INSP - Final | 2/20/1998 | 2/20/1998 | 2/20/1999 | P | NR |
Carl Dependahl
|
|
|
CANC PER CONT.
|
Letter of compliance | | | 5/26/1998 | | PASS |
|
|
|
Letter of Compliance #15056 issued 5-26-98.
|
INSP - Final | 5/14/1998 | 5/14/1998 | 5/14/1998 | P | PASS |
Carl Dependahl
|
|
|
###-#### ###-####pager c/n ok, card signed at site
|
INSP - Final | 5/7/1998 | 5/8/1998 | 5/8/1998 | P | FAIL |
Carl Dependahl
|
|
|
tony ###-####...keep c/n, will recall when ready, need fire
|
INSP - Final | 5/6/1998 | 5/7/1998 | 5/7/1998 | P | FAIL |
Carl Dependahl
|
|
|
tony...still need fire signature (signed 1 card for other permit) keep c/n
|
INSP-Final Inspection | 5/5/1998 | 5/6/1998 | 5/6/1998 | A | PASS |
Joe Tawney
|
|
|
05/06/98 406 - ###-#### REINSP OK FOR CERT OF COMPLETION
|
INSP - Foundation | 5/5/1998 | 5/6/1998 | 5/6/1998 | P | NH |
Wes Worcester
|
|
|
05/06/98 342 - ###-#### call no answer at this number
|
INSP - Final | 2/19/1998 | 2/20/1998 | 2/20/1998 | A | FAIL |
Carl Dependahl
|
|
|
02/20/98 340 - TONY ###-#### OR ###-####--HE WILL CALL TO SCHEDULE. NEED FIRE OK, WILL RESCHED.
|
INSP-Final Inspection | 2/19/1998 | 2/19/1998 | 2/19/1998 | P | PASS |
Joe Tawney
|
|
|
02/19/98 406 - TONY ###-#### OR ###-#### REINSP FOR FINAL OK FOR CERT OF COMPLETION
|
INSP-Final Inspection | 2/17/1998 | 2/17/1998 | 2/18/1998 | P | PASS |
Joe Tawney
|
|
|
02/17/98 406 - TONY ###-#### REINSP FOR FINAL OK FOR TEMP OCC ì
|
INSP - Final | 2/17/1998 | 2/17/1998 | 2/17/1998 | P | FAIL |
Carl Dependahl
|
|
|
TONY ###-####ba need other perm. sig's, firestops, speaker at corr lid?
|
INSP - Final | 2/12/1998 | 2/13/1998 | 2/13/1998 | P | NR |
Carl Dependahl
|
|
|
###-####
|
INSP-Final Inspection | 2/12/1998 | 2/13/1998 | 2/13/1998 | P | FAIL |
Joe Tawney
|
|
|
02/13/98 406 - ###-#### Tony FINAL FAIL STROBE SPACING IN CORRIDOR ì
|
INSP - Framing/Rough-in | 1/22/1998 | 1/22/1998 | 1/22/1998 | P | NR |
Carl Dependahl
|
|
|
waterfront \\###-####....not frame insp, carpentry only
|
INSP - Final | 1/8/1998 | 1/8/1998 | 1/8/1998 | P | NR |
Carl Dependahl
|
|
|
NEED OTHER OKS & FULL ACCESS
|
INSP - Final | 1/8/1998 | 1/8/1998 | 1/8/1998 | P | CANC |
Alan Hauser
|
|
|
01/08/98 350 - to be done by #340
|
INSP - Framing/Rough-in | 12/18/1997 | 12/19/1997 | 12/19/1997 | A | PART |
Tom Arcoraci
|
|
|
CEILING GRID grid ok pentrations sealed
|
INSP - Conference | 12/19/1997 | 12/19/1997 | 12/19/1997 | A | PASS |
Carl Dependahl
|
|
|
W/ BOB A.& TOM: CN ON SEISMIC OK AT GRID CLG AT CORR'S
|
INSP - Conference | 12/19/1997 | 12/18/1997 | 12/18/1997 | P | PASS |
Carl Dependahl
|
|
|
W/ BOB A: PLENUMS < 12" DO NOT NEED SEISMIC BRACE
|
INSP - Conference | 12/18/1997 | 12/18/1997 | 12/18/1997 | P | PASS |
Carl Dependahl
|
|
|
W/ CEILING INSTALLER RE C/N
|
INSP - Framing/Rough-in | 12/16/1997 | 12/17/1997 | 12/18/1997 | A | FAIL |
Carl Dependahl
|
|
|
12/18/97 340 - ceiling grid C/N, SEISMIC, FIRESTOP ABOVE CLG
|
INSP - Framing/Rough-in | 12/8/1997 | 12/9/1997 | 12/9/1997 | A | PASS |
Wes Worcester
|
|
|
12/09/97 342 - need ceiling grid inspection
|
INSP - Conference | 12/9/1997 | 12/9/1997 | 12/9/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 - approved 1 hr modification detail
|
INSP - Conference | 10/24/1997 | 10/24/1997 | 10/24/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 - need listed assy for electrical panel in corridor walls....2
|
INSP - Framing/Rough-in | 10/23/1997 | 10/24/1997 | 10/24/1997 | A | PART |
Wes Worcester
|
|
|
10/24/97 342 -
|
90 day tracking............. | | 7/21/1997 | 10/19/1997 | | |
|
|
|
|
INSP - Framing/Rough-in | 10/17/1997 | 10/16/1997 | 10/16/1997 | P | PART |
Wes Worcester
|
|
|
C/N, NEED DETAIL FOR 1 HR ASS'Y.OK TO CONTINUE GYP ON CORR. WALLS. 342 FOR 340.
