INSP-Final Inspection | 11/2/1998 | 11/3/1998 | 11/3/1998 | A | FAIL |
|
|
|
alarm plans not approved,detectors too close to hvac openings, doors on hold open without detectors, sprinkler missing from beauty shop, vert sidewall head pointe wrong way, occ load not posted. strobes not provided.
|
INSP - Final | 11/2/1998 | 11/3/1998 | 11/3/1998 | A | NR |
Carl Dependahl
|
|
|
###-#### JOEL...not at site, called.
|
INSP - Final | 10/29/1998 | 10/29/1998 | 10/29/1998 | P | NR |
Carl Dependahl
|
|
|
joel, will call, want 3-3:30 insp if possible. need fire/safety, unable to contact in pm for insp.
|
INSP - Framing/Rough-in | 10/19/1998 | 10/19/1998 | 10/19/1998 | P | PART |
Carl Dependahl
|
|
|
firestopping & 2hr wall at "patio" at kitchen...ok, framed up through roof, 2 layers gyp ok
|
INSP - Framing/Rough-in | 10/8/1998 | 10/8/1998 | 10/8/1998 | P | PART |
Carl Dependahl
|
|
|
dave ###-#### pager call before going so he can meet you 2hr wall at boiler room...fan at lid moved, replumbed, penetrations. ok
|
INSP - Framing/Rough-in | 9/8/1998 | 9/8/1998 | 9/8/1998 | P | PART |
Carl Dependahl
|
|
|
DAVE TERRELL...2hr wall thru roof at mech rm. 2 layers gyp ok...ok to cover & roof.
|
INSP - Framing/Rough-in | 9/3/1998 | 9/3/1998 | 9/3/1998 | P | NH |
Wes Worcester
|
|
|
09/03/98 342 - no job # 2pm apt and no one to be found. no one knew wher
|
INSP - Framing/Rough-in | 9/1/1998 | 9/1/1998 | 9/1/1998 | P | PART |
Carl Dependahl
|
|
|
DAVE CM COMPANY; 2hr wall adjacent to training & mech. rooms...framing complete to roof decking and to existing masonry; 1st layer rock installed at ext. portions. Need to firestop & repair existing masonry at mech rm...ok to add 2nd layer, will req. insp.
|
INSP - Framing/Rough-in | 8/27/1998 | 8/27/1998 | 8/27/1998 | P | FAIL |
Carl Dependahl
|
|
|
conf only w/ Steve Pavlick, proj. arch...gave c/n for resubmittal to clarify procedure at 2hr wall at boiler room.
|
INSP - Wall cover | 8/27/1998 | 8/27/1998 | 8/27/1998 | P | FAIL |
Carl Dependahl
|
|
|
call from Dave Terrel w/ CM CO...need exam of 2hr wall at room 236 ...chk'd occupancy separation/penetrations, met w/ plumber. Also chk'd roof/wall at adjacent 2hr...need complete to roof deck; requested resubmittal. C/n to cm co, copy to arch.
|
INSP - Framing/Rough-in | 8/24/1998 | 8/24/1998 | 8/24/1998 | A | NR |
Carl Dependahl
|
|
|
conf only; w/ Dan Stuart re contractors proposal at rm 236/ 2hr wall to roof deck.
|
INSP - Framing/Rough-in | 8/20/1998 | 8/20/1998 | 8/20/1998 | P | PART |
Carl Dependahl
|
|
|
nailing at 2hr wall...1st layer;adjacent to cafeteria.
|
INSP - Framing/Rough-in | 8/18/1998 | 8/19/1998 | 8/19/1998 | P | PART |
Carl Dependahl
|
|
|
meet w/ arch (Steve & ? of olsen) & cm co.(Jackie, proj. mgr) at 2:30...ok to cover 2hr wall adjacent to cafeteria; chk'd 2hr wall off kitchen area. asked arch to resubmit/clarify extent of existing "2hr walls". ok to field approve known assemblies. for any proposed changes...ok to field approve if known approved assembly used
|
INSP - Framing/Rough-in | 8/18/1998 | 8/18/1998 | 8/18/1998 | P | PART |
Carl Dependahl
|
|
|
dave no phone at site...ok to cover lid & wall at employee patio area
|
INSP - Framing/Rough-in | 8/18/1998 | 8/18/1998 | 8/18/1998 | A | NR |
Carl Dependahl
|
|
|
conf only; w/ Jackie, proj. mgr. for CM CO...wants to meet onsite w/ arch.
