Permanent Occupancy | | 7/15/1997 | 7/15/1997 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/15/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6913 issued 7-15-97 to Stellar Mortgage Co.
|
INSP - Final | 7/14/1997 | 7/14/1997 | 7/14/1997 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP FOR FINAL OK FOR PERM OCC
|
INSP - Final | 7/11/1997 | 7/11/1997 | 7/11/1997 | P | PASS |
Tom Arcoraci
|
|
|
temp oc until fire sign off
|
INSP-Final Inspection | 7/11/1997 | 7/11/1997 | 7/11/1997 | P | PART |
Joe Tawney
|
|
|
07/11/97 406 - REINSP FOR FINAL OK FOR TEMP OCC TEST EMERG LIGHTS
|
INSP - Final | 6/30/1997 | 7/1/1997 | 7/1/1997 | A | NR |
|
|
|
07/01/97 338 - not ready
|
INSP-Final Inspection | 6/30/1997 | 7/1/1997 | 7/1/1997 | A | FAIL |
Joe Tawney
|
|
|
07/01/97 406 - FINAL FAIL MOVE EXIT SIGN INSTALL EMERG LIGHTING
|
90 day tracking............. | | 3/27/1997 | 6/25/1997 | | PEND |
|
|
|
|
INSP - Final | 6/11/1997 | 6/11/1997 | 6/11/1997 | P | NR |
|
|
|
06/11/97 338 - LATE P.M.
|
INSP - Framing/ Rough-in | 5/21/1997 | 5/21/1997 | 5/21/1997 | | PASS |
|
|
|
/ / 338 - made ok with verbal fixes
|
INSP - Framing/Rough-in | 5/19/1997 | 5/20/1997 | 5/20/1997 | A | CANC |
Jim Sly
|
|
|
THIS WAS SCHEDULED FOR PM 5/19/97-YOU WERE IN A MEETING CALLED KIM, HE STATED THAT HE'D TRY TO MAKE IT OUT THERE. WASN'T SURE
|
INSP - Conference | 5/20/1997 | 5/20/1997 | 5/19/1997 | P | NH |
|
|
|
05/20/97 333 - no one there
|
Issue PAID IN FULL permit | | | 4/14/1997 | | |
|
|
|
|
Telephone call | | | 4/11/1997 | | PASS |
|
|
|
CALLED CLAY LEFT MESSAGE
|
Inspection Record Card- Bld | | | 4/11/1997 | | |
|
|
|
|
Print Occupancy Form | | | 4/11/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/11/1997 | | PASS |
|
|
|
Recieved corrections ready to issue.
|
Print Pending Permit.LaserJet4 | | | 4/11/1997 | | PASS |
|
|
|
|
Plan assigned to (R_H) | 3/27/1997 | | 4/11/1997 | | PASS |
|
|
|
04/11/97 09:20:30 R_H - this action updated by action script from <<>> in Case No. BLD97-0722
|
Routing - FIRE | 4/9/1997 | | 4/10/1997 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/4/1997 | | 4/9/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 4/8/1997 | | |
|
|
|
Started plan review
|
Plan Reviewer's activity | | | 4/8/1997 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 4/1/1997 | | 4/4/1997 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 4/1/1997 | | |
|
|
|
Route to PUBLIC WORKS then back to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT.
|
Application received | | | 3/27/1997 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/27/1997 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 4/10/1997 | | | | |
|
|
|
|