Routing - PLAN CHECK | 12/8/1998 | | 12/8/1999 | | PASS |
|
|
|
PLAN MODIFICATION COMPLETED AND APPROVED. MLO
|
Permanent occupancy | | | 4/29/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7754 issued 4-29-99 to Burger King.
|
Permanent Occupancy | | 4/22/1999 | 4/22/1999 | | DONE |
|
|
|
|
INSP - Final | 4/21/1999 | 4/22/1999 | 4/22/1999 | P | PASS |
Carl Dependahl
|
|
|
04/22/99 340 - Final reinspect, Steve, ###-####
|
INSP-Final Inspection | 4/15/1999 | 4/15/1999 | 4/15/1999 | P | PASS |
Joe Tawney
|
|
|
04/15/99 406 - Steve ###-#### REINSP OK FOR PERM OCC
|
Receive PAYMENT IN FULL PRINT | | | 4/15/1999 | | |
|
|
|
|
Code Occupancy Approval | | | 3/30/1999 | | |
|
|
|
Final requested by: Steve ###-####.
|
INSP - Final | 3/29/1999 | 3/29/1999 | 3/29/1999 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - REINSP FAIL OCC LOAD SIGNS
|
INSP - Final | 3/26/1999 | 3/29/1999 | 3/29/1999 | A | FAIL |
Carl Dependahl
|
|
|
03/29/99 340 - ###-#### STEVE//FINAL FOR OCCUPY keep cn
|
INSP - Final | 3/29/1999 | 3/29/1999 | 3/29/1999 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - REINSP FAIL OCC LOAD SIGNS
|
CHANGE STATUS TO (F) | | | 3/22/1999 | | |
|
|
|
ADDITIONAL VALUE
|
INSP - Final | 3/2/1999 | 3/2/1999 | 3/2/1999 | P | FAIL |
Carl Dependahl
|
|
|
new card generated??? discussed w/ Cathy W. ok for t/o if all other agencies ok.
|
Temporary occupancy | | | 3/2/1999 | | PASS |
|
|
|
Temp. Occ. Cert. #3790 issued 3-2-99 to Burger King.
|
INSP - Final | 3/1/1999 | 3/1/1999 | 3/1/1999 | P | FAIL |
Carl Dependahl
|
|
|
03/01/99 340 - need card onsite, draft stop, temp windows, etc. has t/o
|
INSP-Final Inspection | 2/25/1999 | 2/26/1999 | 2/26/1999 | A | PART |
|
|
|
burger king\\\joe ###-#### temp occupancy approved. need hood balance, occ load signs, assembly permit
|
Code Occupancy Approval | | | 2/26/1999 | | FAIL |
|
|
|
OCCUPANCY INSPECTION MADE- EVERYTHING OK EXCEPT LANDSCAPING - THEY WILL BOND FOR TEMPORARY - AMOUNT IS $28,580.00.
|
INSP - Framing/Rough-in | 2/19/1999 | 2/22/1999 | 2/22/1999 | A | PART |
Bob Archibald
|
|
|
ceiling grid joe ###-####. Approved placement of tiles, leave a few out for inspection at a later time.
|
INSP - Framing/Rough-in | 2/16/1999 | 2/16/1999 | 2/16/1999 | P | PART |
Carl Dependahl
|
|
|
02/16/99 340 - ###-#### ###-#### pager conf. ok to continue, need grid i
|
Fee Review-notes | 11/2/1998 | | 1/27/1999 | | |
|
|
|
|
INSP - Framing/Rough-in | 1/20/1999 | 1/21/1999 | 1/21/1999 | A | FAIL |
Jim Storey
|
|
|
01/21/99 301 - joe- ###-#### fire stop insp-re-insp fire blocking ok sha
|
INSP - Framing/Rough-in | 1/19/1999 | 1/19/1999 | 1/19/1999 | P | PART |
Jim Storey
|
|
|
01/19/99 301 - c/n on site ok to start gyp and insulation. not to cover
|
Receive PAYMENT IN FULL PRINT | | | 1/12/1999 | | |
|
|
|
|
(F) Reprint permit | | | 1/11/1999 | | |
|
|
|
|
Telephone call | | | 1/11/1999 | | |
|
|
|
called plan modification ready left message
|
Plan Reviewer's activity | | | 1/8/1999 | | PASS |
|
|
|
PLAN MODIFICATION SENT TO FRONT DESK. MLO
|
Plan resubmittals received | | | 1/7/1999 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM BRIGGS ENGINEERING VIA BRS, FORWARDED SAME TO MIKE OTTO. DAR 1/7/99
|
INSP - Framing/Rough-in | 1/7/1999 | 1/8/1999 | 1/6/1999 | P | PART |
|
|
|
01/08/99 338 - made ok to ijns only
|
INSP - Framing/Rough-in | 12/15/1998 | 12/16/1998 | 12/16/1998 | P | PART |
|
|
|
12/16/98 338 - made ok with sp insp approval
|
Plan resubmittals requested | | | 12/16/1998 | | |
|
|
|
RECEIVED TWO SHEETS OF REVISED S1.1, AND S2.0 AND ROUTED TO PERRY P. KMM
|
Routing - PLANNING | 12/1/1998 | 12/7/1998 | 12/8/1998 | | PASS |
|
|
|
Approved per DRH97-0188 (CUP97-0013 APPROVED. CONDITIONS OF APROVAL PER ATTACHED TO SITE PLAN).
