Permanent Occupancy | | 4/17/1998 | 4/17/1998 | | DONE |
|
|
|
|
INSP - Final | 4/17/1998 | 4/17/1998 | 4/17/1998 | P | PASS |
|
|
|
04/17/98 338 - SIGNED THE PERM COL OF THE OCC REQ CARD OK CATHY TO SIGN
|
Permanent occupancy | | | 4/17/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7224 issued 4-17-98 to Respond, Inc.
|
Temporary occupancy | | | 3/2/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3558 issued 3-2-98 to Respond, Inc.
|
INSP-Final Inspection | 2/25/1998 | 2/25/1998 | 2/25/1998 | P | PART |
Joe Tawney
|
|
|
02/25/98 406 - john ###-#### call 1st before coming to site fire life sa FINAL OK FOR TEMP OCC FIRE EXT TAGS RATED DOORS AND WINDOWS SEE PERRY
|
INSP - Final | 2/25/1998 | 2/25/1998 | 2/25/1998 | | PART |
|
|
|
02/25/98 338 - ok for cathy to sighn for me with achd no sign confirm an sigh-off this insp request was for fire insp
|
Code Occupancy Approval | | | 2/25/1998 | | PASS |
|
|
|
Will paint vent to match bldg. - complies w/DRH97-0100
|
INSP - Framing/Rough-in | 2/18/1998 | 2/19/1998 | 2/19/1998 | A | PASS |
|
|
|
02/19/98 338 - CEILING \RESPOND ###-#### madeok SCLG-OK SUSPENDED CEILING
|
INSP - Framing/Rough-in | 12/29/1997 | 12/30/1997 | 12/30/1997 | A | PASS |
|
|
|
12/30/97 338 - FRAM-OK FRAMING
|
INSP - Conference | 12/22/1997 | 12/22/1997 | 12/23/1997 | P | PASS |
Tom Arcoraci
|
|
|
12/22/97 408 -
|
INSP - Miscellaneous | 11/6/1997 | 11/7/1997 | 11/7/1997 | A | PART |
Tom Arcoraci
|
|
|
MASONARY SPECIAL INSPECTOR ON SITE
|
INSP - Miscellaneous | 11/3/1997 | 11/4/1997 | 11/5/1997 | P | CANC |
Jim Storey
|
|
|
11/04/97 301 - trans to tom a.ND INC.
|
INSP - Miscellaneous | 10/30/1997 | 10/31/1997 | 10/31/1997 | P | PART |
|
|
|
MASONARY MADE OK R-BAR PLACED WITH THE SP INSP APPROVAL FOR THE 5'-0" BOND BEAM ELEVATION
|
90 day tracking............. | | 8/1/1997 | 10/30/1997 | | |
|
|
|
|
INSP - Foundation | 10/15/1997 | 10/15/1997 | 10/15/1997 | A | PASS |
|
|
|
made ok with the sp insp approvel poureed before my insp I told the sp inspector that he does not have to accept anything other than the approved plans
|
(F) Reprint permit | | | 10/15/1997 | | |
|
|
|
|
INSP - Footings | 10/14/1997 | 10/14/1997 | 10/14/1997 | P | PASS |
|
|
|
JOHN CEL ###-#### made ok with sp insp approval worker stopped from stripping forms before the concrete was set up??? picked up permit at 8:15 a.m. insists on inspection at 11:30 a.m. amd pours w/o insp see note above.
|
Plan assigned to (M_P) | 8/27/1997 | | 10/14/1997 | | PASS |
Mike Phillips
|
|
|
10/14/97 08:13:44 KMM - this action updated by action script from <<>> in Case No. BLD97-2254
|
Issue PAID IN FULL permit | | | 10/14/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/14/1997 | | PASS |
|
|
|
|
Print Occupancy Form | | | 10/14/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/14/1997 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/13/1997 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 10/13/1997 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 10/7/1997 | | FAIL |
|
|
|
CLARIFICATION OF RESUBMITTAL ON STRUCTURAL CAL'S AND SHOWER. PHONED AND TALKED TO PHIL AND DISCUSSED CONCERNS.
|
Plan resubmittals received | | | 10/3/1997 | | |
|
|
|
|
Routing - FIRE | 9/9/1997 | | 9/26/1997 | | PASS |
|
|
|
PACKAGE #1 APPROVED FOR GRADING AND DRAINAGE PERMIT ONLY BY FLOYD VARLEY. 09-03-97 APPROVED FOR BUILDING PERMIT BY FLOYD VARLEY. 09-26-97
|
Print Pending Permit.LaserJet4 | | | 9/9/1997 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 9/9/1997 | | FAIL |
|
|
|
SENT CORRECTION NOTICE REQUESTING RESUBMITTALS. Follow up structural review will be done by plan reviewer in office.
|
Routing - PLAN CHECK | 8/26/1997 | | 9/9/1997 | | |
|
|
|
PACKAGE #1
|
Routing - PUBLIC WORKS | 8/29/1997 | | 9/4/1997 | | PASS |
|
|
|
PACKAGE #2
|
Plan assigned to (RGG) | 8/4/1997 | | 8/27/1997 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 8/8/1997 | | 8/26/1997 | | PASS |
|
|
|
PACKAGAE #1 NO REVIEW FIELD VERIFY PER JS.
|
Routing - PLANNING | 8/8/1997 | | 8/18/1997 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/4/1997 | | 8/18/1997 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO ATWOOD HINZMAN, AND JONES PACKAGE #3 Follow up review will be done by plan reviewer.
|
Routing Off Site - A.C.H.D | 8/4/1997 | | 8/14/1997 | | PASS |
|
|
|
PACKAGE #4 CONTACTED JON VANDERHOEF AT ###-#### TO TAKE PLANS OUT TO ACHD. NO IMPACT FEES DUE.
|
Routing - PUBLIC WORKS | 8/4/1997 | | 8/8/1997 | | FAIL |
|
|
|
PACKAGE #2 REQUIRES DRAINAGE PLAN.
|
Routing - PLUMBING | 8/4/1997 | | 8/7/1997 | | PASS |
|
|
|
PACKAGE #1
|
Plans ACCEPTED BY PLAN CHECK | | | 8/4/1997 | | PASS |
|
|
|
|
Received Certificate of Value | | | 8/4/1997 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/4/1997 | | PASS |
|
|
|
|
Routing - MECHANICAL | 8/4/1997 | | 8/4/1997 | | PASS |
|
|
|
PACKAGE #1 NO REVIEW FIELD VERIFY
|
Plan assigned to (MYS) | 8/1/1997 | | 8/4/1997 | | |
Marlene Southard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/1/1997 | | |
|
|
|
|
Application received | | | 8/1/1997 | | |
|
|
|
|