONSTRUCTION PERMIT READY
|
Inspection Record Card- Bld | | | 5/7/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/7/1997 | | PASS |
|
|
|
|
Print Occupancy Form | | | 5/7/1997 | | |
|
|
|
|
Routing - FIRE | 4/23/1997 | | 5/5/1997 | | PASS |
|
|
|
|
Plan assigned to (RGG) | 3/17/1997 | | 4/23/1997 | | PASS |
|
|
|
PC# 126-97
|
Waiting for Cert. of Value | | | 4/23/1997 | | HOLD |
|
|
|
WE NEED A UPDATED CERTIFICATE OF VALUE SHOWING ELECTRICAL.
|
Routing - ELECTRICAL | 4/23/1997 | | 4/23/1997 | | PASS |
|
|
|
TO BE FIELD REVIEWED.
|
Routing - PLANNING | 3/27/1997 | | 3/31/1997 | | PASS |
|
|
|
X-ref: CU-5-97. Approved by RC & RLB.
|
Routing - PUBLIC WORKS | 3/20/1997 | | 3/27/1997 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 3/20/1997 | | PASS |
|
|
|
received stamped and signed structural sheet from Bob Lemoine.
|
Plan routing begun/NEW & ADDTN | | | 3/20/1997 | | PASS |
|
|
|
|
Received Certificate of Value | | | 3/17/1997 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 3/17/1997 | | HOLD |
|
|
|
WAITING FOR STAMP AND SIGN. ON STRUCTURAL SHEETS 1 THRU 7. CONTACTED BOB LEMOINE INFORMING HIM OF THIS NEED.
|
Application received | | | 3/14/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 3/31/1997 | | | | |
|
|
|
|
Routing - PLAN CHECK | 5/5/1997 | | | | |
|
|
|
|