Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD97-02465
StatusFinaled
Name STEVE HOSAC
Site Address 1211 W MYRTLE ST
Project NamePIONEER PLAZA II
Customer Number 
ePlanReviewNo
Description
PIONEER PLAZA PHASE 2 * (SHELL AND CORE ONLY) TO CONSTRUCT A NEW 3-STORY, TYPE II ONE-HOUR, FULLY FIRE SPRINKLERED, MULTI TENANT SHELL OFFICE BUILDING. WORK TO INCLUDE THE INSTALLATION OF THE TWO STAIR ENCLOSURES, RESTROOMS ON EACH FLOOR AND AN ELEVATOR TO EACH FLOOR, THE INSTALLATION OF THE CORE MECHANICAL SYSTEM. THE INSTALLATION OF THE FIRE SPRINKLER SYSTEM IS BEING USED FOR ONE-HOUR SUBSTITUTION. ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED COMMENT LIST, CABO/ANSI 117.1 AND THE 1994 EDITIN OF THE UBC. WORK ON SITE TO INCLUDE LANDSCAPING, PAVING SITE UTILITIES. THIS PERMIT DOES NOT ALLOW FOR OCCUPANCY OF THE STRUCTURE. SEPARATE PERMITS AND CERTIFICATE OF OCCUPANCIES MUST BE OBTAINED FOR EACH SEPARATE TENANT SPACE TO BE FINISHED. THE ACCUMULTIVE OCCUPANT LOAD FOR EACH FLOOR CAN NOT EXCEED 100. MJP (P.C.#543-97) DR#44-97 CU-34-97 GRADING PERMIT BLD97-2723 ISSUED 10-08-97 FOUNDATION PERMIT ISSUED, PERMIT NUMBER MIS97-0213 ON 10/16/97.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  6/4/2004  
PRINT ACTIONS  8/29/2000 DONE
Letter of compliance  4/18/2000 DONE
Letter of Compliance #18481 issued 4-18-00.
BLD-Final9/27/19999/27/19999/27/1999APASS
Details
made ok for l/c
INSP - Final6/23/19996/23/19996/23/1999PFAIL
Details
06/23/99 338 - achd not approved
INSP - Framing/Rough-in6/14/19996/15/19996/15/1999AFAIL
Details
06/15/99 338 - need to complete assys as per details
INSP - Framing/Rough-in6/15/19996/15/19996/15/1999 FAIL
Details
06/15/99 338 - need fix on the horiz. beam at the east prop line wall
INSP - Final6/7/19996/7/19996/7/1999PFAIL
Details
06/07/99 338 - MUST FOLLOW ASSEMBLIES SUBMITTED SLOPPY WORK
INSP - Final6/2/19996/2/19996/2/1999 FAIL
Details
06/02/99 338 - cancelled will reschedule
INSP-Final Inspection5/26/19995/27/19995/27/1999PPASS
DetailsRick Jackson
2pm Doug ###-#### occ approved
INSP - Framing/Rough-in5/14/19995/17/19995/17/1999PFAIL
Details
conference/ Joe ###-#### c/n on the final need assy for the wall to floor deck at the stair rated walls and the redo of the fire proofing of the east I beam at each level this work is to be done per the plan approved by 338 in its complete detail.
SUPER- Supervisor's review5/13/19995/13/19995/13/1999
penitrations not sealed on back side of enclosure wall also problems with alarm test= rick
INSP - Final5/11/19995/12/19995/12/1999PFAIL
Details
05/12/99 338 - other agencies not approved
INSP-Final Inspection5/11/19995/12/19995/12/1999PFAIL
DetailsRick Jackson
###-#### KEN//FIRE & LIFE SAFETY alarm plans not approved; access road not complete; elevator not working; address; tampers not wired properly
SUPER- Supervisor's review5/10/19995/10/19995/10/1999
shell not quite completed interior walls not completed
SUPER- Supervisor's review5/4/19995/4/19995/4/1999
completing ephis system on exterire
INSP - Framing/Rough-in4/21/19994/21/19994/30/1999PPART
Details
04/26/99 338 - ok to drop in the tiles
SUPER- Supervisor's review4/16/19994/16/19994/16/1999
finish still in progress perry working on handrail details
SUPER- Supervisor's review4/1/19994/1/19994/1/1999
exterior not done. very slow. work is ok.
INSP-Conference3/29/19993/30/19993/30/1999APART
Details
03/30/99 338 - made ok for conf
INSP - Framing/Rough-in2/18/19992/19/19992/19/1999APART
DetailsJim Storey
02/19/99 301 - 2nd and 3hrd floor line east wall ok.
