DOC - Permit Finaled | 1/24/2001 | 1/24/2001 | 1/24/2001 | P | PASS |
Russ Owen
|
|
|
Added by Inspector: 407 On 1/24/2001 1:20:09 PM
|
INSP - Final | 9/29/1998 | 9/29/1998 | 9/29/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
INSP-Conference | 9/22/1998 | 9/22/1998 | 9/22/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF LEFT COPY OF C/N WITH BIRDIE MGR WITH REMAINING ITEM FO
|
Code Occupancy Approval | | | 7/2/1998 | | PASS |
|
|
|
ALL CONDITIONS OF DR52-97 COMPLETED, I SIGNED OFF FINAL OCCUPANCY AND RELEASED THE POSTED BOND.
|
INSP - Final | 6/11/1998 | 6/11/1998 | 6/11/1998 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - REINSP FAIL STILL NEED COPY OF NFPA 72 RECORD OF COMPLETION
|
INSP - Final | 4/21/1998 | 4/22/1998 | 4/22/1998 | A | PART |
|
|
|
still in fire testing mode ok for jtawney to initial card for me
|
INSP-Final Inspection | 4/21/1998 | 4/22/1998 | 4/22/1998 | A | PART |
Joe Tawney
|
|
|
04/22/98 406 - OK FOR TEMP OCC
|
Temporary occupancy | | | 4/22/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3594 issued 4-22-98 to Gem State Paper.
|
Code Occupancy Approval | | | 4/21/1998 | | PASS |
|
|
|
Posted bond for unfinished site work - sprinkler system, curbing, landscaping and mechanical screening at east of bldg. $22,716.00 (DR-52-97)
|
INSP-Final Inspection | 4/15/1998 | 4/15/1998 | 4/15/1998 | | FAIL |
|
|
|
FINAL FAIL ALARM SYST NOT READY EMERG LIGHTS EXIT LIGHTS BLDG ADDRESS PAINT AND LETTER CURBS
|
INSP - Final | 4/14/1998 | 4/15/1998 | 4/15/1998 | A | NR |
|
|
|
04/15/98 338 - other agencies not approved correction issued with phone
|
INSP-Sprinkler Rough-in/Hydro | 3/12/1998 | 3/12/1998 | 3/12/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND & ABOVE HYDRO TESTS OK ON REFLUSH OF UNDER
|
INSP - Energy code compliance | 3/5/1998 | 3/6/1998 | 3/6/1998 | A | PASS |
|
|
|
03/06/98 338 - made ok to cover insulation okken ###-####
|
INSP-Sprinkler Rough-in/Hydro | 3/4/1998 | 3/5/1998 | 3/5/1998 | P | PART |
Joe Tawney
|
|
|
03/05/98 406 - PLEASE MEET TROY AT 2:00--PAGER ###-#### OR OFFICE IS 887 OK ABOVE GRND HYDRO & ROUGH IN. UNDRGRND FAILED MUST REDO FLUSH WHEN RE
|
INSP-Supply line flush | 3/5/1998 | 3/5/1998 | 3/5/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND FLUSH GEM STATE PAPER
|
INSP - Framing/Rough-in | 2/6/1998 | 2/9/1998 | 2/9/1998 | A | PASS |
|
|
|
02/09/98 338 - ###-#### ken framing rough in--AFTER 9:00 made ok need to insulation prior to cover to check for draft stopping . contr. to reque final for the mis permit on theis project asap need sp insp reports asap
|
INSP - Framing/Rough-in | 12/20/1997 | 12/19/1997 | 12/19/1997 | | PART |
|
|
|
12/19/97 338 - this is to be a masonry inspection should be sp inspectio
|
INSP - Framing/Rough-in | 12/20/1997 | 12/19/1997 | 12/19/1997 | | PART |
|
|
|
12/19/97 338 - this is to be a masonry inspection should be sp inspectio
|
(F) Reprint permit | | | 11/21/1997 | | |
|
|
|
|
Plan assigned to (M_P) | 10/9/1997 | | 11/20/1997 | | PASS |
Mike Phillips
|
|
|
11/20/97 06:42:57 DAR - this action updated by action script from <<>> in Case No. BLD97-1943
|
Issue PAID IN FULL permit | | | 11/20/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/1997 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 11/20/1997 | | |
|
|
|
|
Print Occupancy Form | | | 11/20/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 11/19/1997 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/19/1997 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 11/18/1997 | | PEND |
|
|
|
Waiting for phone call about certificate of value for fire sprinklers.
