Permit Information
Permit NumberBLD97-01430
StatusFinaled
Name QUILTED BEAR CRAFT MALL
Site Address 3255 N COLE
Project NameCOLE VILLAGE
Customer Number 
ePlanReviewNo
Description
To finish a 19,154 sq.ft. tenant space for retail craft sales and storage per approved plans on file. Work to include construction of one-hour rated corridor, accessible ramp, and approximately 150 lf of one-hour rated tenat demising wall. Two accessible restrooms. Installation of suspended ceiling. And the construction of a 580 sq ft. enclosure for display area. Interior retail area to have partial height partitions not to exceed 5'6" in height not requiring a permit. This space is divided from tenant on north side by a 2-hr. existing area separation wall. NOTE: This building is fully fire sprinklered. Any relocation of sprinkler heads shall comply with NFPA #13 (P.C.#300-97)RMH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 9/23/19979/23/1997 DONE
Details
INSP - Final9/22/19979/23/19979/23/1997APASS
DetailsJim Sly
09/22/97 316 - C/N Removed...PASS
Permanent occupancy  9/23/1997 PASS
Perm. Occ. Cert. #6996 issued 9-23-97 to the Quilted Bear Craft Mall in the Cole Village.
INSP - Final9/18/19979/19/19979/19/1997ANR
DetailsJim Sly
09/18/97 316 - QUILTED BEAR Contractor Cancelled.
INSP - Final9/11/19979/12/19979/12/1997ANR
DetailsJim Sly
09/11/97 316 - Contractor cancelled...
INSP-Final Inspection9/8/19979/10/19979/10/1997APASS
DetailsJoe Tawney
09/10/97 406 - reinspection REINSP FOR FINAL OK FOR PERM OCC
INSP - Final9/8/19979/10/19979/10/1997PFAIL
DetailsJim Sly
09/09/97 316 - C/N..Complete tenant dem wall, Tempered glass doors,.....
INSP-Final Inspection9/4/19979/5/19979/5/1997AFAIL
DetailsJoe Tawney
09/05/97 406 - REINSP FOR FINAL FAIL OPENING IN TEN DEM WALL LETTER ON SEAL
INSP-Final Inspection9/2/19979/3/19979/3/1997ANR
DetailsJoe Tawney
09/03/97 406 - NOT READY FOR REINSP
INSP - Final9/2/19979/3/19979/3/1997PNR
DetailsJim Sly
09/02/97 316 - Builder cancelled...
INSP - Final8/21/19978/22/19978/22/1997ANR
DetailsJim Sly
08/21/97 316 - Need all signatures from req. agencies..Scheduled by Hell 14:00:43.
INSP-Final Inspection8/21/19978/21/19978/21/1997 FAIL
DetailsJoe Tawney
08/21/97 406 - late p.m. other trades being done early p.m. FINAL FAIL LONG LIST MEANT TO SCHED ME TOMORROW
90 day tracking............. 5/23/19978/21/1997 PEND
INSP - Ceiling grid8/15/19978/15/19978/15/1997APASS
DetailsTom Arcoraci
INSP - Ceiling grid8/13/19978/14/19978/14/1997PPART
DetailsTom Arcoraci
RE-INSPECTION
INSP - Ceiling grid8/8/19978/8/19978/8/1997PPART
DetailsTom Arcoraci
needs wires on fixtures then ok
INSP - Ceiling grid8/7/19978/8/19978/8/1997ACANC
DetailsJim Sly
08/08/97 316 - Gave to Tom A.
INSP - Framing/Rough-in7/22/19977/23/19977/23/1997APART
DetailsWes Worcester
you said you would stop at 7:40a.m. kind of early bird aren't you
INSP - Framing/Rough-in7/21/19977/22/19977/22/1997ACANC
DetailsJim Sly
07/22/97 316 - Gave to Wes W.
INSP - Framing/Rough-in7/22/19977/22/19977/22/1997ACANC
DetailsJim Sly
GIVEN TO WES #342
INSP - Framing/Rough-in7/22/19977/22/19977/22/1997PNR
DetailsWes Worcester
no one there
Telephone call  7/10/1997 PASS
CALLED MIKE AND HE WILL BE IN RIGHT AWAY
Print Occupancy Form  7/10/1997
Issue PAID IN FULL permit  7/10/1997
Inspection Record Card- Bld  7/10/1997
Plan assigned to (R_H)5/29/1997 7/9/1997 PASS
Details
See conditions list for items requiring a response. 07/09/97 14:48:43 R_H - this action updated by action script from <<>> in Case No. BLD97-1430
Routing - PLAN CHECK6/3/1997 7/9/1997 PASS
Print Pending Permit.LaserJet4  7/9/1997
Plan Reviewer's activity  7/9/1997 PASS
Received corrections and final certificate of value. Ready to issue.
PLANS/APPL TAKEN TO FRONT DESK  7/9/1997 PASS
Routing - FIRE6/20/1997 7/7/1997
Plan Reviewer's activity  7/1/1997
Received resubmittals from architect. Waiting for plans from fire department.
Plan Reviewer's activity  6/19/1997 FAIL
Requested more information from architect.
Routing - PUBLIC WORKS5/29/1997 6/3/1997 PASS
Plan routing begun/TENANTS  5/29/1997
Route to PUBLIC WORKS then back to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT.
Plan assigned to (MYS)5/23/1997 5/29/1997
DetailsMarlene Southard
Recd Pcfee & Taken To Pln CK  5/23/1997
Application received  5/23/1997