Permanent occupancy | | | 12/10/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7535 issued 12-10-98 to the Renaissance Apts., Bldg. #8.
|
INSP - Final | 12/8/1998 | 12/8/1998 | 12/8/1998 | P | PASS |
Jim Sly
|
|
|
12/08/98 316 -
|
Permanent Occupancy | | 12/8/1998 | 12/8/1998 | | DONE |
|
|
|
|
INSP - Final | 12/1/1998 | 12/2/1998 | 12/2/1998 | P | FAIL |
Jim Sly
|
|
|
12/02/98 316 - Scheduled by Hello!.
|
Temporary occupancy | | | 9/8/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3691 issued 9-8-98 to the Renaissance Apts.
|
INSP-Final Inspection | 9/1/1998 | 9/3/1998 | 9/3/1998 | A | PASS |
Joe Tawney
|
|
|
09/03/98 406 - Scheduled by Hello!. Contact phone is [9395335]. FINAL OK FOR PERM OCC
|
INSP - Final | 9/1/1998 | 9/3/1998 | 9/3/1998 | P | PART |
Jim Sly
|
|
|
09/03/98 316 - OK for Temp Occ. C/N...1 1/2 " clear on handrails, adjust
|
INSP-Alarm Testing | 9/1/1998 | 9/3/1998 | 9/3/1998 | A | PASS |
Joe Tawney
|
|
|
09/03/98 406 - Scheduled by Hello!. Contact phone is [9395335]. FINAL OK ON ALARM TEST
|
INSP-Sprinkler Rough-in/Hydro | 7/17/1998 | 7/17/1998 | 7/17/1998 | P | PART |
Joe Tawney
|
|
|
07/17/98 406 - ###-#### renaissance OK ON FDC HYDRO TEST
|
INSP - Energy code compliance | 6/12/1998 | 6/12/1998 | 6/12/1998 | P | PASS |
Jim Sly
|
|
|
06/12/98 316 - Scheduled by Hello!. Contact phone is [9395335].
|
INSP - Framing/Rough-in | 6/11/1998 | 6/12/1998 | 6/12/1998 | A | FAIL |
Jim Sly
|
|
|
06/12/98 316 - Complete prv corr notice.............. [9395335].
|
INSP - Framing/Rough-in | 6/12/1998 | 6/12/1998 | 6/12/1998 | P | PASS |
Jim Sly
|
|
|
06/12/98 316 - Scheduled by Hello!. Contact phone is [9395335].
|
INSP - Framing/Rough-in | 6/11/1998 | 6/11/1998 | 6/11/1998 | P | PART |
Jim Sly
|
|
|
06/11/98 316 - !st floor only....... Contact phone is [9395335].
|
INSP - Framing/Rough-in | 6/10/1998 | 6/10/1998 | 6/10/1998 | P | FAIL |
Jim Sly
|
|
|
06/10/98 316 - C/N..Draftst, elect box 24" horiz, fireblk chimn, extend
|
INSP - Framing/Rough-in | 5/28/1998 | 5/29/1998 | 5/29/1998 | A | PART |
Jim Sly
|
|
|
05/29/98 316 - OK for pre rock only..Kitch Bath Utility..............
|
INSP - Framing/Rough-in | 5/20/1998 | 5/21/1998 | 5/21/1998 | A | FAIL |
Jim Sly
|
|
|
05/21/98 316 - C/N...Complete chimn, firblk, fireclk, Cont gyp membr at
|
INSP - Framing/Rough-in | 5/19/1998 | 5/19/1998 | 5/19/1998 | P | PART |
Jim Sly
|
|
|
05/19/98 316 - OK for pre-rock Bath, Kitch and util....
|
INSP-Supply line flush | 5/4/1998 | 5/4/1998 | 5/4/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND FLUSH
|
INSP - Wall cover | 4/28/1998 | 4/29/1998 | 4/29/1998 | A | PART |
Jim Sly
|
|
|
04/29/98 316 - Shear and HDs OK at stair towers.
|
INSP - Framing/Rough-in | 4/22/1998 | 4/23/1998 | 4/23/1998 | A | FAIL |
Jim Sly
|
|
|
04/23/98 316 - Missed holdown on S. E. stair tower...
|
INSP-Sprinkler Rough-in/Hydro | 4/10/1998 | 4/13/1998 | 4/13/1998 | A | PART |
Joe Tawney
|
|
|
Scheduled by Hello!. Contact phone is [9395335]. OK ON ROUGH IN & OK ON HYDRO TEST EXC FDC PIPING
|
INSP - Foundation | 3/19/1998 | 3/20/1998 | 3/20/1998 | A | CANC |
Tom Arcoraci
|
|
|
03/20/98 408 - Scheduled by Hello!. Contact phone is [9395335]. done by 316
|
INSP - Foundation | 3/4/1998 | 3/4/1998 | 3/4/1998 | P | PART |
Jim Sly
|
|
|
03/04/98 316 - Holdowns only OK Contact phone is [9395335].
|
Issue PAID IN FULL permit | | | 7/22/1997 | | |
|
|
|
|
Telephone call | | | 7/1/1997 | | |
|
|
|
CALLED CINDY AT DUKE/ PERMITS READY, FEE DUE
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/30/1997 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 6/30/1997 | | |
|
|
|
|
Print Occupancy Form | | | 6/30/1997 | | |
|
|
|
|
Print permit w/o conditions | | | 6/24/1997 | | |
|
|
|
|
testing condition printout | | | 6/24/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 6/6/1997 | | PASS |
|
|
|
Drawings approved June 6, 1997 after resubmittal review.
|
Plan resubmittals received | | | 5/16/1997 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 4/30/1997 | | |
|
|
|
See actions attached to BLD97-0407 for additional information.
|
Plan Reviewer's activity | | | 4/9/1997 | | |
|
|
|
UBC plan check started April 9, 1997 and completed April 16, 1997. Report sent to the Architect. A report slightly modified from the original was sent April 30, 1997.
|
Application received | | | 2/25/1997 | | |
|
|
|
|