Case Summary (BLD) | | | 11/10/2008 | | |
|
|
|
|
Case Summary (BLD) | | | 7/12/2007 | | |
|
|
|
|
Permanent occupancy | | | 6/5/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7267 issued 6-5-98 to the First Presbyterian Church.
|
INSP - Final | 6/4/1998 | 6/4/1998 | 6/4/1998 | P | PASS |
|
|
|
06/05/98 333 - FNL -OK FINAL
|
Permanent Occupancy | | 6/4/1998 | 6/4/1998 | | DONE |
|
|
|
|
INSP-Final Inspection | 5/26/1998 | 5/27/1998 | 5/27/1998 | A | PASS |
Rick Jackson
|
|
|
###-#### occ approved per approved plans
|
Code Occupancy Approval | | | 5/27/1998 | | PASS |
|
|
|
Trees and sod replaced per P&Z ltr. Final ok.
|
Code Occupancy Approval | | | 4/15/1998 | | TEMP |
|
|
|
Signed Temp on 4/10/98. No land scape requirements in coditions. Small amount of grass and couple small trees to be added by church.
|
INSP - Final | 4/10/1998 | 4/10/1998 | 4/10/1998 | | PART |
|
|
|
04/10/98 333 - card signed for temp cn placed
|
INSP - Framing/Rough-in | 4/7/1998 | 4/10/1998 | 4/10/1998 | P | PASS |
|
|
|
temp ok cn placed
|
INSP - Final | 4/9/1998 | 4/10/1998 | 4/10/1998 | P | PART |
|
|
|
temp ok cn placed
|
Temporary occupancy | | | 4/10/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3589 issued 4-10-98 to First Presbyterian Church on their addn.
|
INSP - Framing/Rough-in | 4/7/1998 | 4/8/1998 | 4/8/1998 | A | PART |
|
|
|
not ready
|
INSP - Framing/Rough-in | 4/8/1998 | 4/8/1998 | 4/8/1998 | | PASS |
|
|
|
04/08/98 333 - conference on temp occ
|
INSP-Sprinkler Rough-in/Hydro | 4/1/1998 | 4/1/1998 | 4/1/1998 | A | PASS |
Rick Jackson
|
|
|
completed attic area. old portion of building complete.
|
INSP-Sprinkler Rough-in/Hydro | 3/26/1998 | 3/27/1998 | 3/27/1998 | A | FAIL |
Rick Jackson
|
|
|
9:00 ###-#### attic area not covered.
|
INSP-Sprinkler Rough-in/Hydro | 3/10/1998 | 3/11/1998 | 3/11/1998 | P | PART |
|
|
|
michael ###-#### hydro passed, need to install sprinkler in soffit, north end of west area.
|
INSP - Miscellaneous | 11/19/1997 | 11/19/1997 | 11/19/1997 | P | FAIL |
|
|
|
11/19/97 333 - ceeptage beb dont do pits
|
INSP - Wall cover | 11/17/1997 | 11/18/1997 | 11/18/1997 | A | FAIL |
Wes Worcester
|
|
|
11/18/97 342 - FIRE WALL IN ROOM 250 fire wall not to plan, not to specs looked at first layer of two hour assembly's...detail and resubmittal re
|
INSP - Carpentry | 11/18/1997 | 11/18/1997 | 11/18/1997 | P | PASS |
|
|
|
11/18/97 333 - FIRE WALLS ok ì
|
INSP - Wall cover | 11/4/1997 | 11/5/1997 | 11/5/1997 | A | PART |
|
|
|
11/05/97 333 - FIRE WALL IN ATTIC..
