INSP - Letter of compliance | 12/11/1997 | 12/11/1997 | 12/11/1997 | | PASS |
Russ Owen
|
|
|
/ / 407 - LC#12840,contractor ordered 2 temp windows,temporay boared w inspection when installed.
|
INSP - Letter of compliance | 12/11/1997 | 12/11/1997 | 12/11/1997 | | PASS |
Russ Owen
|
|
|
/ / 407 - LC#12840,contractor ordered 2 temp windows,temporay boared w inspection when installed.
|
INSP - Final | 12/10/1997 | 12/11/1997 | 12/11/1997 | P | PASS |
Russ Owen
|
|
|
12/11/97 407 -
|
INSP - Final | 12/9/1997 | 12/10/1997 | 12/10/1997 | A | FAIL |
Russ Owen
|
|
|
12/10/97 407 - left corrections.
|
INSP - Wall cover | 9/30/1997 | 10/1/1997 | 10/1/1997 | A | PASS |
Russ Owen
|
|
|
10/01/97 407 - SHEER WALL IN THE BASEMENT. This wall completes foundatio engineer. also attached to enginering was rebar #4 ok at a tall section wall. This now completes foudation.
|
INSP - Energy code compliance | 9/25/1997 | 9/26/1997 | 9/26/1997 | A | PASS |
Russ Owen
|
|
|
09/26/97 407 -
|
INSP - Framing/Rough-in | 9/23/1997 | 9/24/1997 | 9/24/1997 | A | PASS |
Russ Owen
|
|
|
09/24/97 407 -
|
INSP - Framing/Rough-in | 9/19/1997 | 9/22/1997 | 9/22/1997 | A | FAIL |
Russ Owen
|
|
|
09/22/97 407 - left corrections.
|
INSP - Framing/Rough-in | 9/18/1997 | 9/19/1997 | 9/19/1997 | P | CANC |
Russ Owen
|
|
|
09/19/97 407 - will call in for monday am inspection.
|
INSP - Conference | 9/17/1997 | 9/17/1997 | 9/17/1997 | | PART |
Russ Owen
|
|
|
/ / 407 - talked with contractor about correction notice for straps le sheating,said he had a repair from engineer,told him not to cover the re wall where hold-down are untill inspection.
|
INSP - Conference | 9/17/1997 | 9/17/1997 | 9/17/1997 | | PART |
Russ Owen
|
|
|
/ / 407 - talked with contractor about correction notice for straps le sheating,said he had a repair from engineer,told him not to cover the re wall where hold-down are untill inspection.
|
INSP - Miscellaneous | 9/17/1997 | 9/15/1997 | 9/17/1997 | | PART |
Russ Owen
|
|
|
on mechanical insp,left a framing correction for stapHD,s let-into sheating. added this in 9/17/97.
|
INSP - Conference | 7/31/1997 | 7/31/1997 | 7/31/1997 | | PART |
Russ Owen
|
|
|
/ / 407 - foundation contractor called me,said the engineer has approv instead of #5 for horizontals, on the taller walls, said i would get a f asked to pour i said at your own risk.
|
INSP - Wall cover | 7/29/1997 | 7/29/1997 | 7/29/1997 | P | PART |
Russ Owen
|
|
|
07/29/97 407 - contractor has a revised detail for a butras on the far l will have detail from engineer. also the 8'to9' high walls call for #5 b horizontal have #4 bar need approval from engineer left correction and m number.
|
INSP - Footings | 7/24/1997 | 7/25/1997 | 7/25/1997 | P | PASS |
Russ Owen
|
|
|
07/25/97 407 - WILL BE READY AT 1 O'CLOCK footings ok.
|
Issue PAID IN FULL permit | | | 6/24/1997 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/23/1997 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 6/23/1997 | | PASS |
|
|
|
ROOF FRAME INFO REC.
|
Plan assigned to (DJO) | 6/12/1997 | | 6/23/1997 | | PASS |
Dan Overy
|
|
|
06/23/97 13:38:50 DJO - this action updated by action script from <<>> in Case No. BLD97-1651
|
Telephone call | | | 6/23/1997 | | |
|
|
|
PERMIT READY, FEE DUE
|
Inspection Record Card- Bld | | | 6/23/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/23/1997 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 6/19/1997 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 6/19/1997 | | PEND |
|
|
|
information required for roof frame
|
Routing - PLANNING | 6/16/1997 | | 6/17/1997 | | PASS |
|
|
|
Approved by: GRH
|
Routing - PUBLIC WORKS | 6/12/1997 | | 6/16/1997 | | PASS |
|
|
|
|
Application received | | | 6/12/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 6/17/1997 | | | | PEND |
|
|
|
|