INSP - Energy code compliance | 6/17/1997 | 6/18/1997 | 6/18/1997 | A | PASS |
Russ Owen
|
|
|
06/18/97 407 - MID A.M....
|
INSP - Framing/Rough-in | 6/17/1997 | 6/17/1997 | 6/17/1997 | P | PASS |
Russ Owen
|
|
|
06/17/97 407 -
|
INSP - Footings | 5/20/1997 | 5/20/1997 | 5/20/1997 | P | PART |
Russ Owen
|
|
|
05/20/97 407 - NEED THE 2 FRONT PORCH FOOTINGS FOR ROOF, ALSO MISSING A FRONT OF REAR POP OUT CONTRACTOR WILL POUR THESE AT TIME OF WALL POUR CH FRAMING INSP.
|
Issue PAID IN FULL permit | | | 5/7/1997 | | |
|
|
|
|
Plan assigned to (DJO) | 4/24/1997 | | 5/5/1997 | | PASS |
Dan Overy
|
|
|
05/05/97 08:50:45 DJO - this action updated by action script from <<>> in Case No. BLD97-1028
|
Inspection Record Card- Bld | | | 5/5/1997 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/5/1997 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/5/1997 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 5/5/1997 | | PASS |
|
|
|
|
Telephone call | | | 5/5/1997 | | |
|
|
|
TOLD CHUCK PERMIT READY
|
Routing - PLANNING | 4/25/1997 | | 4/30/1997 | | PASS |
|
|
|
Approved by: MH Driveway is ok---M. Hall, but side setback adjoining street is 20'.
|
Routing - PUBLIC WORKS | 4/24/1997 | | 4/25/1997 | | PASS |
|
|
|
|
Application received | | | 4/24/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 4/30/1997 | | | | PEND |
|
|
|
|