Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD97-01597
StatusFinaled
Name DAN HANSEN
Site Address 3130 S OWYHEE ST
Project NameBRIDGEVIEW (BLDG)
Customer Number 
ePlanReviewNo
Description
(BRIDGEVIEW BUILDING #1)(NEW BUILDING) TO CONSTRUCT A (1) ONE STORY 9,846 SQ. FT. OFFICE BUILDING AND 1250 SQUARE FOOT BASEMENT WITH SITE IMPROVEMENTS. CONSTRUCTION TO BE ALL WOOD FRAME, CONCRETE FOUNDATION, TRUSS JOIST FLOOR SYSTEM, TRUSSED ROOF SYSTEM, INTERIOR FINISHED WITH SHEET-ROCK, SUSPENDED CEILINGS AND PARTITION WALLS. ALL PER APPROVED PLANS AND DR-34-97 PC-339-97 NOTE! THIS BUILDING IS NOT FIRE SPRINKLERED.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
(F) Reprint permit  8/5/1998
Fee Review-notes7/14/1998 8/5/1998 SUBS
Routing - PLAN CHECK6/30/1997 7/9/1998 PEND
PACKAGE #2
FEE REVIEW-NOTES  5/20/1998 FEES
THERE WAS A OVERPAYMENT ON PLAN CHECK FEES. THIS THE ADDITIONAL VALUES IT MAKES UP FOR THE OVERPAYMENT. I DIDN'T FEE DUE. BUT I DID ADD THE ADDITIONAL PROJECT FEE OF 33,750.00 LHJ
INSP - Final5/4/19985/4/19985/4/1998 PASS
DetailsJim Storey
05/04/98 301 - FNL -OK FINAL
Permanent Occupancy 5/4/19985/4/1998 DONE
Details
Permanent occupancy  5/4/1998 PASS
Perm. Occ. Cert. #7239 issued 5-4-98 to the Bridgeview Bldg. #1.
Code Occupancy Approval  4/30/1998 PASS
after a mod to the original DR was approved to deleat some vegetation and replace with trees, see letter in DR file, I made site inspection and all requirements have been made, signed off final 4-28-98
INSP-Final Inspection4/22/19984/22/19984/22/1998PPASS
DetailsRick Jackson
fire lanes per approved plans. occ approved
INSP-Final Inspection12/17/199712/17/199712/17/1997PPART
DetailsRick Jackson
12/17/97 409 - REINSPECTION fire lanes per approved plans still needed. temp c/o approved.
INSP - Final12/15/199712/17/199712/17/1997PPASS
DetailsJim Storey
12/17/97 301 - FNL -OK FINAL TCO -TEMP C OF O ISSUED routed by contractor.
Temporary occupancy  12/17/1997 PASS
Temp. Occ. Cert. #3522 issued 12-17-97 to Bridgeview.
INSP - Final12/12/199712/15/199712/15/1997AFAIL
DetailsJim Storey
12/15/97 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED hand rail. fire damper lables stopping.
INSP-Final Inspection12/12/199712/12/199712/12/1997PFAIL
DetailsRick Jackson
12/12/97 409 - c/n issued
INSP - Framing/Rough-in12/3/199712/3/199712/3/1997PPART
DetailsJim Storey
12/03/97 301 - CEILING GRID conf. ok
INSP - Framing/Rough-in11/18/199711/19/199711/19/1997APASS
DetailsJim Storey
11/19/97 301 - basement ceilings GWB -OK SHEETROCK NAILING on celling assembly
INSP - Framing/Rough-in11/10/199711/12/199711/12/1997APASS
DetailsJim Storey
11/12/97 301 - GWB -OK SHEETROCK NAILING shaft and tunnel in basement.
