Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD97-01610
StatusFinaled
Name MICHELLE JUELFS
Site Address 1465 S VINNELL WAY
Project NameGOODWILL/EASTER SEAL
Customer Number 
ePlanReviewNo
Description
GOODWILL INDUSTRIES/EASTER SEAL * * TO CONSTRUCT A NEW 19055 SQ.FT SINGLE STORY, CONCRETE MASONRY EXTERIOR WALL, FULLY FIRE SPRINKLERED, TYPE V NONRATED, RETAIL, OFFICE, WAREHOUSE, COLLECTION CENTER. THE RETAIL AREA IS APPROXIMATELY 9,846 SQ.FT. IN AREA, THE WAREHOUSE IS APPROXIMATELY 4,524,SQ.FT. IN AREA WITH THE REMAINING 4,454 SQ.FT. IS FOR OFFICE SPACE. ALL CONSTRUCTION PER THE APPROVED PLANS ATTACHED COMMENT LIST CABO/ANSI A117.1 AND THE 1994 EDITION OF THE UBC. THIS PERMIT IS TO INCLUDE LANDSCAPING, PARKING LOT AND RELATED SITE IMPROVEMENTS. MJP (PC#343-97) DR-21-97 CU-9-97
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled2/23/20012/23/20012/23/2001PPASS
DetailsRuss Owen
Added by Inspector: 407 On 2/23/2001 3:43:37 PM
Receive PAYMENT IN FULL  2/2/1998
INSP-Final Inspection1/22/19981/26/19981/27/1998PPASS
DetailsJoe Tawney
01/26/98 406 - 1:00 PLEASE ###-#### JOHN REINSP FOR FINAL OK FOR PERM OCC
INSP - Final1/26/19981/26/19981/26/1998PPASS
Details
01/26/98 338 - GOODWILL\###-#### JOHN made ok signed the perm occ colm
INSP - Final1/26/19981/26/19981/26/1998 PASS
DetailsJoe Tawney
/ / 406 - FINAL OK FOR TEMP OCC SMOKE/FIRE DOORS DET IN CONTROL RM LE
Permanent Occupancy 1/26/19981/26/1998 DONE
Details
INSP - Final1/21/19981/22/19981/22/1998ANR
Details
/ / 338 - FINAL/CALL JOHN V ###-#### TO SET APPT. TO MEET I signed p/z OTH-OTHER AGENCIES NOT APPROVED were on that project.
(F) Reprint permit  1/22/1998
INSP - Final1/21/19981/21/19981/21/1998PFAIL
DetailsRick Jackson
FINAL GOODWILL JOHN V 870=0342/CALL TO SET APPT. alarms not monitored, door hardware, need to test alarms, PIV locked.
Print Occupancy Form  1/16/1998
Inspection Record Card- Bld  1/16/1998
INSP-Sprinkler Rough-in/Hydro1/12/19981/14/19981/14/1998APART
DetailsJoe Tawney
01/14/98 406 - CALL MICK AT ###-#### FOR A TIME ok on hydro test of FDC piping
INSP - Conference1/14/19981/14/19981/14/1998 PASS
Details
/ / 338 - on phone with john to set time for inspection
INSP - Framing/Rough-in1/13/19981/14/19981/14/1998PPASS
Details
01/14/98 338 - ###-####-VANDERHOFF VERBAQL CORREWCTIONS ON THE CEILING G LIGHT FIXTURE SEIZMIC AND THE CROSS-T SLACK WIRES AT THE FINAL
INSP - Framing/Rough-in12/16/199712/16/199712/16/1997AFAIL
DetailsTom Arcoraci
NEEDS HEATING APPROVAL BEFORE COVER
INSP - Framing/Rough-in12/15/199712/16/199712/16/1997ACANC
Details
12/16/97 338 - goodwill done by 408
INSP - Framing/Rough-in11/24/199711/25/199711/25/1997APASS
Details
11/25/97 338 - made ok for the sign canopy only
INSP-Sprinkler Rough-in/Hydro11/21/199711/21/199711/21/1997 PART
DetailsJoe Tawney
11/21/97 406 - OK ON ABOVEGROUND HYDRO TEST EXCEPT FDC PIPING STILL NEED
INSP-Supply line flush11/17/199711/19/199711/19/1997PPART
DetailsJoe Tawney
11/19/97 406 - OK ON UNDERGROUND FLUSH AND UNDERGROUND HYDRO TEST
INSP - Miscellaneous11/5/199711/6/199711/6/1997A
DetailsTom Arcoraci
GROUT
INSP - Miscellaneous10/22/199710/23/199710/23/1997PPASS