|
INSP - Framing/Rough-in | 8/17/1998 | 8/17/1998 | 8/17/1998 | P | PART |
Carl Dependahl
|
|
|
no phone #...employee patio area, drywall ok for 2hr wall/ 1hr lid; need clarification for protection of roof framing at opposite side (cafeteria). need to complete firestopping before cover at lid.
|
INSP - Wall cover | 8/11/1998 | 8/12/1998 | 8/12/1998 | A | CANC |
Wes Worcester
|
|
|
08/11/98 342 - fire wall jim ###-#### given to Carl
|
INSP - Framing/Rough-in | 8/11/1998 | 8/11/1998 | 8/11/1998 | A | NR |
Carl Dependahl
|
|
|
conf w/ Steve of Olsen Arch's re c/n of 8-10...need detail for penetrations; equivalent alternate const at 2hr wall ok so as to give contractor option.
|
INSP - Framing/Rough-in | 8/7/1998 | 8/10/1998 | 8/10/1998 | P | FAIL |
Carl Dependahl
|
|
|
nailing late pm levar ###-####...1st layer gyp ok at ext wall/lid at break room area. C/N ...need detail for penetration protection at 2hr. area sep. wall. Wall is framed, not cmu as per arch's detail
|
INSP - Framing/Rough-in | 8/7/1998 | 8/7/1998 | 8/7/1998 | P | NR |
Carl Dependahl
|
|
|
conf. only; rec'd add'l resubmittal re 2hr wall
|
INSP - Wall cover | 8/4/1998 | 8/5/1998 | 8/5/1998 | A | FAIL |
Wes Worcester
|
|
|
08/05/98 342 - give a write-up on the fire wall outside the kitchen need wall type at kitchen ###-####
|
INSP - Framing/Rough-in | 8/5/1998 | 8/5/1998 | 8/5/1998 | P | NR |
Carl Dependahl
|
|
|
discussed resub w/ wes; spoke w/ Joel of CM CO
|
INSP - Framing/Rough-in | 8/5/1998 | 8/5/1998 | 8/5/1998 | | PART |
Wes Worcester
|
|
|
/ / 342 -
|
INSP - Framing/Rough-in | 8/3/1998 | 8/4/1998 | 8/4/1998 | A | NR |
Wes Worcester
|
|
|
08/04/98 342 - ###-####
|
INSP - Framing/Rough-in | 7/6/1998 | 7/6/1998 | 7/6/1998 | P | PART |
Carl Dependahl
|
|
|
not insp, conf w/ c/m co...left msg for Joel Brown
|
INSP - Framing/Rough-in | 5/28/1998 | 5/28/1998 | 5/28/1998 | P | NR |
Carl Dependahl
|
|
|
resubmittal; work not completed.
|
INSP - Framing/Rough-in | 5/11/1998 | 5/11/1998 | 5/11/1998 | A | PART |
Carl Dependahl
|
|
|
not insp, conf. for resubmittal at 2 hr wall
|
INSP - Framing/Rough-in | 5/8/1998 | 5/8/1998 | 5/8/1998 | A | PART |
Carl Dependahl
|
|
|
NOT INSP, REC'D RESUBMITTAL; CONF W/ DAN STUART
|
INSP - Framing/Rough-in | 4/15/1998 | 4/15/1998 | 4/15/1998 | P | PART |
Carl Dependahl
|
|
|
1hr req's w/ Joel...not insp
|
INSP - Framing/Rough-in | 3/18/1998 | 3/18/1998 | 3/18/1998 | A | PART |
Carl Dependahl
|
|
|
not insp, conf. w/ cont re 1hr req's
|
INSP - Framing/Rough-in | 3/18/1998 | 3/17/1998 | 3/17/1998 | P | PART |
Carl Dependahl
|
|
|
TOOK FOR WES...OK TO COVER RESTROOM OFF MAIN CORRIDOR
|
INSP - Framing/Rough-in | 3/16/1998 | 3/17/1998 | 3/17/1998 | A | CANC |
Wes Worcester
|
|
|
03/17/98 342 - jay ###-####
|
INSP - Framing/Rough-in | 3/13/1998 | 3/12/1998 | 3/12/1998 | P | PART |
Carl Dependahl
|
|
|
conf w/ arch re fire doors, labels, etc
|
INSP - Framing/Rough-in | 3/10/1998 | 3/9/1998 | 3/9/1998 | P | PART |
Carl Dependahl
|
|
|
conf w/ arch, chk openings...
