Permanent occupancy | | | 1/8/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7584 issued 1-8-99 to Dr. Foote in the St. Al's Ofc. Bldg. #5.
|
Permanent Occupancy | | 11/16/1998 | 11/16/1998 | | DONE |
|
|
|
|
INSP - Final | 11/16/1998 | 11/16/1998 | 11/16/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
INSP - Final | 10/29/1998 | 10/29/1998 | 10/29/1998 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - REINSP FAIL WAITING FOR SHELL SIGN OFF
|
Temporary occupancy | | | 5/6/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3602 issued 5-6-98 to Dr. Julie Foote.
|
INSP - Final | 4/30/1998 | 4/30/1998 | 4/30/1998 | P | PASS |
|
|
|
OK FOR THE OFFICE TO SIGN FOR ME
|
INSP - Final | 4/30/1998 | 4/30/1998 | 4/30/1998 | | PASS |
|
|
|
04/30/98 338 - made ok for office to sign for me
|
INSP - Final | 4/30/1998 | 4/30/1998 | 4/30/1998 | | PASS |
|
|
|
04/30/98 338 - made ok for office to sign for me
|
INSP-Alarm Testing | 4/29/1998 | 4/30/1998 | 4/30/1998 | P | PART |
Joe Tawney
|
|
|
04/30/98 406 - RON/###-#### - RE-INSPECTION. REINSP OK FOR TEMP OCC SHELL NOT FINALLED
|
INSP - Final | 4/23/1998 | 4/24/1998 | 4/24/1998 | A | NR |
|
|
|
04/24/98 338 - ###-#### did not pass per 406
|
INSP-Final Inspection | 4/23/1998 | 4/23/1998 | 4/24/1998 | P | CANC |
Joe Tawney
|
|
|
04/23/98 406 - ###-#### RON FINAL CANCELLED RESCHED TO 4/24/98
|
INSP - Wall cover | 3/30/1998 | 3/31/1998 | 3/31/1998 | A | FAIL |
Jim Storey
|
|
|
03/31/98 301 - FIRE WALL--DR FOOTE OFFICE--RON ###-#### FIRE STOPPING REQUIRED ON PENTRATIONS/ P.PAINE WILL REINSP AT FRAMING IN
|
INSP - Framing/Rough-in | 2/24/1998 | 2/25/1998 | 2/25/1998 | A | PART |
|
|
|
02/25/98 338 - ron pager 3838553 located on 2nd floor made ok to drywall need to check rated wall terminations at the underfloor and under the ui beams
|
INSP - Framing/Rough-in | 2/13/1998 | 2/17/1998 | 2/17/1998 | A | NR |
Wes Worcester
|
|
|
02/17/98 342 - 2ND FLOOR ###-#### RON called by Perry and will reschedul
|
Issue PAID IN FULL permit | | | 2/5/1998 | | |
|
|
|
|
90 day tracking............. | | 6/18/1997 | 9/16/1997 | | |
|
|
|
|
Plan assigned to (CJW) | 7/3/1997 | | 9/5/1997 | | PASS |
Carl Westfall
|
|
|
09/05/97 10:49:00 CJW - this action updated by action script from <<>> in Case No. BLD97-1716
|
Inspection Record Card- Bld | | | 9/5/1997 | | |
|
|
|
|
Print Occupancy Form | | | 9/5/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/5/1997 | | PASS |
|
|
|
|
Telephone call | | | 9/5/1997 | | |
|
|
|
CALLED VIVIAN PERMIT READY
|
Print permit w/o conditions | | | 9/4/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 9/4/1997 | | PASS |
|
|
|
Drawings approved, with conditions, after review of Architect's response.
|
testing condition printout | | | 9/4/1997 | | |
|
|
|
|
Plan resubmittals received | | | 8/27/1997 | | |
|
|
|
Received response from the Architect.
|
Routing - FIRE | 7/25/1997 | | 7/29/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 7/15/1997 | | 7/25/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 7/24/1997 | | |
|
|
|
UBC plan check started July 24, 1997 and finished July 25, 1997. Response required from the Architect.
|
Routing - PLUMBING | 7/10/1997 | | 7/14/1997 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/8/1997 | | 7/10/1997 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 7/3/1997 | | |
|
|
|
Route to PUBLIC WORKS and PLUMBING then back to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT.
|
Plan assigned to (MYS) | 6/18/1997 | | 7/3/1997 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 7/2/1997 | | |
|
|
|
PLANS WERE ON HOLD UNTIL 7/2/97 WAITING FOR ARCHITECT TO COME IN TO STAMP AND SIGN PART OF THE PLANS.
|
Application received | | | 6/18/1997 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/18/1997 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 7/30/1997 | | | | |
|
|
|
|