Permanent occupancy | | | 6/10/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7273 issued 6-10-98 to the Life Care Center (addn.).
|
Permanent Occupancy | | 6/4/1998 | 6/4/1998 | | DONE |
|
|
|
|
INSP - Final | 6/3/1998 | 6/4/1998 | 6/4/1998 | A | PASS |
|
|
|
06/04/98 338 - made ok will sign card a t the office
|
Code Occupancy Approval | | | 6/2/1998 | | PASS |
|
|
|
Bonded for temporary - landscaping, sprklr. system and parking needs to be done per compliance w/ AA-56-97 ($46,526.00) CAM. Requested Final Inspection (6/2/98)- Inspected made - Passed. Bond release executed.
|
INSP - Final | 5/7/1998 | 5/7/1998 | 5/7/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
INSP-Conference | 3/19/1998 | 3/19/1998 | 3/19/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - CONF ON ALARM SYSTEM WITH HAROLD OF MOUNTAIN POWER
|
INSP - Final | 3/19/1998 | 3/19/1998 | 3/19/1998 | | PART |
|
|
|
/ / 338 - made ok for temp c/n issued mark aat 8630507
|
Temporary occupancy | | | 3/19/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3578 issued 3-19-98 to the Life Care Center.
|
INSP - Final | 3/18/1998 | 3/18/1998 | 3/18/1998 | P | NR |
|
|
|
03/18/98 338 - moved insp to tomorrow out of time no one on jobsite for
|
INSP - Final | 3/10/1998 | 3/11/1998 | 3/11/1998 | P | NR |
|
|
|
03/11/98 338 - Scheduled by Hello!. OTH-OTHER AGENCIES NOT APPROVED
|
INSP-Final Inspection | 3/10/1998 | 3/11/1998 | 3/11/1998 | P | FAIL |
Joe Tawney
|
|
|
03/11/98 406 - bill ###-#### FINAL FOR TEMP ON NEW ADDITION FAIL SMOKE SEAL LANDING DOOR SIGN
|
INSP - Framing/Rough-in | 2/9/1998 | 2/9/1998 | 2/9/1998 | P | PART |
|
|
|
02/09/98 338 - markus ###-#### drop ceiling ok to drop in tiles need to at the sprinkler drops
|
INSP-Sprinkler Rough-in/Hydro | 2/2/1998 | 2/2/1998 | 2/2/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON SPKLR ROUGH IN OF AREA BELOW GRID & OK ON HYDRO TEST N
|
INSP - Energy code compliance | 12/30/1997 | 12/31/1997 | 12/31/1997 | A | CANC |
|
|
|
not needed not required
|
INSP - Framing/Rough-in | 12/23/1997 | 12/23/1997 | 12/24/1997 | P | NH |
|
|
|
12/24/97 338 - LIFE CARE CENTER no ACCESS
|
INSP - Wall cover | 12/8/1997 | 12/9/1997 | 12/9/1997 | A | PART |
|
|
|
12/09/97 338 - sent to 408
|
INSP - Wall cover | 12/5/1997 | 12/5/1997 | 12/8/1997 | P | NR |
|
|
|
12/05/97 338 - LIFE CARE CENTER
|
INSP - Framing/Rough-in | 12/3/1997 | 12/3/1997 | 12/4/1997 | P | CANC |
|
|
|
12/04/97 338 - sent to 301
|
INSP - Framing/Rough-in | 12/2/1997 | 12/3/1997 | 12/4/1997 | A | PASS |
|
|
|
12/03/97 338 - made ok for the conference on the 2-hour wall
|
INSP - Framing/Rough-in | 12/1/1997 | 12/1/1997 | 12/1/1997 | P | CANC |
|
|
|
12/01/97 338 - canc given to 342
|
INSP - Framing/Rough-in | 12/1/1997 | 12/1/1997 | 12/1/1997 | P | NR |
Wes Worcester
|
|
|
no other signatures and 2 hr wall is wrong....need detailed fix and do not cover
|
INSP - Roof | 11/18/1997 | 11/18/1997 | 11/18/1997 | P | PART |
|
|
|
11/18/97 333 - renail ok
|
INSP - Roof | 11/17/1997 | 11/17/1997 | 11/17/1997 | P | PART |
|
|
|