Details
made ok with the sp insp approval
INSP - Miscellaneous10/21/199710/22/199710/22/1997PPASS
Details
r-bar made ok with sp insp approval
INSP - Miscellaneous10/21/199710/21/199710/21/1997PPASS
Details
made ok with sp insp approval
INSP - Miscellaneous10/20/199710/20/199710/20/1997PPASS
Details
GOODWILL/ MASONARY made ok with sp insp approval
INSP - Miscellaneous10/16/199710/17/199710/17/1997APASS
Details
MASONARY made ok with sp insp ok
INSP - Miscellaneous10/15/199710/15/199710/15/1997PPASS
Details
made ok with sp insp approval
INSP - Miscellaneous10/13/199710/14/199710/14/1997PPASS
Details
MASONARY/ GOODWILL, EASTER SEALS made ok with sp insp approval
INSP - Miscellaneous10/10/199710/10/199710/10/1997PPASS
Details
10/10/97 338 - MASONARY made ok with sp insp blessing
INSP - Miscellaneous10/8/199710/8/199710/8/1997PPASS
Details
10/08/97 338 - MASONARY made ok with sp insp approval
INSP - Miscellaneous10/6/199710/7/199710/6/1997APASS
Details
10/07/97 338 - MASONRY FOR RE-BAR CONCRETE POUR MASN-REBAR OK
INSP - Miscellaneous10/6/199710/6/199710/6/1997PPASS
Details
10/06/97 338 - MASONRY GROUT POUR FOR RE-BAR PLACEMENT made ok with sp i
INSP - Foundation10/1/199710/2/199710/2/1997PPASS
Details
10/02/97 338 - GOODWILL/ EASTER SEAL made ok with sp insp approval
CHANGE STATUS TO (F)  10/2/1997 FEES
ADDITIONAL FEES FROM ELECT. PARKING LOT AND WATER LINE LH
INSP - Foundation10/1/199710/1/199710/1/1997PCANC
Details
PER CONTRACTOR
INSP - Miscellaneous9/24/19979/25/19979/25/1997APASS
Details
09/26/97 338 - late am - rebar made ok with sp insp ok
INSP - Footings9/8/19979/9/19979/9/1997APASS
Details
09/09/97 338 - made ok for the ramp at the dock MASN-REBAR OK
INSP - Footings9/5/19979/8/19979/8/1997APASS
Details
09/08/97 338 - MASN-REBAR OK ok to pour with sp insp approval
INSP - Foundation9/8/19979/8/19979/8/1997 PASS
Details
/ / 338 - front entry stem walls and colmn bolting
90 day tracking............. 6/9/19979/7/1997 PEND
INSP - Footings9/4/19979/5/19979/4/1997APASS
Details
09/04/97 338 - FTG -OK FOOTING
INSP - Footings9/4/19979/5/19979/4/1997APASS
Details
09/04/97 338 - Scheduled by Hello! on 09/04/97 at 09:40:39. FTG -OK FOOTING
INSP - Wall cover9/3/19979/4/19979/4/1997APASS
Details
09/04/97 338 - RESCHEDULED THIS IS A FOUNDATION WAL INSPECTION SOUTH 1/2 INSP APPROVAL
INSP - Wall cover9/2/19979/3/19979/3/1997ANR
Details
09/03/97 338 - CANCELLED BY THE CTR TIL NEXT DAY WILL RECALL
INSP - Wall cover9/2/19979/3/19979/3/1997PNR
Details
09/03/97 338 - CANCELLED BY THE CTR WILL RECALL FOR TOMORROW
INSP - Foundation9/2/19979/2/19979/2/1997PPASS
Details
09/02/97 338 - north and west 1/2 for the foundation . FDN -OK FOUNDATION MASN-REBAR OK
INSP - Footings8/28/19978/29/19978/29/1997APASS
Details
08/29/97 338 - could you go somewhere between 8 and 10 a.m.??? FTG -OK FOOTING MASN-REBAR OK SP INSP OK
INSP - Footings8/26/19978/27/19978/28/1997APASS
Details
08/27/97 338 - north 1/2 ok sp insp made ok MASN-REBAR OK FTG -OK FOOTING
(F) Reprint permit  8/25/1997
INSP - Conference8/18/19978/19/19978/19/1997APASS
Details
08/19/97 338 - questions about sp inspections all was blind as the appro there.
