Permanent occupancy | | | 8/20/1997 | | PASS |
|
|
|
Perm. Occ. Cert. #6943 issued 8-20-97 to Columbia Village Elementary School for a relocatable classroom.
|
Permanent Occupancy | | 8/15/1997 | 8/15/1997 | | DONE |
|
|
|
|
INSP - Final | 8/13/1997 | 8/14/1997 | 8/14/1997 | A | PASS |
Russ Owen
|
|
|
08/14/97 407 - CALL CEL ###-#### RICK AND HE WILL MEET YOU
|
INSP - Final | 8/6/1997 | 8/6/1997 | 8/6/1997 | | PART |
Russ Owen
|
|
|
/ / 407 - temporay the plumbing inspector has a correction for a valve
|
Temporary occupancy | | | 8/6/1997 | | PASS |
|
|
|
Temp. Occ. Cert. #3438 issued 8-6-97 to Trail Wind Elementary School for a relocatable classroom bldg.
|
INSP - Final | 8/11/1997 | | 8/6/1997 | | PART |
|
|
|
plumbing inspector corrections a valve.
|
INSP - Final | 8/4/1997 | 8/5/1997 | 8/5/1997 | P | FAIL |
Russ Owen
|
|
|
08/05/97 407 - doors need to be adjusted to open with-out force.
|
INSP - Final | 8/1/1997 | 8/4/1997 | 8/4/1997 | A | NR |
Russ Owen
|
|
|
08/04/97 407 - RE-INSPECT left correction.
|
INSP - Final | 8/1/1997 | 8/1/1997 | 8/1/1997 | P | NR |
Russ Owen
|
|
|
08/01/97 407 -
|
Receive PAYMENT IN FULL PRINT | | | 8/1/1997 | | |
|
|
|
|
INSP-Final Inspection | 7/30/1997 | 7/30/1997 | 7/30/1997 | P | PASS |
|
|
|
|
90 day tracking............. | | 5/1/1997 | 7/30/1997 | | |
|
|
|
|
INSP-Final Inspection | 7/24/1997 | 7/28/1997 | 7/28/1997 | A | NR |
|
|
|
NOT COMPLETE
|
INSP - Final | 7/28/1997 | 7/28/1997 | 7/28/1997 | P | NR |
Jim Storey
|
|
|
07/28/97 301 - n/r call from flyod.
|
INSP - Final | 7/24/1997 | 7/25/1997 | 7/25/1997 | P | NR |
Jim Storey
|
|
|
07/25/97 301 - ready at 3 floyd fire dept going out p.m. also. maybe you what time. reisp. fee no acess.
|
INSP-Final Inspection | 7/24/1997 | 7/25/1997 | 7/25/1997 | A | NR |
|
|
|
ready at 2 o'clock
|
INSP - Final | 7/23/1997 | 7/24/1997 | 7/25/1997 | P | NR |
Jim Storey
|
|
|
07/24/97 301 - UGA -UNABLE TO GAIN ACCESS-LEFT NOTC
|
CHANGE STATUS TO (F) | | | 7/25/1997 | | |
|
|
|
as per jim storey reinspection fee due
|
(F) Reprint permit | | | 7/25/1997 | | |
|
|
|
as per jim storey
|
INSP-Final Inspection | 7/23/1997 | 7/24/1997 | 7/24/1997 | A | FAIL |
|
|
|
alarms not complete
|
Issue PAID IN FULL permit | | | 6/26/1997 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/25/1997 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 6/25/1997 | | |
|
|
|
|
Print Occupancy Form | | | 6/25/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/23/1997 | | PASS |
|
|
|
|
Routing - FIRE | 6/17/1997 | | 6/19/1997 | | PASS |
|
|
|
|
Routing - PLUMBING | 6/12/1997 | | 6/13/1997 | | PASS |
|
|
|
|
Plan assigned to (RGG) | 5/2/1997 | | 6/11/1997 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/2/1997 | | 6/10/1997 | | PASS |
|
|
|
|
Routing - PLANNING | 5/19/1997 | | 5/28/1997 | | PASS |
|
|
|
X-REF: ZONING CERTIFICATE @ 3701 LAKE FOREST. APPROVED BY MH.
|
Routing - PUBLIC WORKS | 5/8/1997 | | 5/16/1997 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN. BM
|
Routing Off Site - A.C.H.D | 5/2/1997 | | 5/7/1997 | | PASS |
|
|
|
CONTACTED DON HUTCHISON AT ###-#### TO TAKE PLANS OUT TO ACHD. NO ACHD FEES DUE.
|
Plan routing begun/NEW & ADDTN | | | 5/2/1997 | | PASS |
|
|
|
|
Received Certificate of Value | | | 5/2/1997 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 5/2/1997 | | PASS |
|
|
|
|
Application received | | | 5/2/1997 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 5/1/1997 | | 5/2/1997 | | PEND |
Marlene Southard
|
|
|
|
Application received | | | 5/1/1997 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/1/1997 | | |
|
|
|
|