|
Routing - FIRE | 10/31/1997 | | 11/4/1997 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 10/31/1997 | | FAIL |
|
|
|
NEED ADDITIONAL INFORMATION. REQUESTED ADDITIONAL STRUCTURAL DRAWINGS.
|
Telephone call | | | 10/31/1997 | | |
|
|
|
REQUESTED ADDITIONAL STRUCTURAL DETAILS AND CALCULATIONS. TALKED TO GERALD MARTINS.
|
Plan resubmittals received | | | 10/21/1997 | | |
|
|
|
ROUTED TO PW FOR ALLEY ACCESS APPROVAL
|
Routing - FIRE | 10/15/1997 | | 10/20/1997 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 10/20/1997 | | PASS |
|
|
|
RESUBS SENT TO P&Z. MIKE RETAINED MAIN SET OF PLANS. SIGNED OFF BY MARTY SANTOYA FILES WHICH REERENCE THIS PROJECT ARE DRH97-0052 PLANS GIVEN TO MIKE P. PACKAGE #1
|
Routing - PLANNING | 10/16/1997 | | 10/20/1997 | | PASS |
|
|
|
X-REF: DRH97-0052. APPROVED BY MGS.
|
Routing Off Site - A.C.H.D | 10/17/1997 | | 10/17/1997 | | PASS |
|
|
|
Received new plans and sent to ACHD for review returned and impact fees have been paid.
|
Plan resubmittals received | | | 10/16/1997 | | PASS |
|
|
|
RESUBS SENT OUT TO ACHD VIA RUSS HEPWORTH. MIKE P. HAS RETAINED MAIN SET OF PLANS. IMPACT FEE RECEIPT #97-1808
|
Plan Reviewer's activity | | | 10/15/1997 | | FAIL |
|
|
|
ROUTING TO FIRE DEPARTMENT.
|
Print Pending Permit.LaserJet4 | | | 10/15/1997 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 10/15/1997 | | |
|
|
|
REQUESTED RESUBMITTALS.
|
Routing - PLAN CHECK | 10/2/1997 | | 10/15/1997 | | |
|
|
|
|
Plan assigned to (RGG) | 7/24/1997 | | 10/9/1997 | | PASS |
|
|
|
|
90 day tracking............. | | 7/8/1997 | 10/6/1997 | | |
|
|
|
|
Routing - ELECTRICAL | 10/2/1997 | | 10/2/1997 | | PASS |
|
|
|
NO REVIEW FIELD VERIFY
|
Routing - FIRE | 9/29/1997 | | 10/1/1997 | | PEND |
|
|
|
10-01-97 APPROVED FOR GRADING ONLY
|
Routing - PLUMBING | 9/26/1997 | | 10/1/1997 | | PASS |
|
|
|
|
Routing - PLUMBING | 9/19/1997 | | 9/25/1997 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 9/16/1997 | | 9/19/1997 | | PASS |
|
|
|
|
Routing - PLANNING | 9/12/1997 | | 9/16/1997 | | PASS |
|
|
|
Approved by: MGS
|
Routing - PUBLIC WORKS | 9/3/1997 | | 9/11/1997 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN REVISION
|
Routing Off Site - A.C.H.D | 7/24/1997 | | 9/2/1997 | | PEND |
|
|
|
CONTATED RUSS HEPWORTH AT ###-#### TO TAKE PLANS OUT TO ACHD. RUSS IS LOCAL CONTACT PERSON. ACHD FEES NOT PAID.
|
Plan routing begun/NEW & ADDTN | | | 7/24/1997 | | PASS |
|
|
|
|
Routing - MECHANICAL | 7/24/1997 | | 7/24/1997 | | PASS |
|
|
|
NO REVIEW FIELD VERIFY
|
Plans ACCEPTED BY PLAN CHECK | | | 7/24/1997 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 7/8/1997 | | 7/24/1997 | | |
Marlene Southard
|
|
|
|
Received Certificate of Value | | | 7/10/1997 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 7/10/1997 | | HOLD |
|
|
|
CONTACTED TIM OF GEM STATE PAPER TO LET HIM KNOW I NEED DRAINAGE CALC. AND ENGINEERED DRAWINGS FROM VULCRAFT FOR THE MANUFACTURED ROOF SYSTEM. KMM
|
Application received | | | 7/8/1997 | | |
|
|
|
|