ROOF SHEATHING in progress
|
INSP - Foundation | 10/24/1997 | 10/24/1997 | 10/24/1997 | P | PASS |
|
|
|
r-bar placed ok to pour
|
INSP - Footings | 10/22/1997 | 10/23/1997 | 10/22/1997 | A | PASS |
|
|
|
made ok the r-bar is placed
|
Issue PAID IN FULL permit | | | 10/10/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 9/18/1997 | | 10/9/1997 | | |
|
|
|
PACKAGE #3
|
Print Occupancy Form | | | 10/9/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/9/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/9/1997 | | PASS |
|
|
|
|
Plan assigned to (M_P) | 7/22/1997 | | 10/9/1997 | | PASS |
Mike Phillips
|
|
|
10/09/97 09:03:11 KMM - this action updated by action script from <<>> in Case No. BLD97-1013
|
Routing - PLAN CHECK | 10/6/1997 | | 10/9/1997 | | |
|
|
|
PACKAGE #4
|
Routing - PLAN CHECK | 10/3/1997 | | 10/9/1997 | | |
|
|
|
package 2
|
Plan Reviewer's activity | | | 10/8/1997 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/8/1997 | | PASS |
|
|
|
|
Waiting for Cert. of Value | | | 10/7/1997 | | PEND |
|
|
|
Waiting for certificate of value. one must be submitted to discribe the work which will take place on each side of the area separation wall.
|
Plan Reviewer's activity | | | 10/7/1997 | | PEND |
|
|
|
WAITING FOR CERTIFICATE OF VALUE. ONE MUST BE SUBMITTED DISCRIBING THE WORK AND THE VALUE OF THE PROJECT ON EACH SIDE OF THE AREA SEPARATION WALLS.
|
Routing Off Site - A.C.H.D | 6/30/1997 | | 10/6/1997 | | PASS |
|
|
|
#4 CONTACTED DEAN BRIGGS AT ###-#### TO TAKE PLANS OUT TO ACHD NO ACHD IMPACT FEES DUE
|
Plan Reviewer's activity | | | 10/6/1997 | | PEND |
|
|
|
WAITING FOR ACHD INFORMATION.
|
Routing - PLANNING | 9/16/1997 | | 10/1/1997 | | PASS |
|
|
|
Approved by: SAR
|
Routing - FIRE | 10/1/1997 | | 10/1/1997 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/29/1997 | | 10/1/1997 | | |
|
|
|
PACKAGE #1
|
Routing - FIRE | 9/10/1997 | | 9/29/1997 | | FAIL |
|
|
|
PACKAGE #1
|
Plan resubmittals received | | | 9/25/1997 | | |
|
|
|
RECEIVED PLAN RESUBMITTALS WAITING FOR PANS TO RETURN FROM FIRE.
|
Routing Off Site - STRUCTURAL | 9/8/1997 | | 9/18/1997 | | PASS |
|
|
|
CONTACTED PDQ TO TAKE PLANS OUT TO CH2MHILL FOR RESUB REVIEW RESUBS RETURNED 9-18-97 WITH REVIEW LETTER AND RESPONSE LETTER (1 SET) NO PLANS RETURNED AT THIS TIME. Structural review complete no futher review required from oput side engineer.
|
Plan resubmittals requested | | | 9/10/1997 | | FAIL |
|
|
|
SECOND SET OF CORRECTIONS REQUESTED, AND WAITING FOR OUTSIDE STRUCTURAL COMMENTS TO RETURN.
|
Routing - PLAN CHECK | 9/3/1997 | | 9/10/1997 | | |
|
|
|
PACKAGE #1
|
Routing - ELECTRICAL | 7/3/1997 | | 9/9/1997 | | PASS |
|
|
|
PACKAGE 31 FIELD VERIFY
|
Routing - FIRE | 8/18/1997 | | 9/2/1997 | | FAIL |
|
|
|
PACKAGE #1
|
Plan resubmittals received | | | 9/2/1997 | | |
|
|
|
Routed set out to structural for follow up review.
|
Routing - PLAN CHECK | 7/9/1997 | | 8/18/1997 | | |
|
|
|
PACKAGE #1
|
Plan Reviewer's activity | | | 8/15/1997 | | FAIL |
|
|
|
SENT CORRECTION REPORT TO ARCHITECT AND BRIGGS ENGINEERING.
