TO CONSTRUCT A 11,800 SQ. FT. SINGLE STORY, TYPE V-N, STORAGE WAREHOUSE BUILDING. ALL WORK IS PER APPROVED PLANS AND ATTACHMENTS ON FILE AND, PC-97-392 AND ZONING CERT. 5-22-97.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 8/21/19988/21/1998 DONE
Details
Permanent occupancy  8/21/1998 PASS
Perm. Occ. Cert. #7362 issued 8-21-98 to the Boise School District for a storage/warehouse bldg.
INSP - Final7/31/19987/31/19987/31/1998PPASS
Details
07/31/98 333 - card signed for perm
PubWorks Occupancy Approval  7/31/1998 DONE
Drainage project complete 07/31/98. R.Rokovitz
INSP - Final7/17/19987/17/19987/17/1998PPASS
Details
final ok card signed
INSP-Final Inspection7/14/19987/15/19987/15/1998APASS
DetailsRick Jackson
DENNIS GOFF ###-#### FINAL INSP occ approved
Code Occupancy Approval  7/14/1998 PASS
Checked site. No landscape requirements.
INSP - Framing/Rough-in2/11/19982/12/19982/12/1998APART
Details
02/12/98 333 - pre frame need engineer to review DENNIS ###-####
INSP - Framing/Rough-in1/23/19981/23/19981/23/1998PPART
Details
01/23/98 333 - talked about property line south wall openings protection
Routing - PLANNING12/31/1997 12/31/1997 PASS
REVISED ROOF OVERHANG.
Routing - PUBLIC WORKS12/31/1997 12/31/1997 PASS
REVISED ROOF OVERHANG.
Plan resubmittals received  12/31/1997 PASS
PLANS FOR REVISED OVERHANG REVIEWED AND APPROVED.MO
Routing - PLAN CHECK12/31/1997 12/31/1997 PASS
REVISED ROOF OVERHANG.
INSP - Footings10/8/199710/9/199710/9/1997PFAIL
Details
10/09/97 333 - REBAR canceled till tomorrow
INSP - Foundation10/6/199710/6/199710/6/1997PPASS
DetailsWes Worcester
LAST SECTION OF FDN WALL POURED
INSP - Foundation10/6/199710/6/199710/6/1997PNR
DetailsWes Worcester
NEEDS 25" SPLICE ON REBAR LAPS....PLACING ADD BAR
INSP - Footings10/6/199710/6/199710/6/1997PNR
DetailsWes Worcester
IMBEDDED WOOD IN FTG NORTH SIDE...DO NOT BACKFILL UNTIL REMOVED AND APPROVAL BY INSPECTOR
INSP - Foundation10/1/199710/2/199710/2/1997APART
DetailsWes Worcester
REBAR....NEEDS 40D ON #5 REBAR AND 2" SIDE BOARD CLEARANCE
INSP - Conference9/29/19979/29/19979/29/1997APASS
DetailsWes Worcester
reposition some rebar and special insp on site for wall
INSP - Foundation9/26/19979/29/19979/29/1997APART
DetailsWes Worcester
steel footing and foundations West portion only
INSP - Footings9/29/19979/29/19979/29/1997APASS
DetailsWes Worcester
finished entire ftg
90 day tracking............. 6/26/19979/24/1997 PEND
INSP - Footings9/22/19979/23/19979/23/1997APASS
Details
09/23/97 333 - ok pending special insp reports
(F) Reprint permit  9/23/1997
PLANS/APPL TAKEN TO FRONT DESK  9/22/1997 PASS
Inspection Record Card- Bld  9/22/1997
Print Occupancy Form  9/22/1997
Issue PAID IN FULL permit  9/22/1997
(F) Reprint permit  9/22/1997
(F) Reprint permit  9/22/1997
Routing - FIRE9/19/1997 9/22/1997 PASS
Telephone call  9/22/1997
CALLED JEFF FOSTER PERMIT READY
Plan assigned to (M_O)8/22/1997 9/22/1997 PASS
Telephone call  9/15/1997 PEND
Talked to architect and Chuck Tinder of Boise School Dist. regarding early foundation permit. Early start is on hold until meeting with Fire Chief and Chuck Tinder on paving requirements set by Fire Dept. Plan Review. Project may be cancelled if paving is required per C. Tinder. MO
Routing - FIRE8/25/1997 9/8/1997 FAIL
FIRE HYDRANT AND DIFFERENT TYPE OF ROADBED (CAPABLE OF SUPPORTING 70,000 POUNDS) REQUIRED.
Routing - PLAN CHECK9/5/1997 9/8/1997 PASS
Plan resubmittals received  9/5/1997 PEND
RECEIVED RESUBMITTALS FROM ARCHITECT FOR PLAN CHECK COMMENTS. MO
Routing - PLAN CHECK8/22/1997 8/25/1997 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MO
Plan resubmittals requested  8/25/1997 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT 8-25-97. MO
Plan assigned to (RGG)7/1/1997 8/22/1997 PASS
Routing - ELECTRICAL8/7/1997 8/8/1997 PASS
Routing - PUBLIC WORKS8/5/1997 8/7/1997 PASS
Routing - PLUMBING7/30/1997 8/5/1997 PASS
Routing - PLANNING7/24/1997 7/29/1997 PASS
APPROVED BY MGH.
Routing - PUBLIC WORKS7/18/1997 7/24/1997 FAIL
NEEDS DRAINAGE PLAN REVISION.
Routing Off Site - A.C.H.D7/1/1997 7/17/1997 PEND
CONTACTED JEFF FOSTER AT ###-#### TO TAKE PLANS OUT TO ACHD ACHD FEES DUE.
Plan assigned to (MYS)6/26/1997 7/1/1997
DetailsMarlene Southard
Plan routing begun/NEW & ADDTN  7/1/1997 PASS
Received Certificate of Value  7/1/1997 PASS
JUST USED PHASE II VALUE. WILL CONTACT DICK BROOKS FOR NEW FINAL CERT. TO INCLUDE PHASE I AND II.
Plans ACCEPTED BY PLAN CHECK  7/1/1997
COMBINDED BLD97-1826 PHASE I AND BLD97-1828 PHASE II INTO ONE PERMIT UNDER BLD97-1828 PC#392-97
Plans ACCEPTED BY PLAN CHECK  7/1/1997 PASS
Recd Pcfee & Taken To Pln CK  6/26/1997 PEND
Application received  6/26/1997