|
INSP - Framing/Rough-in | 3/6/1998 | 3/6/1998 | 3/6/1998 | A | PART |
Carl Dependahl
|
|
|
re exiting wire glass at corridors; chk w/ Dan S & Ron H; ok if not specifically called out to change opening...
|
INSP - Framing/Rough-in | 3/5/1998 | 3/5/1998 | 3/5/1998 | A | NR |
Carl Dependahl
|
|
|
discussed test/ cert report for door jambs w/ joel; will reinsp
|
INSP - Framing/Rough-in | 3/5/1998 | 3/5/1998 | 3/5/1998 | P | PART |
Carl Dependahl
|
|
|
WILL CALL FOR TIME; ok to cover restroom off corridor (central hall by dining & office
|
INSP - Framing/Rough-in | 3/4/1998 | 3/5/1998 | 3/5/1998 | A | CANC |
Wes Worcester
|
|
|
03/05/98 342 - JOEL WILL CALL YOU given to Carl ###-####
|
INSP - Framing/Rough-in | 3/4/1998 | 3/4/1998 | 3/4/1998 | A | NR |
Carl Dependahl
|
|
|
REC'D NON-COMPLYING REPORT ON DOORS FROM INTER-TEK (WARNOCK-HERSEY)...CALLED JOEL BROWN, WAITING FOR REPLY.
|
INSP - Framing/Rough-in | 2/11/1998 | 2/12/1998 | 2/12/1998 | P | FAIL |
Carl Dependahl
|
|
|
joel at samaritan; corridor wall, ducts, firestops. C/N, NEED GYP MEMBRANE THROUGHOUT...FIRESTOP ALL STRUCT BRG WALLS, FIREBLOCK WOOD FRAMING, ETC,
|
INSP - Framing/Rough-in | 2/13/1998 | 2/12/1998 | 2/12/1998 | P | PART |
Carl Dependahl
|
|
|
NOT FRAME, CONF W/ DAN S. & RON HILL RE PLAN REQ'S...FOR 1HR CONST
|
INSP - Wall cover | 2/12/1998 | 2/11/1998 | 2/11/1998 | P | NR |
Carl Dependahl
|
|
|
CONF W/ JOEL; NEED COMPLETE 1HR DETAILS...
|
INSP - Framing/Rough-in | 2/10/1998 | 2/10/1998 | 2/10/1998 | P | NR |
Carl Dependahl
|
|
|
joel ###-#### framing, NR, NEED COMPLETE DETAILING FOR 1HR CONST...FIRESTOPS, GYP ETC... NEED TO CHK W/ RON HILL IF SPRINKLER SUBSTITUTION USED,NOT INDICATED ON PLAN.
|
INSP - Conference | 1/23/1998 | 1/23/1998 | 1/23/1998 | A | PASS |
Carl Dependahl
|
|
|
w/ Joel re drinking fountain proposed change: need ADA reqs...alcove or wing walls or? also details of struct resub.
