Permanent occupancy | | | 6/17/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7794 issued 6-17-99 to Chuck A Rama.
|
INSP - Final | 6/15/1999 | 6/16/1999 | 6/16/1999 | A | PASS |
|
|
|
06/16/99 338 - signed the occ req card
|
Permanent Occupancy | | 6/15/1999 | 6/15/1999 | | DONE |
|
|
|
|
CHANGE STATUS TO (I) | | | 4/6/1999 | | |
|
|
|
|
Receive PAYMENT IN FULL | | | 3/18/1999 | | |
|
|
|
|
(F) Reprint permit | | | 2/25/1999 | | |
|
|
|
|
(F) Reprint permit | | | 2/18/1999 | | |
|
|
|
|
INSP - Final | 9/29/1998 | 9/29/1998 | 9/29/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
INSP-Final Inspection | 8/26/1998 | 8/31/1998 | 8/31/1998 | A | FAIL |
Joe Tawney
|
|
|
08/31/98 406 - james ###-#### REINSP FAIL NFPA 72 - FAX OF ALARM SIGNALS - AIR BALANCE REPORT
|
INSP - Final | 7/6/1998 | 7/6/1998 | 7/6/1998 | P | PART |
|
|
|
07/06/98 338 - final chuck a rama/ ###-#### signed the temp col of the o
|
INSP-Final Inspection | 7/2/1998 | 7/6/1998 | 7/6/1998 | A | PART |
Joe Tawney
|
|
|
07/06/98 406 - JAMES ###-#### OK FOR TEMP OCC
|
INSP - Final | 7/2/1998 | 7/6/1998 | 7/6/1998 | A | NR |
|
|
|
07/05/98 338 - JAMES ###-#### NEED TO INSTALL LANDING AT THE WEST EMERGE
|
INSP-Final Inspection | 7/2/1998 | 7/2/1998 | 7/6/1998 | P | FAIL |
Joe Tawney
|
|
|
07/02/98 406 - james ###-#### FINAL FAIL ANSUL SYSTEM ALARM SYSTEM EXIT DOORS
|
Temporary occupancy | | | 7/6/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3650 issued 7-6-9 to Chuck A Rama.
|
INSP-Final Inspection | 7/1/1998 | 7/2/1998 | 7/2/1998 | A | FAIL |
Joe Tawney
|
|
|
07/02/98 406 - Tracy ###-#### FINAL FAIL
|
INSP - Final | 6/26/1998 | 6/26/1998 | 6/26/1998 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - SPKLR FINAL FAIL OBSTRUCTION MISSING HEAD TAMPER SWITCHES
|
INSP-Sprinkler Rough-in/Hydro | 6/15/1998 | 6/16/1998 | 6/16/1998 | P | PART |
Joe Tawney
|
|
|
06/16/98 406 - AT 1 P.M. ###-#### TRACY OK ON ABOVE GROUND HYDRO TEST
|
INSP - Wall cover | 6/4/1998 | 6/5/1998 | 6/5/1998 | P | PART |
|
|
|
06/05/98 338 - part ok to cover
|
INSP-Sprinkler Rough-in/Hydro | 6/5/1998 | 6/5/1998 | 6/5/1998 | P | PART |
Joe Tawney
|
|
|
06/05/98 406 - ###-#### said you were meeting him at 2 SPKLR ROUGH IN OK TO COVER SPKLR PROTECTION PROVIDED FOR ALL COMB CONSTR
|
INSP-Conference | 6/3/1998 | 6/3/1998 | 6/3/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF ON LOCATION OF SMOKE DETECTORS AND OUTSIDE ALARM BELL
|
INSP - Wall cover | 6/1/1998 | 6/2/1998 | 6/2/1998 | P | CANC |
|
|
|
06/02/98 338 - not ready as fire ins has failed will recall for thursday
|
INSP-Sprinkler Rough-in/Hydro | 6/1/1998 | 6/1/1998 | 6/1/1998 | P | FAIL |
Joe Tawney
|
|
|
06/01/98 406 - 1 p.m. ###-#### tracy said he talked with you ROUGH IN INSP PROTECTION NEEDED FOR ALL EXPOSED COMBUSTIBLE CONSTRUCTION
|
INSP-Final Inspection | 5/6/1998 | 5/6/1998 | 5/6/1998 | P | PART |
Joe Tawney
|
|
|
05/06/98 406 - tracy ###-#### ROUGH IN OF ROOM ON NE CORNER OK TO COVER ì
|
INSP - Wall cover | 5/4/1998 | 5/5/1998 | 5/5/1998 | A | PART |
|
|
|
05/05/98 338 - made ok to cover 1-side only
|
INSP - Wall cover | 5/5/1998 | 5/5/1998 | 5/5/1998 | | PART |
|
|
|
05/05/98 338 - UPPER LEVEL MADE OK
|
INSP-Sprinkler Rough-in/Hydro | 4/30/1998 | 5/1/1998 | 5/1/1998 | A | PART |
Joe Tawney
|
|
|
05/01/98 406 - reinspection tracy ###-#### OK ON ROUGH IN OF KITCHEN AREA
|
INSP - Framing/Rough-in | 4/30/1998 | 5/1/1998 | 5/1/1998 | P | NR |
|
|
|
Scheduled by Hello!. Contact phone is [6580016].