|
INSP - Framing/Rough-in | 10/16/1997 | 10/16/1997 | 10/16/1997 | P | CANC |
Carl Dependahl
|
|
|
PREFER BEFORE 3:30. GAVE TO 342...
|
INSP - Framing/Rough-in | 10/16/1997 | 10/15/1997 | 10/15/1997 | P | FAIL |
Carl Dependahl
|
|
|
NO ACCESS, LEFT C/N...FASTEN GYP; $42 FEE NEXT TIME NO ACCESS. 340
|
INSP - Framing/Rough-in | 10/14/1997 | 10/15/1997 | 10/15/1997 | A | CANC |
Alan Hauser
|
|
|
10/15/97 350 - to be done by #408
|
INSP - Conference | 10/6/1997 | 10/6/1997 | 10/6/1997 | P | FAIL |
Wes Worcester
|
|
|
STEED PROJECT MGR STATED THIS WAS A V-1HR BLDG WITH SPRINKLER SUBSTITUTION...? THEY WERE NOT READY FOR A FRAME INSP AND HAVE NUMEROUS PENETRATIONS IN A VN BLDG
|
INSP - Framing/Rough-in | 10/6/1997 | 10/6/1997 | 10/6/1997 | P | NR |
Wes Worcester
|
|
|
NUMEROUS PENETRATIONS IN 1 HR CORRIDOR MEMBRANE WITH ROCKED COLUMNS, DUCT PENETRATIONS IN CEILING, CEILING NOT FRAMED COMPLETELY, NEED DETAILS FROM ARCHITECT FOR FIXES, VN BLDG
|
INSP - Framing/Rough-in | 10/1/1997 | 10/2/1997 | 10/1/1997 | A | PART |
Wes Worcester
|
|
|
|
INSP - Framing/Rough-in | 9/25/1997 | 9/25/1997 | 9/25/1997 | P | PASS |
Carl Dependahl
|
|
|
09/25/97 340 - go to back ask for rob; REQUESTED DETAIL FOR LOOBY AREA
|
INSP - Conference | 9/25/1997 | 9/25/1997 | 9/25/1997 | A | PASS |
Carl Dependahl
|
|
|
w/ ROB OF STEED CONST; WANTS DECISION REGARDING 1HR CONST AT NEW/ EXISTING CORRIDOR. TOLD HIM THAT I'D LOOK AT IT, BUT THAT HE NEEDS TO GET DETAIL FROM ARCH.
|
INSP - Conference | 9/23/1997 | 9/24/1997 | 9/24/1997 | A | NR |
Carl Dependahl
|
|
|
09/24/97 340 - NO ONE AT SITE, NO PH# OR CONTACT. WHAT DO THEY WANT??? L
|
Telephone call | | | 8/25/1997 | | |
|
|
|
CALLED WES PERMIT READY
|
(F) Reprint permit | | | 8/25/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/25/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/25/1997 | | |
|
|
|
|
Print Occupancy Form | | | 8/25/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/25/1997 | | PASS |
|
|
|
issue
|
Plan assigned to (PRP) | 7/23/1997 | | 8/21/1997 | | PASS |
|
|
|
Waterfront offices--core upgrade, Building B 08/21/97 13:39:11 PRP - this action updated by action script from <<>> in Case No. BLD97-2104
|
Routing - PLAN CHECK | 8/7/1997 | | 8/21/1997 | | PASS |
|
|
|
issued
|
Print Pending Permit.LaserJet4 | | | 8/21/1997 | | PASS |
|
|
|
files
|
Plan resubmittals received | | | 8/20/1997 | | PASS |
|
|
|
received two sets of revised plans for review, approve with red-lining, assemble and issue.
|
Routing - FIRE | 8/5/1997 | | 8/7/1997 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 8/4/1997 | | PEND |
|
|
|
reviewed plans and history, investigate location and address, correct address for appropriate location in structure and change all related documents. Prepare correction list and fax to Architect 8/5/97.
|
Plan resubmittals requested | 8/4/1997 | | 8/4/1997 | | |
|
|
|
|
Routing - PUBLIC WORKS | 7/23/1997 | | 7/28/1997 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 7/21/1997 | | 7/23/1997 | | |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 7/23/1997 | | |
|
|
|
This plan to be route to PUBLIC WORKS then back to PLAN CHECK and then sent to the FIRE DEPARTMENT.
|
Recd Pcfee & Taken To Pln CK | | | 7/21/1997 | | |
|
|
|
|
Application received | | | 7/21/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 7/28/1997 | | | | |
|
|
|
|