INSP - Framing/Rough-in2/15/19992/16/19992/16/1999APART
Details
02/16/99 338 - made ok to cover ext walls only
INSP - Energy code compliance2/2/19992/2/19992/2/1999PPART
Details
02/02/99 338 - madeok for the details of the heater protection and the v
INSP - Framing/Rough-in2/1/19992/1/19992/1/1999PPART
Details
02/01/99 338 - made ok to cover the rest room areas only
INSP - Framing/Rough-in1/28/19991/29/19991/29/1999ANR
DetailsCarl Dependahl
01/29/99 340 - KEN SKAGGS ###-#### FR INSP unable to contact
SUPER- Supervisor's review1/27/19991/27/19991/27/1999
firestopping floor at curtain walls with thermafiber. ok once submitted to parry p
INSP - Framing/Rough-in1/25/19991/25/19991/25/1999PPART
Details
MADE OK FO TPOUR
SUPER- Supervisor's review1/8/19991/8/19991/8/1999
ephis system installed glazing will be starting
INSP-Conference1/7/19991/7/19991/7/1999APART
DetailsRick Jackson
informed general contractor that the alarm plans have not been submitted and approved. electrical contractor was calling simplex as I was leaving...
SUPER- Supervisor's review12/18/199812/18/199812/18/1998
encloser of building on going. proceeding per plan ok
Fee Review-notes8/3/1998 12/15/1998
SUPER- Supervisor's review11/30/199811/24/199811/24/1998
seal on curtain walls in progress ok
SUPER- Supervisor's review11/20/199811/20/199811/20/1998
floor separation at curtain walls to be maintained at same hourly rating as the floor. continuout to outside wall.
INSP - Framing/Rough-in11/18/199811/19/199811/19/1998APART
Details
11/19/98 333 - resub on efis system
SUPER- Supervisor's review11/13/199811/13/199811/13/1998
floor protection to extend to exterior wall. Type II n building. ok.
SUPER- Supervisor's review11/12/199811/12/199811/12/1998
highstrenth bolting completed. special inspection ok.
INSP - Framing/Rough-in11/12/199811/12/199811/12/1998APART
Details
11/12/98 333 - north wall efis exterior only ok
INSP-Conference10/27/199810/27/199810/27/1998APART
DetailsRick Jackson
pre-con meeting with Kim M. Sprinkler plans from State FM not on site and alarm plans not approved - requested both from K2 contractors
INSP - Framing/Rough-in10/22/199810/27/199810/27/1998APART
Details
10/27/98 333 - pre con
SUPER- Supervisor's review10/21/199810/21/199810/21/1998
one and onehalf inches clearance required from the wall
INSP - Framing/Rough-in10/20/199810/21/199810/21/1998PFAIL
Details
10/21/98 333 - conference on handrails clearances to wall not correct
INSP - Concrete9/23/19989/24/19989/24/1998APASS
Details
09/24/98 333 - north half slab ok
Issue PAID IN FULL permit  9/14/1998
Plan assigned to (M_P)9/22/1997 9/2/1998 PASS
DetailsMike Phillips
09/02/98 14:12:32 M_P - this action updated by action script from <<>> in Case No. BLD97-2465
Print Pending Permit.LaserJet4  9/2/1998 PASS
Print Occupancy Form  9/2/1998
PLANS/APPL TAKEN TO FRONT DESK  9/2/1998 PASS
Plan Reviewer's activity  9/2/1998 PASS
Inspection Record Card- Bld  9/2/1998
Plan Reviewer's activity  6/24/1998
Extension for building permit has been approved till Nov. 30,1998
Plan resubmittals received  1/28/1998 PEND
RECEIVED PLAN RESUBS FORWARDED TO MIKE PHILLIPS.DAR
Plan Reviewer's activity  1/26/1998 FAIL
REQUESTED ADDITIONAL INFORMATION BY PHONE FROM CLINTON. WAITING FOR OUTSIDE ENGINEERING FIRM RESPONSE TO RESUBMITTALS.
Plan resubmittals received  1/16/1998
RECEIVED 3 COPIES REVISED STRUCTURAL PACKAGE 2 COPIES STRUCTURAL CALCULATIONS 3 COPIES REVISED STRUCTURAL PLANS, FOUNDATION 2 COPIES REVIESD ARCHITECTURAL PACKAGE RECEIVED 1 RESPONSE TO PRELIMINARY PLAN REVIEW 2 COPIES OF RESPONSE FROM GREG LEISHMAN. 1 COPIE OF FOUNDATION RESPONSE ROUTED TO MIKE PHILLIPS KMM
Routing Off Site - A.C.H.D10/1/1997 10/14/1997 FAIL
CONTACTED BOB LAMOINE TO TAKE PLANS OUT TO ACHD PACKAGE #4 NOT SIGNED OFF
Routing - FIRE9/30/1997 10/14/1997 PASS
PACKAGE #1
Routing - PLANNING10/1/1997 10/2/1997 PASS
PACKAGE #2 X-REF: CUP97-0034, DRH97-0044. APPROVED BY SAR & TKW.
