Fee Review-notes | 7/14/1998 | | 11/19/1998 | | |
|
|
|
|
INSP - Final | 11/4/1998 | 11/5/1998 | 11/5/1998 | A | PASS |
Russ Owen
|
|
|
DOUG--###-#### WESTERN TRAILERS MANUF BLDG
|
Permanent Occupancy | | 11/5/1998 | 11/5/1998 | | DONE |
|
|
|
|
Permanent occupancy | | | 11/5/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7484 issued 11-5-98 to Western Trailers.
|
INSP-Final Inspection | 10/26/1998 | 10/26/1998 | 10/26/1998 | P | PASS |
Rick Jackson
|
|
|
re-inspection for final occ approved
|
INSP - Final | 10/23/1998 | 10/23/1998 | 10/23/1998 | | PART |
Jim Storey
|
|
|
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED ok for 90 day temp.
|
INSP - Final | 10/22/1998 | 10/23/1998 | 10/23/1998 | P | FAIL |
|
|
|
10/23/98 333 - given to jim2 ì
|
INSP-Final Inspection | 10/22/1998 | 10/23/1998 | 10/23/1998 | P | PART |
Rick Jackson
|
|
|
doug ###-#### NFPA 704 for storage area; NFPA 72
|
Code Occupancy Approval | | | 10/20/1998 | | PASS |
|
|
|
ALL IMPROVEMENTS REQUIRED UNDER DR63-96 IN AS REQUIRED, PERMANENT SIGNED OFF FOR CODE ENFORCEMENT.
|
INSP-Final Inspection | 10/14/1998 | 10/15/1998 | 10/15/1998 | A | CANC |
Rick Jackson
|
|
|
MIKE ###-#### PAINT BOOTH inspection was for the paint booth under BLD97-3293
|
INSP - Framing/Rough-in | 10/13/1998 | 10/13/1998 | 10/13/1998 | P | PART |
Russ Owen
|
|
|
10/13/98 407 - cameron ###-#### conference
|
INSP - Final | 9/24/1998 | 9/25/1998 | 9/25/1998 | P | PART |
Russ Owen
|
|
|
09/25/98 407 - This is for a temporary only in the shop area,I have talk and mechanical,an Fire will be out later today,If Fire ok then they may occupy shop only.
|
INSP-Sprinkler Rough-in/Hydro | 9/24/1998 | 9/25/1998 | 9/25/1998 | P | PART |
Rick Jackson
|
|
|
CAMERON ###-#### temp occ approved for remainder of FAB; offices not ready
|
INSP-Final Inspection | 9/22/1998 | 9/23/1998 | 9/23/1998 | P | PART |
Rick Jackson
|
|
|
mike ###-#### tested the office/shop area riser flow switch - okay. not a final occupancy request
|
INSP - Framing/Rough-in | 9/17/1998 | 9/18/1998 | 9/18/1998 | A | PART |
Russ Owen
|
|
|
09/18/98 407 - ok to occupy a portion of shop.
|
INSP-Sprinkler Rough-in/Hydro | 9/17/1998 | 9/18/1998 | 9/18/1998 | A | PART |
Rick Jackson
|
|
|
CAMERON ###-####-FIRST HALF OF MAN BLD-CALL 1ST approval for occ in additional 2 stalls okay. see floor plan ot job site for location. upstairs office area - sprinkler head overspaced; water heater room has no lid - recheck this room
|
INSP - Framing/Rough-in | 9/15/1998 | 9/16/1998 | 9/16/1998 | A | PART |
Russ Owen
|
|
|
09/16/98 407 - left corrections for t-bar .
|
INSP-Sprinkler Rough-in/Hydro | 9/10/1998 | 9/11/1998 | 9/11/1998 | P | PART |
Rick Jackson
|
|
|
DOUG ###-#### partial temp occ inspection - west bays approved only. tested alarms and sprinkler
|
INSP - Framing/Rough-in | 9/10/1998 | 9/11/1998 | 9/11/1998 | P | PART |
Russ Owen
|
|
|
09/11/98 407 - ok to occupie small section at corner as on plan.
|
Code Occupancy Approval | | | 9/10/1998 | | FAIL |
|
|
|
REQUIRED LANDSCAPE AND PARKIN NOT COMPLETED, POSTED BOND WITH CATHY FOR OVER $30,000, TEMPORARY SIGNED OFF.
