Fee Review-notes | 11/16/1998 | | 11/18/1998 | | |
|
|
|
|
INSP - Miscellaneous | 12/4/1997 | 12/5/1997 | 12/5/1997 | P | PASS |
Rick Jackson
|
|
|
THE ELECTRICAL CONTRACTOR REQUESTED YOU GO OUT TO TEST ALARM SYSTEM HE INSTALLED, PAT LASS IS ALSO GOING OUT TODAY TO CHECK WIRING OF ALARM--PLEASE MEET PAT LASS AT 1:30--FRONT OF SECURITY GATE-- alarms tested - passed
|
Issue PAID IN FULL permit | | | 10/24/1997 | | |
|
|
|
|
90 day tracking............. | | 7/10/1997 | 10/8/1997 | | PEND |
|
|
|
|
Received partial PAYMENT | | | 10/1/1997 | | FEES |
|
|
|
paid 542.28 plan check fee by journal entry6169602699515
|
Print Occupancy Form | | | 8/13/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/13/1997 | | |
|
|
|
|
Telephone call | | | 8/13/1997 | | |
|
|
|
CALLED LEFT MESSAGE
|
Plan assigned to (CJW) | 7/11/1997 | | 8/12/1997 | | PASS |
Carl Westfall
|
|
|
08/12/97 16:31:08 CJW - this action updated by action script from <<>> in Case No. BLD97-1971
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/12/1997 | | PASS |
|
|
|
|
Routing - FIRE | 8/7/1997 | | 8/11/1997 | | PASS |
|
|
|
|
Print permit w/o conditions | | | 8/6/1997 | | |
|
|
|
|
testing condition printout | | | 8/6/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 7/30/1997 | | PASS |
|
|
|
UBC plan check started July 30, 1997 and finished August 4, 1997. Drawings approved.
|
Plan routing begun/TENANTS | | | 7/11/1997 | | |
|
|
|
This plan to be reviewed by PLAN CHECK ONLY. STAMP PLANS TO FIELD VERIFY HVAC.
|
Plan assigned to (MYS) | 7/10/1997 | | 7/11/1997 | | |
Marlene Southard
|
|
|
|
Application received | | | 7/10/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 7/10/1997 | | | | PEND |
|
|
|
|
Routing - PLAN CHECK | 8/12/1997 | | | | |
|
|
|
|