Case Summary (BLD) | | | 5/22/2003 | | |
|
|
|
|
Letter of compliance | | | 11/18/1999 | | DONE |
|
|
|
Letter of Compliance #18183 issued 11-18-99.
|
BLD-Final | 11/4/1999 | 11/4/1999 | 11/4/1999 | P | PASS |
|
|
|
Ok for L/C
|
Code Occupancy Approval | | | 11/4/1999 | | DONE |
|
|
|
Meets compliance with DR-144-96
|
INSP - Final | 4/9/1999 | 4/9/1999 | 4/9/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR CERT OF COMPLETION ON SHELL
|
INSP-Conference | 4/1/1999 | 4/1/1999 | 4/1/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF W/DAVE TUCKER REG SIGN OFF OF PERMIT
|
Temporary occupancy | | | 12/22/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3762 issued 12-22-98 to the Sailfish Place Bldg.
|
INSP - Final | 12/21/1998 | 12/21/1998 | 12/21/1998 | | PART |
|
|
|
12/21/98 338 - c/n issued need fire; ele; p/z; and mech perm sign-off
|
INSP - Final | 12/18/1998 | 12/18/1998 | 12/18/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR TEMP OCC CONTROL VLV SUPR, ACCELERATOR
|
INSP-Final Inspection | 12/17/1998 | 12/17/1998 | 12/17/1998 | P | FAIL |
Joe Tawney
|
|
|
12/17/98 406 - dwayne- ###-#### fn fire REINSP FAIL ACCEL FAILED DUCT DET CONTROL VLV MONITORING
|
Fee Review-notes | 7/14/1998 | | 12/15/1998 | | |
|
|
|
|
INSP-Final Inspection | 12/4/1998 | 12/7/1998 | 12/7/1998 | P | FAIL |
Joe Tawney
|
|
|
12/07/98 406 - dwayne ###-#### fn fire per joe 1? REINSP FAIL SPKLR SYSTEM DUCT DET
|
INSP - Final | 12/2/1998 | 12/4/1998 | 12/4/1998 | A | FAIL |
|
|
|
12/04/98 338 - OTHER AGENCIES NOT APPROVED
|
INSP - Final | 12/3/1998 | 12/3/1998 | 12/3/1998 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - FINAL FAIL SPKLR SYSTEM NOT READY FOR TEST
|
PubWorks Occupancy Approval | | | 11/13/1998 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 11/13/98. R.Cummings
|
Print Occupancy Form | | | 11/12/1998 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 10/9/1998 | 10/12/1998 | 10/12/1998 | P | PART |
Joe Tawney
|
|
|
10/12/98 406 - brian ###-#### r-in spr insp-early if possible OK ROUGH IN OF SHELL & 1ST FLR OK HYDRO TEST 1ST FLR
|
INSP-Sprinkler Rough-in/Hydro | 6/3/1998 | 6/3/1998 | 6/3/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TEST OF FDC
|
INSP-Sprinkler Rough-in/Hydro | 5/29/1998 | 5/29/1998 | 5/29/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TEST EXCEPT FDC PIPING
|
INSP-Supply line flush | 5/29/1998 | 5/29/1998 | 5/29/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND FLUSH
|
INSP - Framing/Rough-in | 3/30/1998 | 3/30/1998 | 3/31/1998 | P | PASS |
Jim Storey
|
|
|
03/30/98 301 - RF -OK ROOF NAILING
|
INSP - Framing/Rough-in | 3/18/1998 | 3/18/1998 | 3/18/1998 | P | PART |
|
|
|
03/18/98 338 - nailing robbie edmans -nails in deck penetrate to far int
|
INSP - Framing/Rough-in | 3/18/1998 | 3/18/1998 | 3/18/1998 | | PASS |
|
|
|
/ / 338 - with cornell larson, will get nailing problems resolved and,
|
INSP - Framing/Rough-in | 1/26/1998 | 1/26/1998 | 1/26/1998 | P | PART |
|
|
|
01/26/98 338 - robert ###-#### made ok r-bar placed ok to pour with sp i to re-check panel # 5
|
INSP - Foundation | 1/6/1998 | 1/7/1998 | 1/7/1998 | A | PASS |
|
|
|
01/07/98 338 - made ok with sp insp approval
|
INSP - Footings | 12/29/1997 | 12/30/1997 | 12/30/1997 | A | PASS |
|
|
|
12/30/97 338 - made ok with sp insp papproval
|
INSP - Footings | 12/17/1997 | 12/17/1997 | 12/18/1997 | P | PASS |
|
|
|
