Permit Information
Permit NumberBLD97-01824
StatusFinaled
Name BMC WEST
Site Address 720 PARK BLVD Unit: 2 FLR
Project NameMK CENTRAL PLAZA
Customer Number 
ePlanReviewNo
Description
To remodel the west half of the second floor for new office tenant area of 24,096 sq. ft. and central lobby area of 3,270 sq. ft. A certificate of occupancy to be issued for BMC West. A vanilla finish for Suite I is a part of this permit - a letter of compliance to be issued when finaled - separate plans & permit required for C of O when tenant space is to be leased. All per approved plans on file. Work to include interior noncombustible, nonbearing walls, suspended ceiling system, connection & testing of the smoke exhaust system for the building as previously agreed. Agreement on file. NOTE: This building is fully fire sprinklered and will have an approved smoke exhaust system for the entire building. FRAMING ALLOWED TO BEGIN PRIOR TO PERMIT ISSUANCE PER LETTER FROM TIM HOGLAND, DIRECTOR OF THE PLANNING & DEVELOPMENT SERVICES DEPT. DATED 7/31/97 - NO INSPECTIONS CAN BE AUTHORIZED UNTIL A BUILDING PERMIT IS ISSUED. FINAL & ISSUANCE OF CERTIFICATE OF OCCUPANCY FOR TENANT WILL BE TIED TO APPROVAL OF SMOKE EXHAUST SYSTEM & PASSING FIELD TESTING. (P.C.#387-97)/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 12/23/199712/23/1997 DONE
Details
Permanent occupancy  12/23/1997 PASS
Perm. Occ. Cert. #7085 issued 12-23-97 to BMC West.
INSP - Final12/22/199712/22/199712/22/1997PPASS
DetailsWes Worcester
12/22/97 342 - Hi, Parnelli! ì
INSP-Final Inspection12/22/199712/22/199712/22/1997PPASS
DetailsRick Jackson
re-inspect of sprinkler head in conference room and verification of smoke evac modifications
INSP-Final Inspection10/31/199710/31/199710/31/1997PPART
DetailsRick Jackson
temp c/o approved. recheck smoke evac system dampers by 11/30.
INSP - Final10/31/199710/31/199710/31/1997PPASS
DetailsWes Worcester
10/31/97 342 -
Temporary occupancy  10/31/1997 PASS
Temp. Occ. Cert. #3494 issued 10-31-97 to BMC West for offices.
INSP - Final10/30/199710/30/199710/30/1997PNR
DetailsWes Worcester
10/30/97 342 - have not rec'd smk exhaust exception
INSP - Conference10/30/199710/30/199710/30/1997 PART
DetailsWes Worcester
/ / 342 - talked to Bob...called Dan 3 times
INSP - Final10/30/199710/30/199710/30/1997 FAIL
DetailsWes Worcester
/ / 342 - STAIRTOWER PENETRATIONS STILL NOT ALL FIRESTOPPED.....4-5 TR LEAST 1 FOR BOB
INSP - Final10/28/199710/29/199710/29/1997PFAIL
DetailsWes Worcester
10/28/97 342 -
INSP - Conference10/29/199710/29/199710/29/1997 PART
DetailsWes Worcester
/ / 342 - met w/architect and vp of owner, need smoke evach system agr braced wall panels, fire dept approval as previously discussed
INSP-Final Inspection10/28/199710/29/199710/29/1997AFAIL
DetailsRick Jackson
approved doors exiting BMC West to lobby area. smoke evacuation system not tested per building permit requirement.
INSP - Final10/23/199710/24/199710/24/1997PNR
DetailsWes Worcester
10/24/97 342 -
INSP-Sprinkler Rough-in/Hydro10/23/199710/24/199710/24/1997AFAIL
DetailsRick Jackson
alarm system not ready. c/n issued.
90 day tracking............. 6/26/19979/24/1997 PEND
INSP - Framing/Rough-in9/15/19979/16/19979/16/1997PPART
DetailsWes Worcester
09/16/97 342 - detail elevator shaft repair as necessary if required for
INSP - Conference9/10/19979/10/19979/10/1997PCANC
DetailsDave Lightfoot
09/10/97 337 - 1:30 pm w/arch, owner, drywall i have a meeting at the hotel at this time
INSP - Conference9/9/19979/10/19979/10/1997PPART
DetailsWes Worcester
09/09/97 342 - AS PER WES 1:30
INSP - Conference9/10/19979/10/19979/10/1997PPASS
DetailsBob Archibald
Pre-con and clairification meeting w/ Wes, architect and maintence manager.