|
Issue PAID IN FULL permit | | | 10/16/1997 | | |
|
|
|
|
testing condition printout | | | 10/10/1997 | | |
|
|
|
|
Print permit w/o conditions | | | 10/10/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 10/10/1997 | | PASS |
|
|
|
Drawings approved after second review by the consultant engineer.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/1997 | | PASS |
|
|
|
|
Print Occupancy Form | | | 10/10/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/10/1997 | | |
|
|
|
|
Telephone call | | | 10/10/1997 | | |
|
|
|
called talked to someone at 1st prebsyterian church will let paul no.mps
|
Plan assigned to (CJW) | 6/13/1997 | | 10/10/1997 | | PASS |
Carl Westfall
|
|
|
10/10/97 13:49:08 CJW - this action updated by action script from <<>> in Case No. BLD97-1561
|
Routing Off Site - STRUCTURAL | 10/2/1997 | | 10/9/1997 | | PASS |
|
|
|
Second review done by consultant engineer. Drawings approved.
|
Plan resubmittals received | | | 10/2/1997 | | |
|
|
|
Received response from the Engineer of Record. Gave a copy to Dave Radford to send to the consultant engineer.
|
Meeting | | | 9/22/1997 | | |
|
|
|
Had a meeting with the Engineer of Record. The architect and the consultant engineers (Keith Jones and Bill Cook) were present. The Engineer of Record will comply with the consultant engineers requests.
|
Telephone call | | | 9/16/1997 | | |
|
|
|
Called Paul Hoffman. Told him the status of the permit. He ask if he could get a demolition permit. He was told that if he filled out an application for a demo permit we would have a demo permit ready within 24 hours.
|
Telephone call | | | 9/16/1997 | | |
|
|
|
Called Libby Hill (architect). Told her the status of the permit. Three items on the Engineer's response are not complete (7, 8, & 10). Otherwise, the drawings are in order.
|
Plan Reviewer's activity | | | 9/12/1997 | | |
|
|
|
Resubmittal review completed. Approval from consultant engineer is pending. Copy of engineer's response faxed to the consultant.
|
Routing - FIRE | 8/24/1997 | | 9/11/1997 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/4/1997 | | |
|
|
|
|
90 day tracking............. | | 6/4/1997 | 9/2/1997 | | PEND |
|
|
|
|
Routing - PUBLIC WORKS | 8/19/1997 | | 8/22/1997 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/8/1997 | | 8/19/1997 | | |
|
|
|
Drawings reviewed the first time and meeting held with architects to go over the plan check report.
|
Meeting | | | 8/19/1997 | | |
|
|
|
Met with the Architect (Libby Hill) and went through each item on the plan check report (conditions list). Personally gave her a copy of that report.
|
Plan Reviewer's activity | | | 8/8/1997 | | |
|
|
|
UBC plan check started Aug. 8, 1997 and finished Aug. 18, 1997. Resubmittals required. See conditions list.
|
Routing - PLUMBING | 8/1/1997 | | 8/7/1997 | | PASS |
|
|
|
|
Routing - PLANNING | 7/24/1997 | | 8/1/1997 | | PASS |
|
|
|
X-REF: AA-76-96 & DR-94-96. APPROVED BY RLB & MGS.
|
Routing - PUBLIC WORKS | 7/14/1997 | | 7/21/1997 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN REVISION. PER BM
|
Routing Off Site - A.C.H.D | 6/18/1997 | | 7/11/1997 | | PASS |
|
|
|
CALLED PAUL HOFFMAN TO TAKE PLANS TO ACHD. ACHD FEES PAID. COPY OF RECEIPT ATTACHED TO PLANS AND IN THE FILE.
|
Plan assigned to (MYS) | 6/4/1997 | | 6/13/1997 | | |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 6/13/1997 | | |
|
|
|
Route the (2) main sets of drawings to ADA COUNTY HIGHWAY DISTRICT, PUBLIC WORKS, PLANNING, PLUMBING, then back to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT. Route separate set of structural plans to off site ENGINEER.
|
Recd Pcfee & Taken To Pln CK | | | 6/4/1997 | | |
|
|
|
|
Application received | | | 6/4/1997 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | | | | | |
|
|
|
6/13/97-Called Libby Hill for a 3rd set of structural sheets so we can send out to engineer for review. (9-12-97) Faxed a copy of the response from the Engineer of Record to the consultant Engineer (Bill Cook with Atwood-Hinzman-Jones) and ask him to review and comment.
|