|
Print Pending Permit.LaserJet4 | | | 8/15/1997 | | FAIL |
|
|
|
|
Plan Reviewer's activity | | | 7/24/1997 | | HOLD |
|
|
|
Requested an analysis of building per Dan Stuart's letter in file. This was agreed by Life Care Center's John Lytle back in 1995.
|
90 day tracking............. | | 4/23/1997 | 7/22/1997 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/30/1997 | | 7/22/1997 | | FAIL |
|
|
|
PACKAGE #3 CONTACTED PDQ TO TAKE PLANS OUT TO CH2MHILL WRITTEN RESPONSE AND FOLLOW-UP REVIEW REQUIRED BY OUTSIDE ENGINEERING FIRM.
|
Plan assigned to (RGG) | 6/30/1997 | | 7/22/1997 | | PASS |
|
|
|
RECEIVED DR/MOD ON6-9-97
|
Routing - PLAN CHECK | 7/14/1997 | | 7/19/1997 | | |
|
|
|
PACKAGE #2
|
Routing - PLANNING | 7/8/1997 | | 7/11/1997 | | PEND |
|
|
|
PACKAGE #2 These plans are in the review stage with planning. AA-56-97 Continue to route and send to planning last. Rerouted by: SAR
|
Routing - PUBLIC WORKS | 6/30/1997 | | 7/3/1997 | | PASS |
|
|
|
DACKAGE #2
|
Routing - PLUMBING | 6/30/1997 | | 7/2/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing - MECHANICAL | 6/30/1997 | | 6/30/1997 | | |
|
|
|
NO REVIEW FILD VERIFY PACKAGE #1
|
Plan routing begun/NEW & ADDTN | | | 6/30/1997 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 6/30/1997 | | PASS |
|
|
|
SEE ACTION007 HOLD
|
Plan assigned to (RGG) | 4/23/1997 | | 6/30/1997 | | HOLD |
|
|
|
NO CU OR DR.
|
Received Certificate of Value | | | 6/26/1997 | | PASS |
|
|
|
SEE ACTION A017
|
Plans ACCEPTED BY PLAN CHECK | | | 4/23/1997 | | HOLD |
|
|
|
PLANS ON HOLD UNTIL LIFE CARE CENTER OF BOISE RECEIVES A DR OR A MOD. CU ACCORDING TO P&Z. PACKAGE #2 NEEDS 2 SETS OF LANDSCAPE PLANS. CERT. OF VALUE NEEDS SEPARATE PLUMBING AND MECH VALUES INSTEAD OF A COMB. M/P VALUE. CONTACTED DEAN BRIGGS AT ###-#### OF THESE NEEDS. KMM HAVE NOT HEARD FROM DEAN AFTER TWO PHONE CALLS. FAXED A LETTER TO HIM ON 4-28-97 AND MAILED THE SAME LETTER STATING THE ABOVE MENTIONED ITEMS NEED TO BE TAKEN CARE OF BEFORE ROUTING CAN BEGIN. KMM 6-9-97 RECEIVED MOD/CU OF 74-96 FROM P&Z. STILL NEED NEW CERT. OF VALUE AND 2 LANDSCAPE PLANS. CALLED DEAN BRIGGS TO REMIND HIM OF THIS NEED.(VOICE MAIL) KMM 6-26-97 RECEIVED NEW CERT. OF VALUE CALLING OUT PLUMB. MECH. AND ELEC. KMM 6-30-97 RECEIVED TWO LANDSCAPE PLANS. PACKAGES READY TO ROUTE
|
Received Certificate of Value | | | 4/23/1997 | | HOLD |
|
|
|
NEEDS TO CALL OUT PLUMB. AND MECH. SEPARATELY RECEIVED NEW CERT. OF VALUE CALLING PLUMB. AND MECH. AND ELEC. KMM 6-26-97
|
Plan assigned to (MYS) | 4/23/1997 | | 4/23/1997 | | PEND |
Marlene Southard
|
|
|
|
Application received | | | 4/23/1997 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/23/1997 | | PASS |
|
|
|
|