INSP - Framing/Rough-in9/8/19979/9/19979/9/1997PNR
DetailsWes Worcester
09/09/97 342 - 3pm
INSP - Conference9/9/19979/9/19979/9/1997 PART
DetailsWes Worcester
/ / 342 - schedule w/fire, mech, arch, owner, drywall/grid installer a
Routing - PLAN CHECK9/5/1997 9/5/1997 PASS
PLANS/APPL TAKEN TO FRONT DESK  9/5/1997 PASS
Plan resubmittals received  9/5/1997
Received information on smoke exhayst system from Ken Tewksbury, Mech. Eng., designing smoke exhaust system. Reviewed results of field test with fire dept. Ther are still questions to be answered and smoke exhaust plans to be presented for review and approval showing the locations of system components & tie in with existing components and the final field test for final C.O. for the tenants.
Issue PAID IN FULL permit  9/5/1997
Print Occupancy Form  9/5/1997
Print Pending Permit.LaserJet4  9/5/1997 PASS
Inspection Record Card- Bld  9/5/1997
Plan resubmittals requested  8/23/1997 PEND
Faxed copy to John Maulin and mailed copy.
Routing - PLAN CHECK8/15/1997 8/23/1997
Finished preliminary review - copy of corrections needed sent to John Maulin. Outstanding questions concerning the smoke exhaust system that seems to be handled separately form all other TI. This raises a question on the compatability of the two designs when the smoke exhaust is to be done thus causing more delays.
Telephone call  8/22/1997
Called Glenn Boardman of CSHQA to set up an appointment with those involved in MK Smoke Exhaust system design. Two copies of the 1981 Honeywell electrical/mechanical drawings had been presented to me in response to my phone call to Mr. Maulin on the 18th of August. I couldn't see that the plans addressed the original smoke exhaust system system that has been verbally refered to by designers involved. I asked Glenn Boardman to review the plans and come prepared to assist me through them on Monday the 25.
Plan Reviewer's activity  8/20/1997
CSHQA submitted three TI plans for the East half area to get Occupancy. There is still the questions on the smoke exhaust system design & testing details. I am meeting with John Maulin & group on Monday at 10 am to revisit the issues.
Plan Reviewer's activity  8/18/1997
Letter sent to John Maulin concerning the schedule sent for acceptance for proposed time frame for design, submittal for approval, installation and testing of smoke exhaust system. A phone conversation with John Maulin revealed he did not have a copy of the letter of agreement signed by Mr. Houston with agreed to items to be answered prior to occupancy certificates for proposed tenants of the east half remodel. The letter was signed in order to have a permit issued for the East half TI and to clarify conditions still in question. I have not received any new information in regard to the letter of agreement but have been asked to approve this time frame plan and allow occupancy for tenant in East half before answeres are received. This process seems to be working for the tenat/owners but is not resolving concerns of fire & building dept, plan reviewers code considerations.
Routing - PLAN CHECK8/7/1997 8/15/1997
Started to review plans
Plan Reviewer's activity  8/8/1997
LETTER WRITTEN BY T. HOGLAND ON FILE DATED 7/31/97 ALLOWING FRAMING TO BEGIN PRIOR TO PERMIT ISSUANCE. NO INSPECTIONS CAN BE PERFORMED PRIOR TO PERMIT ISSUANCE.
Routing - FIRE8/4/1997 8/6/1997 PASS
Plan assigned to (DRS)7/1/1997 8/1/1997 PEND
DetailsDan Stuart
Plans picked for quick review in order to submit to Fire Dept. for review while on vacation.
Routing - PLAN CHECK7/8/1997 8/1/1997 PEND
Plans processed to allow fire dept. review while I am on vacation.
Routing - PLAN CHECK8/1/1997 8/1/1997 PEND
Routing to fire Dept. for review.
Routing - PUBLIC WORKS7/1/1997 7/8/1997 PASS
Plan routing begun/TENANTS  7/1/1997
Route to PUBLIC WORKS then back to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT.
Plan assigned to (MYS)6/26/1997 7/1/1997
DetailsMarlene Southard
Application received  6/26/1997
Recd Pcfee & Taken To Pln CK  6/26/1997