Information based on query as of Friday, July 19, 2024.
Permit Information
Permit NumberBLD97-01387
StatusFinaled
Name STREET LEVEL HOTEL LOBBY & BAR
Site Address 245 S CAPITOL BLVD
Project NameGROVE HOTEL
Customer Number 
ePlanReviewNo
Description
(STREET LEVEL HOTEL LOBBY & BAR) Fire sprinklers used to meet high-rise requirements. To finish the street level hotel lobby, bar area, front desk office, storage rooms, and restrooms (6,677 sq. ft.) in the East portion of the building. Work is to include interior nonbearing walls, 2 restrooms accessible to the disabled, interior doors, and suspended ceilings all per approved drawings and plan check conditions on file. The maximum occupant load of the hotel lobby and bar (284) shall be posted on an approved sign near the main exit. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. PC-184-97 **CJW**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
(F) Reprint permit  8/4/1998 PASS
INSP - Final7/16/19987/16/19987/16/1998APASS
Details
07/16/98 333 - FNL -OK FINAL
INSP - Final7/16/19987/16/19987/16/1998APASS
Details
07/16/98 333 - FNL -OK FINAL
Permanent Occupancy 7/15/19987/15/1998 DONE
Details
Permanent occupancy  7/15/1998 PASS
Perm. Occ. Cert. #7316 issued 7-15-98 to the Westcoast Hotel Bar.
INSP - Final7/7/19987/7/19987/7/1998 PART
Details
/ / 333 - PROFIT MEETING
INSP-Final Inspection6/18/19986/18/19986/18/1998PPASS
DetailsRick Jackson
occ approved
INSP - Final6/16/19986/16/19986/16/1998 FAIL
Details
/ / 333 - CN PLACED TEMP EXPIRED
INSP - Final6/11/19986/11/19986/11/1998AFAIL
Details
06/11/98 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Final3/26/19983/26/19983/26/1998 PART
Details
/ / 333 - profit meeting
Temporary occupancy  1/8/1998 PASS
Temp. Occ. Cert. #3531 issued 1-8-98 to the Westcoast Hotel for the lobby, bar area & front desk ofc.
INSP - Final1/6/19981/6/19981/6/1998 PART
Details
/ / 333 -
INSP - Final12/31/199712/31/199712/31/1997APART
Details
12/31/97 333 - temp ok
INSP - Final12/30/199712/30/199712/30/1997PFAIL
Details
12/30/97 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Final12/29/199712/29/199712/29/1997PFAIL
Details
12/29/97 333 - cn not made
INSP - Wall cover12/17/199712/17/199712/17/1997 FAIL
Details
/ / 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in12/2/199712/2/199712/2/1997 PASS
Details
/ / 333 -
INSP - Framing/Rough-in11/25/199711/25/199711/25/1997APART
Details
11/25/97 333 - ceiling ok
INSP - Framing/Rough-in10/30/199710/30/199710/30/1997APART
Details
10/30/97 333 - part
INSP - Framing/Rough-in10/29/199710/29/199710/29/1997 PART
Details
/ / 333 - discussed firepalce
INSP - Conference10/1/199710/1/199710/1/1997PFAIL
Details
cn
Issue PAID IN FULL permit  8/28/1997
Print Occupancy Form  8/28/1997
Inspection Record Card- Bld  8/28/1997
PLANS/APPL TAKEN TO FRONT DESK  8/28/1997 PASS
Routing - FIRE7/30/1997 8/26/1997 PASS
testing condition printout  7/29/1997
Print permit w/o conditions  7/29/1997
Plan Reviewer's activity  7/21/1997 PASS
Drawing approved per attached conditions.
Plan Reviewer's activity  5/19/1997
UBC plan check started May 19, 1997 and finished July 21, 1997. Plan check delayed at applicant's request in order to expedite arena permits. See BLD97-0870 for more information.
Application received  4/10/1997
Routing - PLAN CHECK8/27/1997