12/17/97 338 - made ok with the ok from the special inspector
|
INSP - Footings | 12/16/1997 | 12/16/1997 | 12/16/1997 | P | CANC |
Dave Lightfoot
|
|
|
12/16/97 337 -
|
INSP - Framing/Rough-in | 12/12/1997 | 12/15/1997 | 12/15/1997 | A | CANC |
|
|
|
12/15/97 338 - this is to be concrete reinforcing for tilt up walls
|
INSP - Framing/Rough-in | 12/12/1997 | 12/15/1997 | 12/15/1997 | A | CANC |
|
|
|
12/15/97 338 - this is to be a reinforcing inspection for tilt up walls
|
INSP - Footings | 11/10/1997 | 11/12/1997 | 11/12/1997 | A | PART |
|
|
|
center col forms only ok after sp insp approval
|
90 day tracking............. | | 8/14/1997 | 11/12/1997 | | |
|
|
|
|
FEE REVIEW-NOTES | | | 10/30/1997 | | FEES |
|
|
|
OVERPAYMENT ON PLAN CHECK 213.71 REFUND
|
(F) Reprint permit | | | 10/27/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/24/1997 | | |
|
|
|
|
Telephone call | | | 10/23/1997 | | |
|
|
|
called dave tucker
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/1997 | | PASS |
|
|
|
|
Print Occupancy Form | | | 10/23/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/23/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 10/20/1997 | | 10/23/1997 | | PASS |
|
|
|
package #1
|
Plan assigned to (JCM) | 10/9/1997 | | 10/23/1997 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 9/15/1997 | | 10/23/1997 | | PASS |
|
|
|
PACKAGE #3 RESUB FROM ENGINEERING.
|
Routing - FIRE | 10/14/1997 | | 10/20/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLAN CHECK | 10/3/1997 | | 10/14/1997 | | |
|
|
|
PACKAGE #1
|
Plan resubmittals requested | | | 10/13/1997 | | PEND |
|
|
|
CORRECTION LIST SENT TO THE ARCHITECT (CORNEL LARSON) FOR REQUESTED REVISIONS.
|
Plan assigned to (RGG) | 8/18/1997 | | 10/9/1997 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 8/18/1997 | | 10/1/1997 | | PASS |
|
|
|
PACKAGE #2 CONTACTED CORNEL LARSON AT ###-#### TO TAKE PLANS OUT TO ACHD fees paid IMPACT FEE CERTIFICATE #97-5033
|
Routing - FIRE | 9/12/1997 | | 9/23/1997 | | PEND |
|
|
|
PACKAGE #1 9-12-97 for grading.
|
Routing - ELECTRICAL | 9/23/1997 | | 9/23/1997 | | PASS |
|
|
|
PACKAGE #1 FIELD VERIFY.
|
Routing Off Site - STRUCTURAL | 9/11/1997 | | 9/15/1997 | | PASS |
|
|
|
RESUBS SENT TO STRUCTURAL ENGINEER. RESUBS RETURNED FROM STRUCT. GAVE TO PC ( BEHIND BOB'S DOOR ) PLAN RESUBMITTALS APPROVED - SEE LETTER IN FILE FROM ATWOOD-HINZMAN-JONES (RILEY MAHAFFEY)
|
Routing - PLUMBING | 9/9/1997 | | 9/11/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLANNING | 9/3/1997 | | 9/5/1997 | | PASS |
|
|
|
PACKAGE #1 X-REF: DR-144-96. NOTE: BRIAN JORGENSON (FORESTRY) VERBALLY AGREED TO THE WAIVER OF RECOMMENDATION D OF HIS STAFF REPORT DATED 12/24/96. APPROVED BY SB.
|
Routing - PUBLIC WORKS | 8/18/1997 | | 9/3/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing Off Site - STRUCTURAL | 8/18/1997 | | 8/26/1997 | | PEND |
|
|
|
PACKAGE #3 CONTACTED PDQ TO TAKE PLANS OUT TO ATWOOD, HINZMAND, JONES PACKAGE #3 RETURNED FROM AHJ, WITH COMMENTS.
|
Plans ACCEPTED BY PLAN CHECK | | | 8/18/1997 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/18/1997 | | PASS |
|
|
|
|
Routing - MECHANICAL | 8/18/1997 | | 8/18/1997 | | PASS |
|
|
|
PACKAGE #1 NO REVIEW FIELD VERIFY.
|
Plan assigned to (MYS) | 8/14/1997 | | 8/15/1997 | | |
Marlene Southard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/14/1997 | | |
|
|
|
|
Application received | | | 8/14/1997 | | |
|
|
|
|