Description
To remodel an existing 2,318 sq.ft. restaurant, with support mezzanine area, for new tenant per approved plans on file. Work to include new noncombustible frame wall between dining and kitchen/service area and new kithchen/service area cabinets & fixtures. A new Ventmaster Ductless Hood System will be install in the kitchen for removal of grease laden vapors. New make up air directly into kitchen area equal to a minimum of 1600 CFM is required. NOTE: This building is fully fire sprinklered. Separate electrical, plumbing & mechanical permits are required. (P.C.#287-97)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 9/23/19979/23/1997 DONE
Details
Permanent occupancy  9/23/1997 PASS
Perm. Occ. Cert. #7000 issued 9-23-97 to the River City Grille.
INSP - Final9/18/19979/19/19979/19/1997APASS
Details
09/18/97 453 -
INSP - Final9/18/19979/18/19979/18/1997PPART
DetailsWes Worcester
going to City for Assembly Permit
INSP-Final Inspection9/17/19979/18/19979/18/1997APASS
DetailsRick Jackson
passed...
INSP - Final9/17/19979/17/19979/17/1997PFAIL
DetailsWes Worcester
09/17/97 342 - need to comply w/Fire Insp notice of 9/15/97...Install pa fire caulk upstairs. Reinspection for fire not called yet.
INSP - Conference9/15/19979/15/19979/15/1997 PASS
DetailsWes Worcester
/ / 342 - called plan ck and talked to Dan S @ panic haedware....tenan
INSP - Final9/12/19979/15/19979/15/1997ANR
DetailsWes Worcester
09/15/97 342 - need fire, mech, panic hardware, firecaulk, occupant ld
INSP-Final Inspection9/12/19979/15/19979/15/1997AFAIL
DetailsRick Jackson
c/n issued.
INSP - Conference9/8/19979/8/19979/8/1997PPASS
Details
09/08/97 333 - he said your meeting was set for 11 a.m. today????? met about makeup air ok to damper
90 day tracking............. 5/20/19978/18/1997
Print Occupancy Form  7/9/1997
Inspection Record Card- Bld  7/9/1997
Issue PAID IN FULL permit  7/9/1997
Plan assigned to (DRS)5/23/1997 7/8/1997 PASS
DetailsDan Stuart
07/08/97 12:05:52 DRS - this action updated by action script from <<>> in Case No. BLD97-1378
PLANS/APPL TAKEN TO FRONT DESK  7/8/1997 PASS
Routing - PLAN CHECK7/8/1997 7/8/1997 PASS
Received all information requested or made notes on plans. Ready to process for issuance of permit.
Routing - PLUMBING7/7/1997 7/7/1997 PASS
Plan resubmittals received  7/7/1997 PASS
Received response to plan review comments from architect. Plans were rerouted to plumbing division for review and approval of prior outstanding items.
Routing - PLAN CHECK6/27/1997 7/4/1997 PEND
Routed to plumbing for review of requested correction and sign off approval.
Plan resubmittals received  7/3/1997
Received mechanical plans from mechanical engineer but no response from architect Tom Stonehocker concerning the plan review comments and clearing up plumbing dept. rejection of plans. I called and left messages with Tom Stonehocker's answering service as well as Cindy's, new tenant inan effort to see if I could process permit for issuance today. Does not look like it.
Routing - FIRE6/26/1997 6/27/1997 PASS
Print Pending Permit.LaserJet4  6/26/1997 PASS
Plan resubmittals requested  6/25/1997 PASS
Formal letter of request to architect for plans showing mechanical system make-up air for hood & protection of openings through occupancy separation wall. This matter had been discussed before with the architect, Larry Hoff; Eddie Valenzuela, part owner; and Don Hiatt. Mr. Hoff was to have met with me on 06/24/97 with his mechanical contractor at 2p.m. but did not show up. 07/07/97- Received response from architect to plan review comments. Received mechanical make-up air plan on 07/03/97.
Routing - PLAN CHECK6/25/1997 6/25/1997
Routing to fire dept. Waiting for mechanical plan design for installation of make up air system for new VentMaster Ductless Hood.
Routing - PLAN CHECK6/11/1997 6/25/1997 PEND
Picked up plan for preliminary review.
Routing - PLUMBING6/6/1967 6/11/1997 FAIL
Routing - PUBLIC WORKS5/29/1997 6/5/1997 PASS
Routing Off Site - C.D.H5/23/1997 5/29/1997
CONTACTED LARRY HOFF AT ###-#### TO TAKE PLANS OUT TO CDH
Plan routing begun/TENANTS  5/23/1997
Route to CENTRAL DISTRICT HEALTH, PUBLIC WORKS, PLUMBING then back to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT.
Plan assigned to (MYS)5/20/1997 5/23/1997
DetailsMarlene Southard
Recd Pcfee & Taken To Pln CK  5/20/1997
Application received  5/20/1997
Plan Reviewer's activity  4/25/1997
Began phone conversations with Don Haitt, Bargreen/Ellingson food service supply & design, concerning the use of a ductless hood system. The Vent Master system proposed is not listed by ICBO. We found a Giles system which is listed and Mr. Hiatt went to see if this system would work. Over the next several weeks phone conversations and a visit by Jeff Schulz for VentMaster resulted in submittals of proprietory information for VentMaster and phone conversations with UL, review of NFPA 96, a copy of the UL File report and an on site visit & report from Jeff Schultz concerning requirements needing to be met by the restaurant personel if a VentMaster system was to be used, I reviewed all materials with Bob Garrison, Chief Plans Examiner Manager & Dave Miller, Fire Dept. Battalion Chief & Plan Reviewer and it was agreed that we would accept the product if installed per listing, Jeff Schulz' report and NFPA 96. A letter of conditional acceptance was sent to Don Hiatt, with copies to Bob Garrison, Dave Miller & Floyd Varley, Fire dept. field inspector. Copy on plans & in file.