Permanent occupancy | | | 12/21/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7564 issued 12-21-98 to the Women's Center.
|
Permanent Occupancy | | 12/3/1998 | 12/3/1998 | | DONE |
|
|
|
|
INSP - Final | 11/16/1998 | 11/16/1998 | 11/16/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
INSP - Final | 10/29/1998 | 10/29/1998 | 10/29/1998 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - REINSP FAIL ALARM PACKAGE AND MISC ITEMS
|
INSP - Framing/Rough-in | 2/6/1998 | 2/6/1998 | 2/9/1998 | P | PART |
|
|
|
02/06/98 338 - READY AT 1:00--RON PAGER ###-####c/n issued need to reswi soiled linen room per ubc 10 only 21 " clear with door in open position blocking corridor at the 90 degree pos.
|
INSP - Final | 1/30/1998 | 1/30/1998 | 1/31/1998 | P | PART |
|
|
|
01/30/98 338 - ron ###-#### pager ok for temp occ. f/x cabinets need to temp occ cert.
|
INSP-Final Inspection | 1/29/1998 | 1/30/1998 | 1/30/1998 | A | FAIL |
Joe Tawney
|
|
|
01/30/98 406 - 8:30 am prescheduled with Joe ron pager ###-#### FINAL FAIL FIRE EXT DOORS ALARM RESUBMITTAL
|
INSP - Final | 1/30/1998 | 1/30/1998 | 1/30/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP FOR FINAL OK FOR TEMP 0CC
|
Temporary occupancy | | | 1/30/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3546 issued 1-30-98 to St. Al's Women's Center.
|
INSP - Framing/Rough-in | 1/20/1998 | 1/20/1998 | 1/21/1998 | P | PART |
|
|
|
01/21/98 338 - FIRE WALLS 1ST FLOOR \\RON ###-#### VOICE PAGER part made corrections will check at the final
|
INSP - Framing/Rough-in | 1/6/1998 | 1/7/1998 | 1/7/1998 | A | PART |
|
|
|
01/07/98 338 - south most section 1st floor ok to drop in tiles
|
INSP - Framing/Rough-in | 1/5/1998 | 1/5/1998 | 1/5/1998 | P | NR |
|
|
|
01/05/98 338 - CEILING--OFFICE #5 \ not ready contractor will recall when so
|
INSP - Framing/Rough-in | 11/26/1997 | 11/26/1997 | 12/1/1997 | P | PASS |
|
|
|
12/01/97 338 - pass
|
(F) Reprint permit | | | 8/8/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/8/1997 | | |
|
|
|
|
Telephone call | | | 8/7/1997 | | |
|
|
|
CALLED PERMIT READY
|
Inspection Record Card- Bld | | | 8/7/1997 | | |
|
|
|
|
Print Occupancy Form | | | 8/7/1997 | | |
|
|
|
|
Print permit w/o conditions | | | 8/7/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 8/7/1997 | | PASS |
|
|
|
Drawings approved after 2nd resubmittal review.
|
testing condition printout | | | 8/7/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/1997 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 5/8/1997 | | 8/7/1997 | | PASS |
Carl Westfall
|
|
|
Carl: Preliminary plan review performed by Dan Stuart. Take direction from Dan. 08/07/97 11:18:06 CJW - this action updated by action script from <<>> in Case No. BLD97-1212
|
Plan resubmittals received | | | 8/6/1997 | | |
|
|
|
|
Plan resubmittals requested | | | 7/16/1997 | | |
|
|
|
Faxed the architect a list of items still not resolved. See conditions list.
|
Plan Reviewer's activity | | | 7/16/1997 | | |
|
|
|
Drawings NOT approved after resubmittal review. Some items still unresolved. See conditions list.
|
Routing - FIRE | 7/10/1997 | | 7/15/1997 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 6/30/1997 | | 7/10/1997 | | PEND |
|
|
|
|
Plan resubmittals received | | | 7/3/1997 | | |
|
|
|
|
Routing - PLUMBING | 6/23/1997 | | 6/25/1997 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 6/13/1997 | | 6/18/1997 | | PASS |
|
|
|
NO IMPACT FEES DUE ACHD.
|
Plan resubmittals requested | | | 6/13/1997 | | |
|
|
|
Sent plan check report (conditions list) to the architect and requested resubmittals correcting problems.
|
Plan Reviewer's activity | | | 6/13/1997 | | |
|
|
|
UBC plan check started June 11, 1997 and finished June 13, 1997. Response from the architect is required. See conditions list.
|
Routing - PLAN CHECK | 5/12/1997 | | 6/13/1997 | | |
|
|
|
|
Routing - PUBLIC WORKS | 5/9/1997 | | 5/12/1997 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 5/8/1997 | | |
|
|
|
Route to PUBLIC WORKS then back to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT.
|
Application received | | | 5/7/1997 | | |
|
|
|
|