Case Summary (BLD) | | | 1/26/2009 | | |
|
|
|
|
Plan Review Report | | | 5/16/2007 | | |
|
|
|
|
Case Summary (BLD) | | | 5/16/2007 | | |
|
|
|
|
Expired/Cancelled | | | 8/18/2003 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/6/2001 | 7/6/2001 | 7/6/2001 | P | NR |
Rick Jackson
|
|
|
###-#### talked to Jack of Mtn Alarm and they won't be ready until 7/9. 7/6/2001 2:51:11 PM
|
BLD-Conference | 4/20/2001 | 4/20/2001 | 4/20/2001 | | PASS |
George Slane
|
|
|
Up date related to the meeting with Ron Thurber, gs, carl dependahl. Originally this building was to complete the installation of a sprinkler system and basement finish, The contractor doing the job and the owner were in a court dispute legal action was in progress. We gave a temp based on life safety and were working with owner to keep establishment open until litigation was completed and we could finish work in basement. The litigation is now completed and the owner has hired Ron Thurber to develope plan for completion. Once approved we could issue C/o on main areas and carry basement as a separate issue of remodel. This has been a long time comming to resolve but seemed in the best interest to work with courts decrees.At no time was life safety an issue.
|
BLD-Conference | 4/12/2001 | 4/12/2001 | 4/12/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 4/12/2001 5:08:00 PM w/ owner, GS & Ron Thurber at site: Submit new plans for t/i at bsmt.
|
(F) Reprint permit | | | 4/12/2001 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 4/12/2001 | | DONE |
|
|
|
|
Plan Review Report | | | 4/4/2001 | | |
|
|
|
|
Print Occupancy Form | | | 10/24/2000 | | DONE |
|
|
|
|
SUPER- Supervisor's review | 7/7/1999 | 7/7/1999 | 7/7/1999 | | |
|
|
|
still on temp. perry to review and update work still going on
|
Received partial PAYMENT | | | 2/19/1999 | | |
|
|
|
|
Received partial PAYMENT | | | 1/22/1999 | | |
|
|
|
|
Fee Review-notes | 9/25/1998 | | 10/1/1998 | | DONE |
|
|
|
|
INSP - Final | 8/17/1998 | 8/17/1998 | 8/17/1998 | | PART |
|
|
|
/ / 333 - GAVE LETTER TO TERRY
|
INSP - Foundation | 6/29/1998 | 6/29/1998 | 6/29/1998 | | PART |
|
|
|
/ / 333 - SECON POUR STAIR TOWERS
|
INSP - Foundation | 6/18/1998 | 6/18/1998 | 6/18/1998 | | PART |
|
|
|
/ / 333 - ELEVATOR SHAFTS IN PROGRESS
|
INSP - Foundation | 6/15/1998 | 6/15/1998 | 6/15/1998 | | PART |
|
|
|
/ / 333 - STEEL OK ELEVATOR SHAFTS
|
INSP - Foundation | 6/8/1998 | 6/8/1998 | 6/8/1998 | | PART |
|
|
|
/ / 333 - GRADE BEAMS IN PROGRESS
|
INSP - Concrete | 6/3/1998 | 6/3/1998 | 6/3/1998 | P | PART |
|
|
|
06/03/98 333 - basement footings ok
|
INSP - Foundation | 5/27/1998 | 5/27/1998 | 5/27/1998 | | PART |
|
|
|
/ / 333 - SOUTH EAST CORNER OK
|
INSP - Foundation | 5/26/1998 | 5/26/1998 | 5/26/1998 | | PART |
|
|
|
/ / 333 - SOUTHEAST SIDE STEEEL OK
|
INSP - Foundation | 5/19/1998 | 5/19/1998 | 5/19/1998 | | PART |
|
|
|
/ / 333 - STEEL NORTH WEST OK
|
INSP - Foundation | 5/15/1998 | 5/15/1998 | 5/15/1998 | | PART |
|
|
|
/ / 333 - southwest corner ok
|
INSP - Final | 5/14/1998 | 5/14/1998 | 5/14/1998 | | PART |
|
|
|
/ / 333 - TO OK
|
INSP - Foundation | 5/14/1998 | 5/14/1998 | 5/14/1998 | | PART |
|
|
|
/ / 333 - SOUTHEAST WALL OK PEND SP INS REPORT
|
Temporary occupancy | | | 5/14/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3618 issued 5-14-98 to Joe's All American.
|
INSP - Final | 5/13/1998 | 5/13/1998 | 5/13/1998 | | PART |
|
|
|
/ / 333 - CN PLACED
|
INSP - Foundation | 5/13/1998 | 5/13/1998 | 5/13/1998 | | PART |
|
|
|
/ / 333 - SOUTH WEST SIDE OK PENDING SPECIAL INSP REPORT
|
INSP-Sprinkler Rough-in/Hydro | 5/11/1998 | 5/12/1998 | 5/12/1998 | A | FAIL |
Rick Jackson
|
|
|
c/n issued. too many items to list.
