Permit NumberBLD97-01398
StatusFinaled
Name GRACE BIBLE CHURCH OF BOI SE
Site Address 4262 N EAGLE RD
Project NameCHURCH (OFFICE)
Customer Number 
ePlanReviewNo
Description
(GRACE BIBLE CHURCH OF BOISE)(NEW OFFICE) TO CONSTRUCT A 2,400 SQ. FT. OFFICE BUILDING WITH A 2,400 SQ. FT. UNFINISHED BASEMENT. CONSTRUCTON TO BE ALL WOOD FRAME, CONCRETE FOUNDATION AND BASEMENT FLOOR, TRUSS ROOF SYSTEM, BRICK VENEER, SHEET ROCKED INTERIOR. ALL PER APPROVEED PLANS ON FILE. THIS PERMIT INCLUDES PARKING LOT AND LANDSCAPING. CU-15-97 PC#304-97
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent occupancy  5/28/1998 PASS
Perm. Occ. Cert. #7261 issued 5-28-98 to Grace Bible Church Office.
INSP - Final5/26/19985/27/19985/27/1998APASS
DetailsJim Sly
05/27/98 316 - OK for Perm Occ. pending all req signatures...........cod off. ###-#### kevin/call if you dont need to go out.
Permanent Occupancy 5/27/19985/27/1998 DONE
Details
Code Occupancy Approval  5/21/1998 PASS
Inspection 1/09/98 -Bond required. Posted Bond on 1/12/98 for undergrd. sprklr/landscaping/prkg. lot stripping - $8,438.00 - Signed Temporary Occupancy (1-12-98) Inspected for Final (5/21/98) - Complies w/ DR - Pass. (CAM).
Permanent occupancy  5/21/1998 PEND
AM PLEASE
INSP - Final5/19/19985/20/19985/20/1998AFAIL
DetailsJim Sly
05/20/98 316 - C/N....Need code enforcement sign off....
INSP-Sprinkler Rough-in/Hydro1/20/19981/21/19981/21/1998APASS
DetailsJoe Tawney
OK FOR PERM OCC
INSP - Final1/9/19981/12/19981/12/1998PPART
DetailsJim Sly
01/12/98 316 - Temp Occ OK
INSP-Final Inspection1/9/19981/12/19981/12/1998AFAIL
DetailsJoe Tawney
01/12/98 406 - ###-#### Ben Rank REINSP FOR FINAL FAIL FIRE DEPT ACCESS SIGNS EMERG LIGHTS SMOKE SEAL
Temporary occupancy  1/12/1998 PASS
Temp. Occ. Cert. #3533 issued 1-12-98 to Grace Bible Church (ofc. bldg.)
INSP - Final1/8/19981/9/19981/9/1998PNR
DetailsJim Sly
01/09/98 316 - Builder cancelled.....
INSP-Final Inspection1/8/19981/9/19981/9/1998AFAIL
DetailsJoe Tawney
01/09/98 406 - FINAL FAIL EXIT DOORS DR HDWRE BLDG ADDRESS EMERG LIGHTS
INSP-Sprinkler Rough-in/Hydro1/5/19981/5/19981/5/1998 PASS
DetailsJoe Tawney
/ / 406 - OK ON HYDRO TEST OF BASEMENT SPKLR SYSTEM AND UNDERGROUND
INSP-Final Inspection12/29/199712/30/199712/31/1997PFAIL
DetailsJoe Tawney
12/30/97 406 - HYDRO TEST FAIL DOUBLE CHECK LEAKED WILL RESCHEDULE
INSP - Framing/Rough-in12/23/199712/23/199712/23/1997PPASS
DetailsJim Sly
12/23/97 316 - Ceiling Grid OK
INSP - Framing/Rough-in11/25/199711/26/199711/26/1997PPASS
DetailsJim Sly
11/26/97 316 -
INSP - Energy code compliance11/25/199711/26/199711/26/1997PPASS
DetailsJim Sly
11/26/97 316 -
INSP - Framing/Rough-in11/21/199711/25/199711/25/1997PFAIL
DetailsJim Sly
11/24/97 316 - C/N..Misc truss corrections, need sprinkler rough in...
INSP-Final Inspection11/17/199711/17/199711/17/1997PPART
DetailsJoe Tawney
11/17/97 406 - MIKE ###-#### OK ON UNDERGROUND FLUSH ì
INSP - Wall cover10/16/199710/17/199710/17/1997APASS
DetailsTom Arcoraci
10/17/97 408 - SHEER WALL NAILING
INSP - Footings10/8/199710/9/199710/9/1997APASS
DetailsJim Sly
10/08/97 316 - Footings on ext of bldg for stairs, ramps...
INSP - Masonry10/2/199710/2/199710/2/1997 PASS
DetailsJim Sly
/ / 316 - Grout pour at steel columns...OK
INSP - Footings9/3/19979/4/19979/4/1997APASS
DetailsJim Sly
09/03/97 316 - OK
INSP - Footings9/2/19979/3/19979/3/1997AFAIL
DetailsJim Sly
/ / 316 - C/N....Need special inspection for rebar and concrete...
(F) Reprint permit  8/25/1997
90 day tracking............. 5/21/19978/19/1997 PEND
(F) Reprint permit  8/18/1997
Issue PAID IN FULL permit  8/18/1997
Print Occupancy Form  8/11/1997
Inspection Record Card- Bld  8/11/1997
PLANS/APPL TAKEN TO FRONT DESK  8/11/1997 PASS
Telephone call  8/11/1997
CALLED BEN RENK CONST--PERMIT READY
Print Pending Permit.LaserJet4  8/11/1997 PASS
Routing - PUBLIC WORKS7/31/1997 8/1/1997 PASS
Routing - PLAN CHECK7/28/1997 7/31/1997
Routing - FIRE7/23/1997 7/25/1997 FAIL
Routing - PLAN CHECK7/21/1997 7/23/1997
Routing - MECHANICAL7/22/1997 7/22/1997 PASS
Plan assigned to (RGG)5/28/1997 7/22/1997 PASS
Routing - PUBLIC WORKS7/8/1997 7/21/1997 FAIL
NEEDS DRAINAGE PLAN REVISION.
Routing - PLANNING6/24/1997 7/7/1997
Approved by: RLB
Routing - PLUMBING6/17/1997 6/23/1997 PASS
Routing - ELECTRICAL6/13/1997 6/16/1997 PASS
Routing Off Site - A.C.H.D5/28/1997 6/13/1997 PEND
CONTACTED KEVIN HOUGH AT ###-#### TO TAKE PLANS OUT TO ACHD ACHD FEES NOT PAID.
Plan routing begun/NEW & ADDTN  5/28/1997
Plan assigned to (MYS)5/21/1997 5/28/1997
DetailsMarlene Southard
Plans ACCEPTED BY PLAN CHECK  5/28/1997 PASS
Received Certificate of Value  5/28/1997 PASS
Recd Pcfee & Taken To Pln CK  5/21/1997
Application received  5/21/1997
Routing - FIRE8/1/1997 8/4/1996 PASS
Routing - PLAN CHECK8/1/1997