|
INSP-Sprinkler Rough-in/Hydro | 9/4/1998 | 9/4/1998 | 9/4/1998 | P | PASS |
Rick Jackson
|
|
|
MIKE ###-#### hydro pass
|
INSP - Final | 8/31/1998 | 9/3/1998 | 9/3/1998 | A | FAIL |
|
|
|
09/03/98 335 - ###-#### TEMP OCC 10:00 AS PER INSPECTOR CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP-Final Inspection | 8/31/1998 | 9/3/1998 | 9/3/1998 | A | FAIL |
Rick Jackson
|
|
|
###-#### TEMP OCC 10:00 AS PER INSPECTOR emergency lights, exit lights, sprinkler monitoring, PIV too low
|
INSP-Conference | 8/24/1998 | 8/27/1998 | 8/27/1998 | A | PART |
Rick Jackson
|
|
|
DOUG ###-#### discussed requirements for temp: fusible links for vents to above 286F; extinguishers; emergency lights; sprinkler monitoring; testing alarms; access; etc
|
INSP - Conference | 8/27/1998 | 8/27/1998 | 8/27/1998 | A | PART |
Russ Owen
|
|
|
/ / 407 - meet with owner contractor fire/electrical and others for a
|
INSP-Sprinkler Rough-in/Hydro | 8/24/1998 | 8/24/1998 | 8/24/1998 | P | CANC |
Rick Jackson
|
|
|
mike ###-#### this is for the paint booth
|
INSP-Sprinkler Rough-in/Hydro | 8/19/1998 | 8/20/1998 | 8/20/1998 | A | FAIL |
Rick Jackson
|
|
|
MIKE ###-#### couldn't keep flow going due to hose problems
|
INSP-Supply line flush | 8/20/1998 | 8/20/1998 | 8/20/1998 | P | PASS |
Rick Jackson
|
|
|
reinspect from 8/20 am underground flush okay for paint booth
|
INSP-Sprinkler Rough-in/Hydro | 8/6/1998 | 8/7/1998 | 8/7/1998 | A | PART |
|
|
|
MFG AREA AND 2ND FLOOR OFICE HYDRO OK...CORRECTIONS LEFT FOR ROUGHIN...1ST OFFICE NOT HYDRO. PAINT BOOTH CONNECTED W/O HYDRO. TOLD H/R SUPR THAT FLUSH UG AND PIPING NOW REQ'D
|
INSP-Sprinkler Rough-in/Hydro | 7/15/1998 | 7/20/1998 | 7/20/1998 | A | PART |
Rick Jackson
|
|
|
late a.m. mike ###-#### underground hydro and flush okay. installation of main shop not complete. paint booth requires all inspections (flush, hydros, rouhg-in)
|
(F) Reprint permit | | | 6/1/1998 | | |
|
|
|
|
INSP - Framing/Rough-in | 5/20/1998 | 5/20/1998 | 5/21/1998 | P | PART |
Russ Owen
|
|
|
05/20/98 407 - subject to inspection reports from special inspector.
|
INSP - Framing/Rough-in | 5/18/1998 | 5/19/1998 | 5/19/1998 | A | PASS |
Jim Storey
|
|
|
05/19/98 301 - FRMS-OK FORMS-REBAR 2 ND LIFT OF MASSONARY
|
(F) Reprint permit | | | 5/7/1998 | | |
|
|
|
|
INSP - Concrete | 4/2/1998 | 4/3/1998 | 4/3/1998 | A | PART |
Russ Owen
|
|
|
04/03/98 407 - footins and walls have been poured prior to any city insp indicated MTI special inspector at site before all pours.
|
(F) Reprint permit | | | 2/4/1998 | | |
|
|
|
|
(F) Reprint permit | | | 2/4/1998 | | |
|
|
|
|
FEE REVIEW-NOTES | | | 2/4/1998 | | REFN |
|
|
|
OVERPAYMENT ON PLAN CH
|
Issue PAID IN FULL permit | | | 2/3/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/28/1998 | | PASS |
|
|
|
|
Telephone call | | | 1/28/1998 | | PEND |
|
|
|
told sec the $ amount to let dennis sunberg know
|
Inspection Record Card- Bld | | | 1/28/1998 | | |
|
|
|
|
Print Occupancy Form | | | 1/28/1998 | | |
|
|
|
|
Routing Off Site - A.C.H.D | 1/21/1998 | | 1/27/1998 | | PASS |
|
|
|
RECEIVED LETTER FROM MARCUS GREEN STATING THAT ACHD AND WESTERTN TRAILER HAD AN AGREEMENT ON ACHD FEES AND TO RELEASE BUILDING PERMIT. LETTER ON FILE. DAR 1/28/98
|
Plan assigned to (M_O) | 12/1/1997 | | 1/21/1998 | | PASS |
|
|
|
|
Routing - FIRE | 1/9/1998 | | 1/15/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 1/5/1998 | | |
|
|
|
RECEIVED 2 COP0IES SETS REVISED ARCH. SHEETS. ASL 1.1, AA1.1, AA2.1, AA3.1, AA3.2, AA4.1, AA5.1, AA5.2, AA7.1, AA7.2, AA7.3, AB1.1, AB2.1, AND AB7.1 2 COPIES SETS PLUMB. AND MEC. P1 THRU P4, MS1, AND M1 THRU M5. 2 COPIES ELECTRICAL 1.1,1.2,1.3,2.3,3.1,3.2 AND 4.2. CIVIL DRAWINGS C1.0, C1.1, AND C1.2 2 COPIES OF ITEM RESPONCES TO BLDG. AND FIRE PLAN REVIEW IN LETTER FORM.