|
INSP-Conference | 4/22/1998 | 4/23/1998 | 4/23/1998 | A | PART |
Joe Tawney
|
|
|
04/23/98 406 - ###-####/JAMES - CONFERENCE. CONF ON CONCEALED COMBUSTABLE SPACES
|
INSP - Framing/Rough-in | 4/16/1998 | 4/17/1998 | 4/17/1998 | A | PART |
|
|
|
04/17/98 338 - ok to cover the ext walls and start the ceilings behind t
|
INSP - Framing/Rough-in | 4/15/1998 | 4/16/1998 | 4/16/1998 | A | CANC |
|
|
|
Scheduled by Hello!. Contact phone is [6580016]. Cancelled by Hello! (Last update by [HLO]). Contact: [6580016].
|
INSP - Framing/Rough-in | 4/13/1998 | 4/14/1998 | 4/14/1998 | A | PART |
|
|
|
04/14/98 338 - MET WITH SUPER MIKE OTTO AND DISCUSSED THE PLANS AND REQU
|
INSP-Conference | 4/14/1998 | 4/14/1998 | 4/14/1998 | | PART |
|
|
|
CONF ON ALARM SYSTEM WITH RALPH OF SECURITY GROUP
|
INSP - Framing/Rough-in | 4/9/1998 | 4/9/1998 | 4/9/1998 | P | PART |
|
|
|
04/09/98 338 - conference handled on the phone
|
INSP-Supply line flush | 4/7/1998 | 4/7/1998 | 4/7/1998 | P | PART |
Joe Tawney
|
|
|
PAT ###-#### PAGER OK ON UNDERGROUND FLUSH
|
INSP - Framing/Rough-in | 4/10/1998 | 4/13/1998 | 4/3/1998 | A | PART |
|
|
|
|
INSP - Framing/Rough-in | 3/30/1998 | 3/30/1998 | 3/31/1998 | P | PART |
|
|
|
03/30/98 333 - ok to cover tjis at south half ceiling only
|
INSP-Sprinkler Rough-in/Hydro | 3/16/1998 | 3/16/1998 | 3/16/1998 | P | FAIL |
Joe Tawney
|
|
|
03/16/98 406 - CHUCK A RAMA--MICK WILL CALL TO SCHEDULE--###-#### UNDERGROUND FLUSH FAIL VLV CLOSED IN UNDERGROUND UNITED WATER TO CHECK
|
INSP - Framing/Rough-in | 2/18/1998 | 2/19/1998 | 2/19/1998 | A | PART |
|
|
|
02/19/98 338 - this is a masonry insp ok to pour this lift r-bar in plac inspected
|
INSP - Foundation | 12/20/1997 | 12/19/1997 | 12/19/1997 | | PASS |
|
|
|
12/19/97 338 - made ok with sp insp approval
|
INSP - Foundation | 12/20/1997 | 12/19/1997 | 12/19/1997 | | PASS |
|
|
|
12/19/97 338 - made ok with sp insp approval
|
INSP - Footings | 12/15/1997 | 12/15/1997 | 12/15/1997 | | PART |
|
|
|
/ / 338 - footing ok to pour the perimeter except 100 lf in the north concrete truck access. special inspector to be on site for the entire p
|
INSP - Foundation | 12/12/1997 | 12/15/1997 | 12/15/1997 | P | CANC |
|
|
|
12/15/97 338 - madeok forthe footing insp only at 16:50:28.