|
Routing - PUBLIC WORKS | 11/30/1998 | | 12/1/1998 | | PASS |
|
|
|
PLAN MODIFICATION SENT TO PW AT MIKE OTTOS DIRECTION.DAR
|
CHANGE STATUS TO (I) | | | 11/30/1998 | | |
|
|
|
|
CHANGE STATUS TO (P) | | | 11/24/1998 | | PASS |
|
|
|
took in plan modification
|
INSP - Foundation | 11/17/1998 | 11/17/1998 | 11/17/1998 | P | PART |
|
|
|
11/17/98 338 - MADE OK WITH SP INSP APPROVAL
|
INSP - Foundation | 11/12/1998 | 11/13/1998 | 11/13/1998 | A | PART |
|
|
|
11/13/98 338 - made ok for footing only sp insp on site per owner
|
(F) Reprint permit | | | 10/27/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/26/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/29/1998 | | PASS |
|
|
|
PLAN MODIFICATION SENT TO FRONT DESK ON 01-08-99. MLO
|
Inspection Record Card- Bld | | | 9/29/1998 | | |
|
|
|
|
Print Occupancy Form | | | 9/29/1998 | | |
|
|
|
|
Plan assigned to (MLO) | 11/3/1997 | | 9/29/1998 | | PASS |
Mike Otto
|
|
|
09/29/98 13:27:49 MLO - this action updated by action script from <<>> in Case No. BLD97-2517
|
Routing - PUBLIC WORKS | 9/21/1998 | | 9/28/1998 | | PASS |
|
|
|
|
Telephone call | | | 7/21/1998 | | PEND |
|
|
|
PUT CALL INTO KYLE FREUTEL AT BRS ARCHITECTS TO FIND OUT STATUS OF NEW PLAT. RELAYED TO FREUTEL THAT PERMIT NEEDS TO BE ISSUED PRIOR TO CODE CHANGE. MLO
|
Plan Reviewer's activity | | | 6/15/1998 | | PEND |
|
|
|
RECEIVED LETTER FROM BRS ARCHITECTS REQUESTING EXTENSION ON APPLICATION. LETTER STATES THAT ILLEGAL LAND DIVISION HAS BEEN REASON FOR DELAY. MLO.
|
180 day tracking............. | | 8/27/1997 | 2/23/1998 | | PEND |
|
|
|
|
90 day tracking............. | | 8/27/1997 | 11/25/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 11/18/1997 | | 11/25/1997 | | PASS |
|
|
|
still need architect of record. Faxed form to architect 11-25-97. MO Architect of record form received on 11-28-97. MO
|
Plan resubmittals received | | | 11/18/1997 | | PEND |
|
|
|
RESUBMITTALS FOR BUILDING PLAN REVIEW COMMENTS. MO
|
Routing - FIRE | 11/5/1997 | | 11/13/1997 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLAN CHECK | 11/3/1997 | | 11/5/1997 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MO
|
Plan resubmittals requested | | | 11/5/1997 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MO
|
Plan assigned to (RGG) | 8/29/1997 | | 11/3/1997 | | PASS |
|
|
|
|
Routing - PLUMBING | 10/5/1997 | | 10/6/1997 | | PASS |
|
|
|
PACKAGE #1 ROUTE TO PLUMBING WITH PACKAGE #2 WHEN #2 IS BACK FROM P.W. PACKAGES 1&2 TO PLUMBING 10/5/97 DAR
|
Routing - PLANNING | 9/23/1997 | | 10/2/1997 | | PASS |
|
|
|
PACKAGE #2 CU Approved by: SAR DR Approved by: TKW
|
Routing Off Site - STRUCTURAL | 9/19/1997 | | 9/26/1997 | | PASS |
|
|
|
REVISED PLANS SENT OUT TO ATWOOD HINZMAN AND JONES VIA PDQ
|
Routing - PUBLIC WORKS | 9/19/1997 | | 9/23/1997 | | FAIL |
|
|
|
PACKAGE #2 INCOMPLETE SITE PLANS.
|
Routing Off Site - C.D.H | 8/29/1997 | | 9/18/1997 | | PASS |
|
|
|
CONTACTED KYLE FRUETEL AT ###-#### TO TAKE PLANS OUT TO CDH PACKAGE #2
|
Routing - ELECTRICAL | 8/29/1997 | | 9/15/1997 | | PASS |
|
|
|
PACKAGE #1 NO REVIEW FIELD VERIFY.
|
Plan resubmittals requested | | | 9/12/1997 | | PEND |
|
|
|
FAXED KYLE FREUTEL AT BRS WITH A COPY OF THE STRUCTURAL REVIEW COMMENTS FROM ATWOOD-HINZMAN-JONES - THE CONSULTING ENGINEER HAS INDICATED THAT THE REVISIONS REQUESTED ARE SIGNIFICANT ENOUGH THAT THEY WOULD LIKE TO REVIEW THE RESUBMITTED ENGINEERING.
|
Routing Off Site - STRUCTURAL | 8/29/1997 | | 9/12/1997 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE PLANS OUT TO ATWOOD HINZMAN AND JONES.
|
Plans ACCEPTED BY PLAN CHECK | | | 8/29/1997 | | PASS |
|
|
|
|
Routing - MECHANICAL | 8/29/1997 | | 8/29/1997 | | PASS |
|
|
|
PACKAGE #1 NO REVIEW FIELD VERIFY
|
Plan routing begun/NEW & ADDTN | | | 8/29/1997 | | PASS |
|
|
|
|
Received Certificate of Value | | | 8/29/1997 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 8/27/1997 | | 8/29/1997 | | |
Marlene Southard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/27/1997 | | |
|
|
|
|
Application received | | | 8/26/1997 | | |
|
|
|
|
Routing Off Site - A.C.H.D | 8/29/1997 | | | | |
|
|
|
CONTACTED KYLE FREUTEL AT ###-#### TO TAKE PLANS OUT TO ACHD
|