|
90 day tracking............. | | 8/25/1997 | 11/23/1997 | | PEND |
|
|
|
|
Routing - FIRE | 11/7/1997 | | 11/17/1997 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 10/2/1997 | | 11/7/1997 | | PASS |
|
|
|
package 1
|
Plan assigned to (RGG) | 8/28/1997 | | 10/31/1997 | | PEND |
|
|
|
|
Routing - PUBLIC WORKS | 10/1/1997 | | 10/2/1997 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/1/1997 | | 10/2/1997 | | PASS |
|
|
|
THREE SETS OF REVISED PLANS TAKEN OUT TO ATWOOD HINZMAN AND JONES VIA PDQ. SENT FOUNDATION DRAWINGS 1,3,4,& 5 COVER LETTER & CALCULATIONS REGARDING STRUCTURAL REVIEW COMMENTS AND GEM REVIEW RESPONSE. RESUBS RETURNED 10/02/97. TO JOHN.
|
Routing - PLAN CHECK | 9/26/1997 | | 10/1/1997 | | FAIL |
|
|
|
PACKAGE #1
|
Routing - FIRE | 9/23/1997 | | 9/29/1997 | | PEND |
|
|
|
APPROVED FOR GRADING PERMIT ONLY.
|
Routing - PLUMBING | 9/19/1997 | | 9/26/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing - ELECTRICAL | 9/26/1997 | | 9/26/1997 | | PASS |
|
|
|
NO REVIEW FIELD VERIFY
|
Routing Off Site - A.C.H.D | 8/28/1997 | | 9/23/1997 | | FAIL |
|
|
|
PAKAGE #2 CONTACTED DENNIS SUNBURG AT ###-#### TO TAKE PLANS OUT TO ACHD.
|
Routing - PLANNING | 9/12/1997 | | 9/18/1997 | | PASS |
|
|
|
Approved by: MGS
|
Plan resubmittals requested | | | 9/12/1997 | | PEND |
|
|
|
FAXED THE ARCHITECT ROCKY TOWLE A COPY OF THE STRUCTURAL ENGINEER'S COMMENT LIST TO FORWARD TO THE PROJECT ENGINEER OF RECORD (PINNACLE). THE REVISIONS ARE SIGNIFICANT ENOUGH THAT ATWOOD-HINZMAN-JONES HAS REQUESTED TO REVIEW REQUIRED RESUBMITTALS.
|
Routing Off Site - STRUCTURAL | 8/28/1997 | | 9/12/1997 | | |
|
|
|
CONTACTED PDQ TO TAKE PLANS OUT TO ATWOOD HINZMAN AND JONES ENGINEERS REQUESTED A SOILS REPORT. I CONTACTED DENNIS SUNBERG AT 343-551 ON 9-9-97 TO LET HIM KNOW OF THIS NEED. 9-10-97 DOUGLAS ZAMZOW BROUGHT SOILS REPORT TO US. CONTACTED PDQ TO TAKE OUT TO ATWOOD HINZMAN AND JONES. KMM COMMENTS RETURNED 09/12/97. DAR.
|
Routing - PUBLIC WORKS | 8/28/1997 | | 9/12/1997 | | FAIL |
|
|
|
PACKAGE #1 RERVISE SITE PLAN TO ELIMINATE REFERENCE TO SEWER WORK ON PRESSURE MAIN. ALL WORK TO BE DONE UNDER DRI 1019
|
Received Certificate of Value | | | 8/28/1997 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/28/1997 | | PASS |
|
|
|
|
Routing - MECHANICAL | 8/28/1997 | | 8/28/1997 | | PASS |
|
|
|
NO REVIEW FIELD VERIFY
|
Plans ACCEPTED BY PLAN CHECK | | | 8/28/1997 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 8/25/1997 | | 8/28/1997 | | |
Marlene Southard
|
|
|
|
Application received | | | 8/25/1997 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/25/1997 | | |
|
|
|
|
Routing Off Site - A.C.H.D | 10/7/1997 | | 10/9/1909 | | PASS |
|
|
|
CONTACTED DENNIS SUNBERG AT ###-#### TO TAKE PLANS BACK OUT TO ACHD. PACKAGE #2 NO FEES DUE PER MARCUS GREEN
|