INSP - Grading Inspection | 6/22/1998 | | 6/22/1998 | | PASS |
Rita DeYoung
|
|
|
Revegetation is complete and $400.00 bond that was submitted can be released.
|
INSP - Final | 1/5/1998 | 1/5/1998 | 1/5/1998 | P | PASS |
Carl Dependahl
|
|
|
REINSP. $400 bond to be posted for completion of items.
|
INSP - Letter of compliance | 1/5/1998 | 1/5/1998 | 1/5/1998 | P | PASS |
Carl Dependahl
|
|
|
LC 014340 SUBJECT TO BOND FOR COMPLETION...
|
INSP - Conference | 1/5/1998 | 1/5/1998 | 1/5/1998 | A | PASS |
Carl Dependahl
|
|
|
W/ TERRY RECORDS: HE REC'D ENG'S LETTER, WILL RE CHK SITE.
|
INSP - Final | 12/30/1997 | 1/2/1998 | 1/2/1998 | A | FAIL |
Carl Dependahl
|
|
|
NEED ENGS LETTER, AIR SEAL, ETC.
|
INSP - Conference | 12/31/1997 | 12/30/1997 | 12/30/1997 | P | PASS |
Carl Dependahl
|
|
|
W/ TERRY RECORDS; GOT MEMO RE GRADING & OK TO FINAL IF ENG'S LETTER, EROSION CONTROL AT FRONT OF LOT & ROOF DRAINS OK
|
INSP - Carpentry | 12/30/1997 | 12/29/1997 | 12/29/1997 | P | PART |
Carl Dependahl
|
|
|
NEED TO COMPLETE GRADING,GET P.W. OK FOR FINAL
|
INSP - Carpentry | 10/28/1997 | 10/28/1997 | 10/28/1997 | P | PASS |
Carl Dependahl
|
|
|
3:00 W/ BLDR. beam support ok
|
INSP - Framing/Rough-in | 10/29/1997 | 10/28/1997 | 10/28/1997 | P | PASS |
Carl Dependahl
|
|
|
c/n ok
|
INSP - Carpentry | 10/23/1997 | 10/23/1997 | 10/23/1997 | P | NR |
Wes Worcester
|
|
|
10/23/97 342 - chk beam brg at floor .....no one there, not done
|
INSP - Conference | 10/23/1997 | 10/23/1997 | 10/23/1997 | A | PASS |
Carl Dependahl
|
|
|
W/ JOHN RYAN RE FRAME C/N
|
INSP - Energy code compliance | 10/21/1997 | 10/22/1997 | 10/22/1997 | A | CANC |
Wes Worcester
|
|
|
10/22/97 342 - given to Carl
|
INSP - Energy code compliance | 10/22/1997 | 10/22/1997 | 10/22/1997 | P | PASS |
Tom Arcoraci
|
|
|
|
INSP - Framing/Rough-in | 10/22/1997 | 10/22/1997 | 10/22/1997 | P | PART |
Tom Arcoraci
|
|
|
ok to cover all but area around beam at stairs
|
INSP - Framing/Rough-in | 10/20/1997 | 10/20/1997 | 10/20/1997 | P | PART |
Carl Dependahl
|
|
|
OK TO INSUL...NEED COMPLETE FIREBLOCKS& VERIFY BRG FOR BEAM ADDED NEAR STAIRS
|
INSP - Conference | 10/17/1997 | 10/17/1997 | 10/17/1997 | A | PASS |
Carl Dependahl
|
|
|
TOLD FRAMER NEED TRUSS ENG'S OK FOR BEAM BEARING AT TRUSSES.
|
INSP - Conference | 10/16/1997 | 10/16/1997 | 10/16/1997 | A | PASS |
Carl Dependahl
|
|
|
W/ JOHN RYAN, REQUESTED PLAN TO BE ONSITE.
|
INSP - Framing/Rough-in | 10/15/1997 | 10/16/1997 | 10/16/1997 | P | PART |
Carl Dependahl
|
|
|
NEED TRUSS ENG'S OK FOR BEAM AT COMMON TRUSSES & FULL PLBG OK
|
INSP - Wall cover | 9/10/1997 | 9/11/1997 | 9/11/1997 | P | NR |
Tom Arcoraci
|
|
|
SHEER WALL NAILING DISSCUSED NAILING PATTERN
|
INSP - Footings | 7/29/1997 | 7/29/1997 | 7/29/1997 | P | PART |
Carl Dependahl
|
|
|
07/29/97 340 - late pm ...BSMT WALL, PART.
|
INSP - Footings | 7/25/1997 | 7/25/1997 | 7/25/1997 | P | PART |
Carl Dependahl
|
|
|
PART, BSMT. FTGS ONLY
|
Issue PAID IN FULL permit | | | 7/22/1997 | | |
|
|
|
|
Plan assigned to (PRP) | 6/27/1997 | | 7/17/1997 | | PASS |
|
|
|
07/17/97 11:15:39 PRP - this action updated by action script from <<>> in Case No. BLD97-1825
|
Plan Reviewer's activity | | | 7/17/1997 | | PASS |
|
|
|
REVIEW PLANS, MARK-UP, INPUT TO TIDEMARK, CONDITIONS, ASSEMBLE, ISSUE
|
Inspection Record Card- Bld | | | 7/17/1997 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 7/17/1997 | | PASS |
|
|
|
FILES
|
Telephone call | | | 7/17/1997 | | |
|
|
|
LEFT MESSAGE ON MACHINE
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/17/1997 | | PASS |
|
|
|
ISSUE
|
Routing - PLAN CHECK | 7/16/1997 | | 7/17/1997 | | PASS |
|
|
|
|
Print Occupancy Form | | | 7/17/1997 | | |
|
|
|
|
Routing - PLANNING | 7/10/1997 | | 7/15/1997 | | PASS |
|
|
|
Approved by: MH
|
Routing - PUBLIC WORKS GRADING | 7/9/1997 | | 7/9/1997 | | PASS |
Rita DeYoung
|
|
|
Approved as category 3.
|
Application received | | | 6/26/1997 | | |
|
|
|
|