Plan assigned to (M_P)7/10/1997 8/18/1997 PASS
DetailsMike Phillips
08/18/97 10:12:07 DAR - this action updated by action script from <<>> in Case No. BLD97-1610
PLANS/APPL TAKEN TO FRONT DESK  8/18/1997 PASS
Inspection Record Card- Bld  8/18/1997
Print Occupancy Form  8/18/1997
(F) Reprint permit  8/18/1997
Issue PAID IN FULL permit  8/18/1997
Telephone call  8/18/1997
CALLED ANSWERING MACHINE LEFT MESSAGE PERMIT READY
Plan Reviewer's activity  8/15/1997 PASS
Print Pending Permit.LaserJet4  8/15/1997 PASS
Routing Off Site - STRUCTURAL7/31/1997 8/14/1997 PASS
REVISED SET SENT TO CH2MHILL VIA PDQ OUT SIDE STRUCTURAL REVIEW COMPLETE AND APPROVED BY H. HENRIKSON.
Plan Reviewer's activity  8/12/1997 PEND
Waiting for outside sructural review to return
Routing - PUBLIC WORKS7/17/1997 8/11/1997 PASS
PACKAGE #2
Routing Off Site - A.C.H.D6/19/1997 8/4/1997 PASS
PACKAGE #4 CONTACTED JON VANDERJOEF AT ###-#### TO TAKE PLANS OUT TO ACHD ACHD FEES NOT PAID. ACHD FEES PAID 8/14/97 DAR.
Routing - FIRE7/18/1997 7/28/1997 PASS
PACKAGE #1
Print Pending Permit.LaserJet4  7/17/1997 FAIL
SENT CORRECTION REPORT.
Plan Reviewer's activity  7/17/1997 FAIL
SENT CORRECTION LETTER ALONG WITH OUTSIDE STRUCTURAL COMMENT TO ARCHITECT.
Routing - PLANNING6/19/1997 7/16/1997 PASS
PACKAGE #2 Approved by: RLB & TKW
Plan assigned to (RGG)6/11/1997 7/10/1997
Routing - ELECTRICAL6/26/1997 6/30/1997 PASS
PACKAGE #1
Routing - PLUMBING6/19/1997 6/26/1997 PASS
PACKAGE #1
Routing Off Site - STRUCTURAL6/13/1997 6/23/1997 FAIL
PACKAGE #3 CONTACTED PDQ TO TAKE PLANS OUT TO CH2MHILL Resubmittal respocse required from outside engineer
Plans ACCEPTED BY PLAN CHECK  6/19/1997 PASS
PACKAGE #1 RECEIVED TWO STAMPED AND SIGNED SITE PLANS. PACKAGE #2 RECEIVED RECEIVED TWO STAMPED AND SIGNED SITE PLANS AND DRAINAGE CALCS. WITH TOPO SHEET PACKAGE #4 RECEIVED TWO STAMPED AND SIGNED SITE PLANS AND TOPO SHEETS WITH DRAINAGE CALCS. THESE PACKAGE ARE READY TO ROUTE
Plan routing begun/NEW & ADDTN  6/19/1997 PASS
SEE ACTION 007 PASS
Plan routing begun/NEW & ADDTN  6/13/1997 HOLD
SEE ACTION 007 HOLD
Plans ACCEPTED BY PLAN CHECK  6/13/1997 HOLD
PACKAGES #1,2,AND 4 ON HOLD FOR SITE PLANS. CONTACTED PETE ROCKWELL AT ###-#### OF THIS NEED.
Plan assigned to (MYS)6/9/1997 6/9/1997
DetailsMarlene Southard
Application received  6/9/1997
Recd Pcfee & Taken To Pln CK  6/9/1997
(F) Reprint permit  6/9/1997
Received Certificate of Value  6/9/1997 PASS
Routing - PLAN CHECK7/28/1997  
Routing - PLAN CHECK6/23/1997  
PACKAGE #3
Routing - MECHANICAL   
PAKCAGE #1
Routing - PLAN CHECK8/11/1997