Routing - PUBLIC WORKS9/18/1997 9/30/1997 PASS
PACKAGE #1
Routing - PLAN CHECK9/22/1997 9/30/1997
PACKAGE #1
Plan resubmittals requested  9/30/1997 FAIL
ARCHITECTURAL AND STRUCTURAL REVIEW REQUIRED. OUTSIDE ENGINEERING FIRM REQUIRES AN ADDITIONAL REVIEW.
Plan Reviewer's activity  9/30/1997 FAIL
1) REQUESTING RESUBMITTALS FOR ARCHITECTURAL AND ENGINEERING. 2) MUST BE REOUTED BACK TO OUTSIDE ENGINEERING FIRM FOR FOLLOW UP REVIEW.
Print Pending Permit.LaserJet4  9/30/1997 FAIL
REQUESTING ADDITIONAL INFORMATION. ROUTE STRUCTURAL SUBMITTALS BACK TO OUT SIDE ENGINEERING FIRM FOR FOLLOW-UP REVIEW.
Plan assigned to (RGG)8/26/1997 9/22/1997 PASS
Routing - FIRE9/12/1997 9/22/1997 PEND
PACKAGE #1 APPROVED FOR GRADING PERMIT ONLY.
Routing Off Site - A.C.H.D8/26/1997 9/22/1997 PEND
PACKAGE #4 CONTACTED BOB LAMOINE AT ###-#### TO TAKE PLANS OUT TO ACHD FOR GRADING ONLY. LETTER SENT BY MARKUS GREEN APPROVING GRADING ONLY.
Routing - PLANNING9/16/1997 9/18/1997 PEND
PACKAGE #2 Approved by: TKW For Grading Only
Routing - PLAN CHECK9/12/1997 9/16/1997 PEND
PACKAGE #2
Routing - PLUMBING9/4/1997 9/12/1997 PASS
PACKAGE #1
Routing Off Site - STRUCTURAL8/26/1997 9/9/1997 FAIL
PACKAGE #3 CONTACTED PDQ TO TAKE PLANS OUT TO ATWOOD FURTHER REVIEW REQUIRED FROM OUT SIDE ENGINEERING FIRM.
Routing - PUBLIC WORKS9/5/1997 9/8/1997 FAIL
package #2 requires street light plan.
Routing - PLAN CHECK9/4/1997 9/5/1997
PACKAGE #2
Routing - ELECTRICAL8/26/1997 9/4/1997 PASS
PACKAGE #1
Routing - PLANNING9/3/1997 9/3/1997 FAIL
PACKAGE #2 X-REF: CUP97-0034,DRH97-0044. REVIEWED/APPROVED FOR HEIGHT EXCEPTION ONLY BY HEARING EXAMINER-PER SAR. PLEASE CONTINUE ROUTING-DR STAFF UNAVAILABLE. SEND BACK TO P&Z AFTER 9/16/97. (SAR/TKW)
Routing - PUBLIC WORKS8/26/1997 8/29/1997 FAIL
PACKAGE #2 INCOMPLETE SITE PLAN, INCOMPLETE LEGAL DESCRIPTION. REQUIRES DRAINAGE PLAN REVISION.
Plans ACCEPTED BY PLAN CHECK  8/26/1997 PASS
Received Certificate of Value  8/26/1997 PASS
Plan routing begun/NEW & ADDTN  8/26/1997 PASS
Routing - MECHANICAL8/26/1997 8/26/1997 PASS
NO REVIEW FIELD VERIFY. PACKAGE #1
Plan assigned to (MYS)8/21/1997 8/26/1997
DetailsMarlene Southard
Application received  8/21/1997
Recd Pcfee & Taken To Pln CK  8/21/1997
Routing Off Site - STRUCTURAL1/21/1998 1/28/1997 PASS
RESUBS SENT TO ATWOOD , HINZMAN, JONES 1/20/98 DAR 1-28-98 RECEIVED A LETTER FROM T. SCOTT ROBERTSON P.E. OF ATWOOD HINZMAN, JONES. ROUTED ORIGINAL TO MARLENE S. GAVE ONE COPY TO MIKE PHILLIPS AND ONE TO FILE. KMM
Routing Off Site - STRUCTURAL1/16/1998 1/28/1997 PASS
REVISED STRUCTURAL SHEETS SENT TO ATWOOD HINZMAN AND JONES received approval leter of outside engineering firm.
SUPER- Supervisor's review5/4/19995/4/1999 
Routing - PLAN CHECK9/9/1997  
PACKAGE #3 BEHIND DAVES DESK. ROUTE TO P&Z AFTER 9-16-97. PER P&Z
Routing - PLAN CHECK10/3/1997  
package 2
Routing - PLAN CHECK10/14/1997  
PACKAGE #1