|
(F) Reprint permit | | | 12/10/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 12/8/1997 | | |
|
|
|
|
Plan assigned to (M_O) | 10/23/1997 | | 12/5/1997 | | PASS |
|
|
|
|
Print Occupancy Form | | | 12/5/1997 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/5/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/1997 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 11/25/1997 | | 12/3/1997 | | PASS |
|
|
|
RESUBMITTALS SENT TO ATWOOD-HINZMAN-JONES FOR REVIEW. MO
|
Routing - PLAN CHECK | 11/24/1997 | | 11/25/1997 | | PASS |
|
|
|
|
Plan resubmittals received | | | 11/24/1997 | | PEND |
|
|
|
REVISED PLANS FOR STRUCTURAL AND BUILDING CORRECTIONS RECEIVED. MO
|
90 day tracking............. | | 8/19/1997 | 11/17/1997 | | PEND |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/28/1997 | | 11/6/1997 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE PLANS OUT TO ATWOOD HINZMAN JONES
|
Routing - FIRE | 10/28/1997 | | 10/29/1997 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 10/28/1997 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MO
|
Routing - PLAN CHECK | 10/23/1997 | | 10/27/1997 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MO
|
Plan resubmittals requested | | | 10/23/1997 | | |
|
|
|
BILL WAITE OF RON THURBER'S OFFICE CONTACTED REGARDING STRUCTURAL CALCS AND THE SPEC BOOKS WHICH WERE NOT PROVIDED WITH THE SUBMITTAL DOCUMENTS. 10-23-97 MO.
|
Plan assigned to (RGG) | 8/25/1997 | | 10/23/1997 | | PASS |
|
|
|
|
Routing - PLANNING | 10/21/1997 | | 10/21/1997 | | PASS |
|
|
|
X-REF: DRH97-0045. APPROVED BY MGS.
|
Routing - ELECTRICAL | 10/9/1997 | | 10/13/1997 | | PASS |
|
|
|
SITE DRAWING WITH UTILITY TRANS & LOCATION OF SERVICE LOCATION OF MAIN SERVICE RESUBMITLES TO BE GIVEN TO FIELD ELECT. INSP AT TIME OF WORK START.
|
Routing - PLANNING | 10/8/1997 | | 10/9/1997 | | FAIL |
|
|
|
X-REF: DRH97-0045. NEED REVISED LANDSCAPE PLAN, AND WINDOW DESIGN DOES NOT COMPLY WITH APPROVED PLANS, I.E. MUNTINS ARE REQUIRED. REVIEWED BY MGS.
|
Routing - PLUMBING | 10/7/1997 | | 10/8/1997 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/24/1997 | | 10/7/1997 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 9/22/1997 | | 9/23/1997 | | PASS |
|
|
|
CONTACTED GARY BECK AT ###-#### TO TAKE PLANS OUT TO CDH WHEN PLANS ARE DONE AT ACHD.
|
Plan routing begun/NEW & ADDTN | | | 9/22/1997 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 8/27/1997 | | 9/22/1997 | | PEND |
|
|
|
CONTACTED GARY BECK AT ###-#### TO TAKE PLANS OUT TO ACHD. WHEN DONE AT ACHD GARY IS TO TAKE PLANS TO CDH. FEES NOT PAID. PLANS WERE APPROVED BUT NOT SIGNED OFF. CALLED MARCUS GREEN OF THIS NEED. 10-21-97 SPOKE WITH BILL WAITE. HE WOULD LIKE A CALL WHEN PLANS ARE BACK FROM P&Z SO HE CAN TAKE PLANS OUT TO ACHD TO BE SIGNED OFF. HIS #IS ###-####
|
Plans ACCEPTED BY PLAN CHECK | | | 8/27/1997 | | PASS |
|
|
|
ACCEPTED ACHD PACKAGE FOR ROUTING.
|
Routing - MECHANICAL | 8/27/1997 | | 8/27/1997 | | PASS |
|
|
|
NO REVIEW FIELD VERIFY.
|
Plans ACCEPTED BY PLAN CHECK | | | 8/25/1997 | | HOLD |
|
|
|
ARCH. SHEETS AND STRUCT. SHEETS NEED TO BE STAMPED AND SIGNED BY ARCH. CONTACTED GARY BECK AT ###-#### TO ADDRESS THIS ISSUE.
|
Plan assigned to (MYS) | 8/19/1997 | | 8/25/1997 | | |
Marlene Southard
|
|
|
|
Received Certificate of Value | | | 8/25/1997 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/25/1997 | | HOLD |
|
|
|
SEE ACTION OO7 HOLD
|
Recd Pcfee & Taken To Pln CK | | | 8/19/1997 | | |
|
|
|
|
Application received | | | 8/19/1997 | | |
|
|
|
|