Permit Information
Permit NumberBLD97-02517
StatusFinaled
Name BURGER KING
Site Address 8378 W OVERLAND RD
Project NameBURGER KING
Customer Number 
ePlanReviewNo
Description
BURGER KING * TO CONSTRUCT A NEW 4673 SQ. FT. TYPE VN DRIVE THRU RESTAURANT WITH INDOOR PLAYGROUND. CU#13-97 PC#560-97 NOTE: ADDED 617 SQ. FT. TO THE BUILDING BY PLAN MODIFICATION APPROVED ON 1-08-99.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Routing - PLAN CHECK12/8/1998 12/8/1999 PASS
PLAN MODIFICATION COMPLETED AND APPROVED. MLO
Permanent occupancy  4/29/1999 PASS
Perm. Occ. Cert. #7754 issued 4-29-99 to Burger King.
Permanent Occupancy 4/22/19994/22/1999 DONE
Details
INSP - Final4/21/19994/22/19994/22/1999PPASS
DetailsCarl Dependahl
04/22/99 340 - Final reinspect, Steve, ###-####
INSP-Final Inspection4/15/19994/15/19994/15/1999PPASS
DetailsJoe Tawney
04/15/99 406 - Steve ###-#### REINSP OK FOR PERM OCC
Receive PAYMENT IN FULL PRINT  4/15/1999
Code Occupancy Approval  3/30/1999
Final requested by: Steve ###-####.
INSP - Final3/29/19993/29/19993/29/1999 FAIL
DetailsJoe Tawney
/ / 406 - REINSP FAIL OCC LOAD SIGNS
INSP - Final3/26/19993/29/19993/29/1999AFAIL
DetailsCarl Dependahl
03/29/99 340 - ###-#### STEVE//FINAL FOR OCCUPY keep cn
INSP - Final3/29/19993/29/19993/29/1999 FAIL
DetailsJoe Tawney
/ / 406 - REINSP FAIL OCC LOAD SIGNS
CHANGE STATUS TO (F)  3/22/1999
ADDITIONAL VALUE
INSP - Final3/2/19993/2/19993/2/1999PFAIL
DetailsCarl Dependahl
new card generated??? discussed w/ Cathy W. ok for t/o if all other agencies ok.
Temporary occupancy  3/2/1999 PASS
Temp. Occ. Cert. #3790 issued 3-2-99 to Burger King.
INSP - Final3/1/19993/1/19993/1/1999PFAIL
DetailsCarl Dependahl
03/01/99 340 - need card onsite, draft stop, temp windows, etc. has t/o
INSP-Final Inspection2/25/19992/26/19992/26/1999APART
Details
burger king\\\joe ###-#### temp occupancy approved. need hood balance, occ load signs, assembly permit
Code Occupancy Approval  2/26/1999 FAIL
OCCUPANCY INSPECTION MADE- EVERYTHING OK EXCEPT LANDSCAPING - THEY WILL BOND FOR TEMPORARY - AMOUNT IS $28,580.00.
INSP - Framing/Rough-in2/19/19992/22/19992/22/1999APART
DetailsBob Archibald
ceiling grid joe ###-####. Approved placement of tiles, leave a few out for inspection at a later time.
INSP - Framing/Rough-in2/16/19992/16/19992/16/1999PPART
DetailsCarl Dependahl
02/16/99 340 - ###-#### ###-#### pager conf. ok to continue, need grid i
Fee Review-notes11/2/1998 1/27/1999
INSP - Framing/Rough-in1/20/19991/21/19991/21/1999AFAIL
DetailsJim Storey
01/21/99 301 - joe- ###-#### fire stop insp-re-insp fire blocking ok sha
INSP - Framing/Rough-in1/19/19991/19/19991/19/1999PPART
DetailsJim Storey
01/19/99 301 - c/n on site ok to start gyp and insulation. not to cover
Receive PAYMENT IN FULL PRINT  1/12/1999
(F) Reprint permit  1/11/1999
Telephone call  1/11/1999
called plan modification ready left message
Plan Reviewer's activity  1/8/1999 PASS
PLAN MODIFICATION SENT TO FRONT DESK. MLO
Plan resubmittals received  1/7/1999 PEND
RECEIVED RESUBMITTALS FROM BRIGGS ENGINEERING VIA BRS, FORWARDED SAME TO MIKE OTTO. DAR 1/7/99
INSP - Framing/Rough-in1/7/19991/8/19991/6/1999PPART
Details
01/08/99 338 - made ok to ijns only
INSP - Framing/Rough-in12/15/199812/16/199812/16/1998PPART
Details
12/16/98 338 - made ok with sp insp approval
Plan resubmittals requested  12/16/1998
RECEIVED TWO SHEETS OF REVISED S1.1, AND S2.0 AND ROUTED TO PERRY P. KMM
Routing - PLANNING12/1/199812/7/199812/8/1998 PASS
Approved per DRH97-0188 (CUP97-0013 APPROVED. CONDITIONS OF APROVAL PER ATTACHED TO SITE PLAN).