|
INSP - Foundation | 5/12/1998 | 5/12/1998 | 5/12/1998 | P | PART |
|
|
|
05/12/98 333 - wrong insp
|
INSP - Framing/Rough-in | 5/11/1998 | 5/11/1998 | 5/11/1998 | P | PASS |
|
|
|
05/11/98 333 - last of frame ok
|
INSP - Foundation | 5/8/1998 | 5/8/1998 | 5/8/1998 | | PART |
|
|
|
/ / 333 - SOUTH WEST OK PEND SPEC INSP REPORTS
|
INSP - Foundation | 5/5/1998 | 5/5/1998 | 5/5/1998 | | PART |
|
|
|
/ / 333 - DELIVERED APPROVED RESUB ON FOOTING
|
INSP - Foundation | 5/1/1998 | 5/1/1998 | 5/1/1998 | | PART |
|
|
|
/ / 333 - OK PENDING SPECIAL INSP REPORTS
|
INSP - Foundation | 4/30/1998 | 4/30/1998 | 4/30/1998 | | FAIL |
|
|
|
/ / 333 - REVIEW OF CHANGE IN PLAN
|
INSP - Foundation | 4/27/1998 | 4/27/1998 | 4/27/1998 | | PART |
|
|
|
/ / 333 - PRE CON
|
INSP - Framing/Rough-in | 4/22/1998 | 4/23/1998 | 4/23/1998 | A | FAIL |
Jim Storey
|
|
|
04/23/98 301 - kim already performed insp
|
INSP - Wall cover | 4/20/1998 | 4/20/1998 | 4/20/1998 | | PART |
|
|
|
/ / 333 - conference with Ottis Lemmon
|
INSP - Foundation | 4/16/1998 | 4/16/1998 | 4/16/1998 | A | PASS |
|
|
|
04/16/98 333 - footing ok
|
INSP - Foundation | 4/15/1998 | 4/15/1998 | 4/15/1998 | | PART |
|
|
|
/ / 333 - CONF ON PRE CON TIME
|
INSP - Conference | 4/14/1998 | 4/14/1998 | 4/14/1998 | | PASS |
|
|
|
/ / 333 - CHANGED PRECON MEETING DATE
|
INSP - Framing/Rough-in | 4/14/1998 | 4/14/1998 | 4/14/1998 | P | PART |
|
|
|
04/14/98 333 - progress ok
|
INSP - Framing/Rough-in | 3/30/1998 | 3/30/1998 | 3/30/1998 | P | PART |
|
|
|
03/30/98 333 - floor fill okbob ###-####
|
INSP - Framing/Rough-in | 3/23/1998 | 3/24/1998 | 3/24/1998 | A | PASS |
|
|
|
03/24/98 333 - steel ok pending engineers review
|
INSP - Foundation | 3/17/1998 | 3/18/1998 | 3/18/1998 | A | PASS |
|
|
|
03/18/98 333 - pour ok
|
INSP - Foundation | 3/4/1998 | 3/4/1998 | 3/4/1998 | P | PASS |
|
|
|
03/04/98 333 - FTG -OK FOOTING
|
INSP - Foundation | 2/25/1998 | 2/25/1998 | 2/25/1998 | P | PART |
|
|
|
02/25/98 333 - FRMS-OK FORMS-REBAR
|
INSP - Foundation | 2/20/1998 | 2/23/1998 | 2/23/1998 | A | PASS |
|
|
|
02/23/98 333 - FDN -OK FOUNDATION
|
INSP - Concrete | 2/20/1998 | 2/23/1998 | 2/23/1998 | A | PASS |
|
|
|
02/23/98 333 - FDN -OK FOUNDATION
|
INSP - Foundation | 2/19/1998 | 2/19/1998 | 2/19/1998 | P | PART |
|
|
|
02/19/98 333 - SCHEDULED WITH YOU FOR 1:00--ROBERT ###-####
|
Routing Off Site - STRUCTURAL | 2/3/1998 | | 2/3/1998 | | |
|
|
|
RECEIVED 1 COPY OF WAREHOUSE ADDITION FOR POWER BAR INC. STRUCTURAL REVIEW LETTER BY CH2MHILL DATED 2-2-98. ROUTED TO CARL W. KMM
|
Issue PAID IN FULL permit | | | 1/30/1998 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 1/13/1998 | | 1/29/1998 | | PASS |
|
|
|
SENT RESUB TO CH2MHILL RESUBS RECEIVED FROM CH2MHILL 1/29/98.DAR
|
testing condition printout | | | 1/29/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/29/1998 | | PASS |
|
|
|
Drawings approved, with conditions, as noted and attached to the approved drawings.