|
INSP - Carpentry | 1/22/1998 | 1/22/1998 | 1/22/1998 | P | PASS |
Carl Dependahl
|
|
|
got arch's detail & calcs from Ron Hill
|
Plan resubmittals received | | | 1/21/1998 | | |
|
|
|
RECEIVED 2 COPIS OF STRUCT. CALCS FOR HEADER AND ROOF SUPPORT DETAILS. ROUTED TO RON HILL
|
INSP - Carpentry | 1/21/1998 | 1/20/1998 | 1/20/1998 | P | PART |
Carl Dependahl
|
|
|
AREA B...OK TO COVER SOFFIT; NEED VERIFY ELEC RI
|
INSP - Framing/Rough-in | 1/16/1998 | 1/16/1998 | 1/16/1998 | P | PART |
Carl Dependahl
|
|
|
GOOD SAMARITAN JOEL BROWN ###-####\PARTIAL...CALLED JOEL, COULDN'T FIND ONSITE, NO RESPONSE. WORK AT ROOMSIDE OF AREA B LOOKED OK, LEFT NOTE
|
INSP - Conference | 1/12/1998 | 1/9/1998 | 1/9/1998 | P | PASS |
Carl Dependahl
|
|
|
W/ SUPT. RE INSP OK'S
|
INSP - Framing/Rough-in | 1/8/1998 | 1/8/1998 | 1/8/1998 | P | PART |
Carl Dependahl
|
|
|
AREA 2, NEED DETAIL FOR PROPOSED BEAM AT PARTITION(TO SUPPORT ROOF) OK TO COVER ROOMSIDE WALL ONLY, CHK FIRESTOPS, DAMPERS, ETC. AS NEEDED.
|
INSP - Conference | 1/2/1998 | 1/5/1998 | 1/5/1998 | A | PASS |
Tom Arcoraci
|
|
|
CONTRACTOR WILL MAKE FLOOR PLAN FOR INSPECTORS TO MARK OFF AREAS THAT WILL BE OK FOR COVER
|
Issue PAID IN FULL permit | | | 12/2/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/1/1997 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 12/1/1997 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 12/1/1997 | | PASS |
|
|
|
received FINAL CERT. OF VALUE, from Dennis Robinson President of the CM Company, called and verified that NO gas was being used in dentists office. Ready to issue permit for PHASE ONE of this project.
|
Print Occupancy Form | | | 12/1/1997 | | |
|
|
|
|
Telephone call | | | 12/1/1997 | | |
|
|
|
left message with secretary permit was ready and about refund.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/1/1997 | | PASS |
|
|
|
|
Plan assigned to (R_H) | 8/8/1997 | | 12/1/1997 | | PASS |
|
|
|
12/01/97 13:56:05 R_H - this action updated by action script from <<>> in Case No. BLD97-2259
|
Plan Reviewer's activity | | | 11/19/1997 | | PEND |
|
|
|
SPOKE WITH ROGER HARTMAN, HE HAS INDICATED THAT THE WALL THAT WAS TO BE CONSTRUCTED UNDER THE NON COMPLYING CANOPY WILL NOT BE CONSTRUCTED, AND THAT HE WILL SEND ME A LETTER STATING THIS. HE HAS INDICATED THAT THE CANOPY WILL BE REMOVED IN ANOTHER PHASE AS INDICATED IN LETTER ON FILE. I WILL ISSUE PERMIT WHEN I RECEIVE LETTER FROM ROGER.
|
90 day tracking............. | | 8/4/1997 | 11/2/1997 | | |
|
|
|
|
Routing - FIRE | 9/2/1997 | | 9/19/1997 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 9/8/1997 | | FAIL |
|
|
|
Talked to Roger Hartman about the required correction that I had sent to him about the area separation wall. Faxed him some more information about are separation walls.
|
Plan Reviewer's activity | | | 8/27/1997 | | FAIL |
|
|
|
Mailed correction list to Architect. Need more information. Routed to Fire department
|
Routing - PLUMBING | 8/13/1997 | | 8/14/1997 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/12/1997 | | 8/13/1997 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 8/8/1997 | | |
|
|
|
Route to PUBLIC WORKS, PLUMBING then back to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT.
|
Application received | | | 8/4/1997 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/4/1997 | | |
|
|
|
|
Plan assigned to (MYS) | 8/4/1997 | | 8/4/1997 | | |
Marlene Southard
|
|
|
|
Routing - PLAN CHECK | 9/22/1997 | | | | |
|
|
|
|
Routing - PLAN CHECK | 8/14/1997 | | | | |
|
|
|
|