Routing - PUBLIC WORKS11/30/1998 12/1/1998 PASS
PLAN MODIFICATION SENT TO PW AT MIKE OTTOS DIRECTION.DAR
CHANGE STATUS TO (I)  11/30/1998
CHANGE STATUS TO (P)  11/24/1998 PASS
took in plan modification
INSP - Foundation11/17/199811/17/199811/17/1998PPART
Details
11/17/98 338 - MADE OK WITH SP INSP APPROVAL
INSP - Foundation11/12/199811/13/199811/13/1998APART
Details
11/13/98 338 - made ok for footing only sp insp on site per owner
(F) Reprint permit  10/27/1998
Issue PAID IN FULL permit  10/26/1998
PLANS/APPL TAKEN TO FRONT DESK  9/29/1998 PASS
PLAN MODIFICATION SENT TO FRONT DESK ON 01-08-99. MLO
Inspection Record Card- Bld  9/29/1998
Print Occupancy Form  9/29/1998
Plan assigned to (MLO)11/3/1997 9/29/1998 PASS
DetailsMike Otto
09/29/98 13:27:49 MLO - this action updated by action script from <<>> in Case No. BLD97-2517
Routing - PUBLIC WORKS9/21/1998 9/28/1998 PASS
Telephone call  7/21/1998 PEND
PUT CALL INTO KYLE FREUTEL AT BRS ARCHITECTS TO FIND OUT STATUS OF NEW PLAT. RELAYED TO FREUTEL THAT PERMIT NEEDS TO BE ISSUED PRIOR TO CODE CHANGE. MLO
Plan Reviewer's activity  6/15/1998 PEND
RECEIVED LETTER FROM BRS ARCHITECTS REQUESTING EXTENSION ON APPLICATION. LETTER STATES THAT ILLEGAL LAND DIVISION HAS BEEN REASON FOR DELAY. MLO.
180 day tracking............. 8/27/19972/23/1998 PEND
90 day tracking............. 8/27/199711/25/1997
Routing - PLAN CHECK11/18/1997 11/25/1997 PASS
still need architect of record. Faxed form to architect 11-25-97. MO Architect of record form received on 11-28-97. MO
Plan resubmittals received  11/18/1997 PEND
RESUBMITTALS FOR BUILDING PLAN REVIEW COMMENTS. MO
Routing - FIRE11/5/1997 11/13/1997 PASS
PACKAGE #1
Routing - PLAN CHECK11/3/1997 11/5/1997 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MO
Plan resubmittals requested  11/5/1997 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MO
Plan assigned to (RGG)8/29/1997 11/3/1997 PASS
Routing - PLUMBING10/5/1997 10/6/1997 PASS
PACKAGE #1 ROUTE TO PLUMBING WITH PACKAGE #2 WHEN #2 IS BACK FROM P.W. PACKAGES 1&2 TO PLUMBING 10/5/97 DAR
Routing - PLANNING9/23/1997 10/2/1997 PASS
PACKAGE #2 CU Approved by: SAR DR Approved by: TKW
Routing Off Site - STRUCTURAL9/19/1997 9/26/1997 PASS
REVISED PLANS SENT OUT TO ATWOOD HINZMAN AND JONES VIA PDQ
Routing - PUBLIC WORKS9/19/1997 9/23/1997 FAIL
PACKAGE #2 INCOMPLETE SITE PLANS.
Routing Off Site - C.D.H8/29/1997 9/18/1997 PASS
CONTACTED KYLE FRUETEL AT ###-#### TO TAKE PLANS OUT TO CDH PACKAGE #2
Routing - ELECTRICAL8/29/1997 9/15/1997 PASS
PACKAGE #1 NO REVIEW FIELD VERIFY.
Plan resubmittals requested  9/12/1997 PEND
FAXED KYLE FREUTEL AT BRS WITH A COPY OF THE STRUCTURAL REVIEW COMMENTS FROM ATWOOD-HINZMAN-JONES - THE CONSULTING ENGINEER HAS INDICATED THAT THE REVISIONS REQUESTED ARE SIGNIFICANT ENOUGH THAT THEY WOULD LIKE TO REVIEW THE RESUBMITTED ENGINEERING.
Routing Off Site - STRUCTURAL8/29/1997 9/12/1997 FAIL
CONTACTED PDQ TO TAKE PLANS OUT TO ATWOOD HINZMAN AND JONES.
Plans ACCEPTED BY PLAN CHECK  8/29/1997 PASS
Routing - MECHANICAL8/29/1997 8/29/1997 PASS
PACKAGE #1 NO REVIEW FIELD VERIFY
Plan routing begun/NEW & ADDTN  8/29/1997 PASS
Received Certificate of Value  8/29/1997 PASS
Plan assigned to (MYS)8/27/1997 8/29/1997
DetailsMarlene Southard
Recd Pcfee & Taken To Pln CK  8/27/1997
Application received  8/26/1997
Routing Off Site - A.C.H.D8/29/1997  
CONTACTED KYLE FREUTEL AT ###-#### TO TAKE PLANS OUT TO ACHD