Information based on query as of Friday, July 19, 2024.
Permit Information
Permit NumberBLD97-00887
StatusFinaled
Name STEVE SEVERN
Site Address 415 S 4TH ST
Project Name 
Customer Number 
ePlanReviewNo
Description
REYNOLDS, STANTON & WINKLE OFFICE BUILDING * TO REMOVE TWO EXISTING SINGLE FAMILY DWELLINGS AND A DETACHED STORAGE SHED; AND TO THEN CONSTRUCT A NEW 6,165 SQ. FT., TWO STORY, WOOD FRAME OFFICE BUILDING AND RELATED SITE IMPROVEMENTS. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. THIS BUILDING IS NOT PROTECTED BY AN AUTOMATIC FIRE SPRINKLER SYSTEM. DR-91-96/PC#193-97/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final3/18/19983/19/19983/19/1998APASS
Details
03/19/98 333 - card signed for Final for perm. occ.
Permanent occupancy  3/19/1998 PASS
Perm. Occ. Cert. #7175 issued 3-19-98 to Reynolds, Stanton and Winkle.
Permanent Occupancy 3/18/19983/18/1998 DONE
Details
Code Occupancy Approval  3/18/1998 PASS
Final signed. All landscaping and paving etc.. done according to 11/21/96 file plan. Bond release form signed.
(F) Reprint permit  12/8/1997
INSP - Final11/26/199711/28/199711/28/1997APART
Details
11/28/97 333 - CARD SIGNED FOR TEMP OTHER TRADE SIGNATURES NEEDED
Temporary occupancy  11/28/1997 PASS
Temp. Occ. Cert. #3511 issued 11-28-97 to Reynolds, Stanton and Winkle.
INSP-Final Inspection11/26/199711/26/199711/26/1997APASS
DetailsRick Jackson
11/26/97 409 - occupancy approved
INSP - Final11/20/199711/24/199711/24/1997AFAIL
Details
CN PLACED
INSP-Final Inspection11/20/199711/24/199711/24/1997AFAIL
DetailsRick Jackson
11/24/97 409 - MEETING WITH KIM AND GC 1030 adjust corridor doors, retest smoke detectors, address
INSP - Framing/Rough-in11/12/199711/13/199711/13/1997APASS
Details
11/13/97 333 - SAYS YOU HAVE 9:30 APT FOR CEILING GRID grid ok
INSP - Framing/Rough-in9/26/19979/29/19979/29/1997PPASS
Details
09/29/97 333 - FRAM-OK FRAMING
INSP - Conference9/5/19979/8/19979/8/1997APASS
Details
09/08/97 333 - recieved resub
INSP - Framing/Rough-in8/28/19978/29/19978/29/1997APASS
Details
08/29/97 333 - ok to install soffit prop line wall ok
INSP - Conference7/24/19977/24/19977/24/1997APASS
Details
/ / 333 - reviewed change at lproperty line wall approved same
INSP - Carpentry7/23/19977/22/19977/23/1997PPART
Details
/ / 333 - resubmittal review
INSP - Foundation7/17/19977/17/19977/17/1997PPASS
Details
07/17/97 333 - FDN -OK FOUNDATION
INSP - Footings7/14/19977/15/19977/15/1997APASS
Details
07/15/97 333 - FTG -OK FOOTING
INSP - Footings7/14/19977/14/19977/14/1997PPASS
Details
07/14/97 333 - FTG -OK FOOTING
90 day tracking............. 4/11/19977/10/1997
(F) Reprint permit  7/3/1997
Issue PAID IN FULL permit  7/2/1997
PLANS/APPL TAKEN TO FRONT DESK  7/1/1997 PASS
Print Occupancy Form  7/1/1997
Telephone call  7/1/1997 PASS
DOUG HOUSTON\JANE WILL HAVE DOUG COME IN TO GET THIS
Routing - PLAN CHECK6/25/1997 7/1/1997 PASS
Inspection Record Card- Bld  7/1/1997
Routing - PLAN CHECK4/25/1997 7/1/1997 PASS
PACKAGE #3
Routing - PLAN CHECK6/17/1997 7/1/1997 PASS
PACKAGE #2
Plan assigned to (JCM)5/5/1997 7/1/1997 PASS
DetailsJohn Menard
Routing Off Site - A.C.H.D4/14/1997 6/25/1997 PASS
PACKAGE #4 CONTACTED DOUG HOUSTON AT ###-#### TO TAKE PLANS OUT TO ACHD ACHD FEES ARE PAID. ACHD CERT. #97-1425
Routing - PLANNING6/11/1997 6/16/1997 PASS
Approved by: MGS
Plan resubmittals received  6/10/1997 PASS
Routing - PUBLIC WORKS6/4/1997 6/10/1997 PASS
PACKAGE #2
Plan resubmittals requested  6/4/1997 PEND
Routing - PLAN CHECK5/8/1997 6/4/1997 PEND
PACKAGE #2
Plan resubmittals received  6/3/1997 PEND
Routing - FIRE5/13/1997 5/14/1997 PASS
PACKAGE #1
Routing - PLAN CHECK4/22/1997 5/13/1997 PEND
PACKAGE #1
Plan resubmittals requested  5/12/1997 PEND
CORRECTION LIST SENT TO DOUGLAS HOUSTON AT OLSON & ASSOCIATES FOR REQUESTED REVISIONS.
Routing - PLANNING4/29/1997 5/6/1997 FAIL
PACKAGE #2 X-ref: DR-91-96. Need to comply with conditions & revise landscape design in order to interface with drainage ponds. Met with Doug Hauston 5/6/97 to go over these issues. Reviewed by MGS.
Routing - PUBLIC WORKS4/14/1997 4/29/1997 FAIL
PACKAGE #2 NEEDS DRAINAGE PLAN REVISION. BM
Routing Off Site - STRUCTURAL4/14/1997 4/25/1997
PACKAGE #3 CONTACTED PDQ TO TAKE PLANS OUT TO STAPLEY ENG.
Routing - PLUMBING4/17/1997 4/21/1997 PASS
PACKAGE #1
Routing - ELECTRICAL4/14/1997 4/17/1997 PASS
PACKAGE #1
Plan assigned to (MYS)4/11/1997 4/14/1997
DetailsMarlene Southard
Received Certificate of Value  4/14/1997 PASS
Plans ACCEPTED BY PLAN CHECK  4/14/1997 PASS
Plan routing begun/NEW & ADDTN4/14/1997 4/14/1997
Recd Pcfee & Taken To Pln CK  4/11/1997
Application received  4/11/1997
Plan assigned to (RGG)4/14/1997 4/5/1997