|
Print permit w/o conditions | | | 1/29/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/29/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/29/1998 | | |
|
|
|
|
Plan Reviewer's activity | | | 1/29/1998 | | PASS |
|
|
|
Drawings approved, with conditions, as noted and attached to the approved drawings.
|
Print Occupancy Form | | | 1/29/1998 | | |
|
|
|
|
Plan assigned to (CJW) | 9/8/1997 | | 1/29/1998 | | PASS |
Carl Westfall
|
|
|
01/29/98 14:43:29 CJW - this action updated by action script from <<>> in Case No. BLD97-2548
|
Plan resubmittals received | | | 1/12/1998 | | |
|
|
|
Engineer's details and calculations addressing the added roof top units received. Door schedule received.
|
INSP - Foundation | 2/10/1998 | 2/11/1998 | 1/11/1998 | A | PASS |
|
|
|
02/11/98 333 - FRMS-OK FORMS-REBAR
|
Telephone call | | | 1/8/1998 | | |
|
|
|
Called Trey Hoff asking him to provide a door schedule and a roof analysis addressing the added weight from the RTUs.
|
Plan resubmittals received | | | 1/6/1998 | | |
|
|
|
RECEIVED 2 COPIES OF CHANGE ORDER NO. 1 2 COPIES OF REPRODUCIBLE STRUCTURAL SHEETS S-1 THROUGH S-11; REVISED TO DATE. 2 COPIES OF SUPPLEMENTAL STRUCTURAL DESIGN CALCULATIONS; SUP-1 THROUGH SUP-5 2 COPIES OF RESPONSES TO THE STRUCTURAL ENGINEERING DESIGN REVIEW COMMENTS FROM THE CITY DATED 11-3-97 ROUTED TO CARL W. KMM
|
Plan resubmittals received | | | 1/6/1998 | | |
|
|
|
Resubmitted drawings addressed most items on the plan review report. Waiting for a door schedule and for a roof analysis addressing the added weight from the new RTUs.
|
90 day tracking............. | | 8/28/1997 | 11/26/1997 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/23/1997 | | 11/4/1997 | | |
|
|
|
CONTACTED PDQ TO TAKE PLANS OUT TO CH2MHILL PER CARL W. RECEIVED FROM CH2MHILL STRUCTURAL REVIEW LETTER BY CH2MHILL DATED 11-03-97. GAVE TO CARL W. KMM 11-04-97
|
Routing Off Site - STRUCTURAL | 10/23/1997 | | 11/3/1997 | | |
|
|
|
First structural review done. Copy faxed to the Architect of Nov. 5, 1997. The consultant engineer requested written responses to 8 items.
|
Meeting | | | 10/30/1997 | | |
|
|
|
Meet with Trey Hoff and went over each item on my plan check report. He was given a copy of the complete report.
|
Plan Reviewer's activity | | | 10/14/1997 | | |
|
|
|
UBC plan check started October 14, 1997 and finished October 29, 1997. Several item require a response. See conditions list.
|
Routing - PLANNING | 10/9/1997 | | 10/9/1997 | | PASS |
|
|
|
X-REF: DRH97-0165. NOTE: REDLINED ON PAGE A 5.1. APPROVED BY TLC.
|
Routing - PLUMBING | 10/6/1997 | | 10/7/1997 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/22/1997 | | 10/6/1997 | | PASS |
|
|
|
|
(F) Reprint permit | | | 10/3/1997 | | |
|
|
|
|
Routing Off Site - C.D.H | 9/19/1997 | | 9/22/1997 | | PASS |
|
|
|
|
Routing Off Site - A.C.H.D | 9/8/1997 | | 9/19/1997 | | PASS |
|
|
|
NO ACHD FEES DUE.
|
Routing - PLAN CHECK | 9/4/1997 | | 9/8/1997 | | |
|
|
|
Prepared a demo permit and started routing.
|
Plan routing begun/TENANTS | | | 9/8/1997 | | |
|
|
|
This plan to route to ADA COUNTY HIGHWAY DISTRICT, CENTRAL DISTRICT HEALTH, PUBLIC WORKS, PLUMBING, PLANNING then to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT.
|
Plans ACCEPTED BY PLAN CHECK | | | 9/4/1997 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 9/4/1997 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 8/28/1997 | | 9/4/1997 | | |
Marlene Southard
|
|
|
|
Received Certificate of Value | | | 9/4/1997 | | PASS |
|
|
|
|
Application received | | | 8/28/1997 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/28/1997 | | |
|
|
|
|
Routing - FIRE | 10/31/1997 | | 11/12/1917 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/13/1997 | | | | |
|
|
|
|