INSP - Framing/Rough-in11/5/199711/5/199711/6/1997PPART
DetailsJim Storey
11/05/97 301 - FRAM-OK FRAMING CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in10/30/199710/30/199710/30/1997PPART
DetailsJim Storey
10/30/97 301 - ok to rock exterior walls only
INSP - Foundation10/1/199710/2/199710/2/1997APASS
DetailsJim Storey
10/02/97 301 - REBAR FRMS-OK FORMS-REBAR
INSP - Footings9/19/19979/22/19979/22/1997APASS
DetailsJim Storey
09/22/97 301 - LATE A.M. FRMS-OK FORMS-REBAR
INSP - Foundation9/9/19979/10/19979/10/1997APASS
DetailsJim Storey
09/10/97 301 - FDN -OK FOUNDATION
INSP - Footings9/4/19979/5/19979/5/1997APASS
DetailsJim Storey
09/05/97 301 - FRMS-OK FORMS-REBAR out side perimitor
INSP - Footings8/27/19978/28/19978/28/1997APASS
DetailsJim Storey
08/28/97 301 - BASEMENT AND RE-BAR FRMS-OK FORMS-REBARfooting ok special insp on line for testing
(F) Reprint permit  8/26/1997
Plan assigned to (RGG)6/11/1997 8/25/1997 PASS
Routing - PLAN CHECK7/28/1997 8/25/1997 PASS
PACKAGE #2
Routing - PLAN CHECK7/21/1997 8/25/1997 PASS
PACKAGE #4
Print Occupancy Form  8/25/1997
(F) Reprint permit  8/25/1997
Issue PAID IN FULL permit  8/25/1997
Telephone call  8/25/1997
TALKED TO COLEEN AT HANSEN-RICE. TOLD HER PERMIT READY, FEE DUE, AND THEY MUST BRING ACHD RECEIPT BEFORE PERMIT CAN BE ISSUED
Inspection Record Card- Bld  8/25/1997
PLANS/APPL TAKEN TO FRONT DESK  8/25/1997 PASS
Routing - PLAN CHECK8/18/1997 8/25/1997 PASS
PACKAGE #3
Plan Reviewer's activity  8/25/1997 PASS
THE FINAL REVIEW AND ISSUANCE OF THIS PERMIT WAS DONE BY JCM.
Plan resubmittals received  8/22/1997 PASS
Routing - PLAN CHECK7/30/1997 8/18/1997 PEND
STRUCTURAL REVIEW FAXED OVER.
Routing Off Site - STRUCTURAL8/18/1997 8/18/1997 PASS
PACKAGE #3 PLANS RETURNED FROM STAPLEY AND GIVEN TO JOHN REVISE PLANS RECIEVED FROM STRUCTURAL ENGINEER ON 08/20/97 AND HAVE BEEN REVIEWED AND APPROVED. JCM/08/22/97
Routing Off Site - STRUCTURAL8/4/1997 8/11/1997 FAIL
Revised package #3 sent out to Stapley via PDQ.
Plan resubmittals requested  8/11/1997 PEND
STRUCTURAL CORRECTIONS REQUESTED FROM STAPLEY ENGINEERING. FAXED A COPY OF CORRECTION LIST TO DAN HANSEN AT HANSEN-RICE FOR A RESPONSE. ARCHITECT OF RECORD DID NOT INDICATE A FAX NUMBER.
Routing Off Site - STRUCTURAL6/11/1997 7/30/1997 FAIL
PACKAGE #3 CONTACTED PDQ TO TAKE PLANS TO STAPLEY ENG.
Routing - PLANNING7/24/1997 7/28/1997 PASS
X-REF: DR-34-97. APPROVED BY MGS.
Routing - PUBLIC WORKS7/9/1997 7/23/1997 PASS
Routing Off Site - A.C.H.D6/11/1997 7/21/1997 PASS
PACKAGE #4 CONTACTED RUSS HEPWORTH AT ###-#### TO TAKE PLANS OUT TO ACHD ACHD FEES PAID.
Routing - FIRE7/9/1997 7/14/1997 PASS
PACKAGE #1
Routing - MECHANICAL7/9/1997 7/9/1997 PASS
PACKAGE #1
Routing - PLAN CHECK6/17/1997 7/9/1997 FAIL
PACKAGE #1
Routing - PLUMBING7/2/1997 7/7/1997 PASS
PACKAGE #2
Routing - PLANNING6/20/1997 6/26/1997 FAIL
PACKAGE #2 TRASH ENCLOSURE NEEDS TO BE ADDED PER DR CONDITIONS. SPOKE WITH APPLICANT'S REP AND THEY WILL BE REVISING PLANS.
Routing - PUBLIC WORKS6/11/1997 6/19/1997 FAIL
PACKAGE #2 REQUIRES DRAINAGE PLAN REVISION
Routing - ELECTRICAL6/13/1997 6/16/1997 PASS
PACKAGE #1
Routing - PLUMBING6/11/1997 6/12/1997 FAIL
PACKAGE #1
Plan routing begun/NEW & ADDTN  6/11/1997 PASS
SEE ACTION 007
Plans ACCEPTED BY PLAN CHECK  6/11/1997 PASS
AM ROUTING PACKAGES #1,3,&4. WAITING FOR ELEVATIONS ON PACKAGE #2. CONTACTED GERALD MARTENS OF THIS NEED. 6-11-97 RECEIVED TWO SETS OF ELEV. SHEETS FOR PACKAGE #2 WILL ROUTE.
Received Certificate of Value  6/11/1997 PASS
Application received  6/6/1997
Print Pending Permit.LaserJet4  6/6/1997
Recd Pcfee & Taken To Pln CK  6/6/1997
Plan assigned to (MYS)6/6/1997 6/6/1997
DetailsMarlene Southard