Fee Review-notes | 7/14/1998 | | 9/10/1998 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/5/1998 | | PASS |
|
|
|
|
INSP - Final | 7/16/1998 | 7/16/1998 | 7/16/1998 | A | PASS |
|
|
|
07/16/98 333 - final ok
|
Permanent Occupancy | | 7/15/1998 | 7/15/1998 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/15/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7313 issued 7-15-98 to the Diamon's Sports Even Offices.
|
INSP - Final | 7/7/1998 | 7/7/1998 | 7/7/1998 | | PART |
|
|
|
/ / 333 - PROFIT MEETING
|
CHANGE STATUS TO (I) | | | 6/23/1998 | | |
|
|
|
|
INSP-Final Inspection | 6/18/1998 | 6/18/1998 | 6/18/1998 | P | PASS |
Rick Jackson
|
|
|
occ approved
|
Receive PAYMENT IN FULL | | | 6/12/1998 | | |
|
|
|
|
INSP - Final | 6/11/1998 | 6/11/1998 | 6/11/1998 | A | FAIL |
|
|
|
06/11/98 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
Receive PAYMENT IN FULL | | | 6/5/1998 | | |
|
|
|
|
CHANGE STATUS TO (F) | | | 4/7/1998 | | |
|
|
|
|
(F) Reprint permit | | | 4/7/1998 | | |
|
|
|
|
FEE REVIEW-NOTES | | | 4/7/1998 | | FEES |
|
|
|
FEES DUE ADDITIONAL VALUES
|
INSP - Final | 3/26/1998 | 3/26/1998 | 3/26/1998 | | PART |
|
|
|
/ / 333 - profit meeting
|
(F) Reprint permit | | | 3/25/1998 | | |
|
|
|
|
Temporary occupancy | | | 3/3/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3561 issued to the event level offices.
|
INSP - Final | 2/2/1998 | 2/2/1998 | 2/2/1998 | P | PASS |
|
|
|
02/02/98 333 - card signed for temp cn placed
|
INSP-Final Inspection | 1/30/1998 | 1/30/1998 | 1/30/1998 | P | PASS |
Rick Jackson
|
|
|
occ card signed for perm.
|
INSP - Final | 12/29/1997 | 12/29/1997 | 12/29/1997 | P | FAIL |
|
|
|
12/29/97 333 - cn not made
|
Print permit w/o conditions | | | 10/14/1997 | | |
|
|
|
|
INSP - Framing/Rough-in | 8/8/1997 | 8/8/1997 | 8/8/1997 | P | PART |
|
|
|
08/08/97 333 - in progress
|
(F) Reprint permit | | | 7/21/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/30/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/30/1997 | | |
|
|
|
|
Print Occupancy Form | | | 6/30/1997 | | |
|
|
|
|
Telephone call | | | 6/30/1997 | | |
|
|
|
TALKED TO SKIP HYDE/ PERMIT READY
|
FEE REVIEW-NOTES | | | 6/30/1997 | | FEES |
|
|
|
refunded 4472.90
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/1997 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 4/10/1997 | | 6/27/1997 | | PASS |
Carl Westfall
|
|
|
06/27/97 09:15:10 CJW - this action updated by action script from <<>> in Case No. BLD97-0870
|
testing condition printout | | | 6/26/1997 | | |
|
|
|
|
Waiting for Cert. of Value | | | 6/26/1997 | | |
|
|
|
Called Skip and ask for a Certificate of Value for the event level offices only. Left message on "Voice Mail".
|
Print permit w/o conditions | | | 6/26/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 6/26/1997 | | PASS |
|
|
|
Drawings for the event level offices only approved after resubmittal review.
|
Plan resubmittals received | | | 6/25/1997 | | |
|
|
|
|
Routing - FIRE | 6/4/1997 | | 6/6/1997 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 5/19/1997 | | |
|
|
|
UBC plan check for the event level offices started May 19, 1997 and completed May 23,1997. Copy of plan check report given personally to Architect on May 29, 1997.
|
Routing - PLUMBING | 5/14/1997 | | 5/16/1997 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/8/1997 | | 5/13/1997 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 5/5/1997 | | 5/8/1997 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 4/10/1997 | | 4/30/1997 | | FAIL |
|
|
|
|
Plan routing begun/TENANTS | | | 4/10/1997 | | |
|
|
|
Route to CENTRAL DISTRICT HEALTH, PUBLIC WORKS, PLUMBING then back to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT.
|
Routing - PLAN CHECK | 4/10/1997 | | 4/10/1997 | | |
|
|
|
|
Application received | | | 4/9/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 5/16/1997 | | | | |
|
|
|
|
Routing - PLAN CHECK | 6/6/1997 | | | | |
|
|
|
|
Routing - PLAN CHECK | 4/30/1997 | | | | |
|
|
|
|